This is a Quality Assurance Surveillance Plan (QASP) for the NAVSUP FLCJ Gulfport Material Handling Equipment (MHE) Maintenance Contract. The QASP establishes the Government's methodology for monitoring and evaluating contractor performance in maintaining material handling equipment, specifically forklifts, in accordance with the Performance Work Statement, OEM standards, and industry best practices. The plan defines surveillance procedures, performance standards, and acceptable quality levels to ensure services meet contractual requirements and support mission readiness.
The QASP identifies seven key performance objectives with measurable standards and corresponding quality acceptance levels: Preventive Maintenance must be completed on-time 95% of the time per OEM standards; Corrective Maintenance repairs must be completed within OEM time plus two hours of troubleshooting with 95% compliance; Response Time requires 100% compliance in responding to service calls within one business day; Parts Standards mandate 100% compliance using new or like-new OEM-specification parts; Safety/Environmental Compliance requires 100% adherence to Navy, OSHA, and environmental regulations; Recordkeeping must achieve 100% accuracy and completeness; and Equipment Availability must maintain at least 90% forklift fleet availability. Surveillance methods include random inspections, periodic inspections, 100% inspection of critical safety tasks, customer feedback, and records review. The Government will enforce performance through incentives—recognizing satisfactory performance in future past performance evaluations—and remedies including corrective action at no cost to the Government, cure notices, payment withholding, and potential termination for default. The Contracting Officer's Representative documents all surveillance results and immediately reports safety or mission-readiness deficiencies to the Contracting Officer.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP)
For: NAVSUP FLCJ Gulfport Material Handling Equipment (MHE) Maintenance Contract
1. Purpose
The purpose of this Quality Assurance Surveillance Plan (QASP) is to define the methodology and procedures the Government will use to monitor, evaluate, and document the Contractor’s performance in fulfilling the requirements of the Performance Work Statement (PWS). This QASP provides a systematic approach to ensure that services delivered under this contract meet performance standards, comply with contractual requirements, and support mission readiness.
2. Government Roles and Responsibilities
• Contracting Officer (CO): Holds overall responsibility for contract administration, including enforcement of contract terms and conditions.
• Contracting Officer’s Representative (COR): Responsible for day-to-day surveillance and monitoring of Contractor performance, including review of reports, inspections, and acceptance of services.
• Equipment Maintenance Managers: Provide technical input, assist the COR in inspections, and validate maintenance records.
3. Performance Objectives
The Contractor shall perform all services in accordance with the PWS, OEM standards, and industry best practices. Key objectives include:
1. Performance of Preventive Maintenance (PM) at required intervals.
2. Timely and effective completion of Corrective Maintenance (CM).
3. Use of OEM-compliant parts in all repairs.
4. Maintenance of accurate and complete records.
5. Compliance with safety, environmental, and security requirements.
4. Performance Standards and Acceptable Quality Levels (AQLs)
Performance Objective
Performance Standard
Acceptable Quality Level (AQL)
Method of Surveillance
Incentive/Remedy
Preventive Maintenance (PM)
PM performed in accordance with OEM standards and PWS requirements
95% on-time completion
Record review, inspections
Re-performance at no cost; possible payment reduction
Corrective Maintenance (CM)
Repairs completed within OEM time + 2 hours troubleshooting from arrival
95% compliance
Service call logs, inspections
Cure notice for repeated delays
Response Time
Respond to service calls within 1 business day (Mon– Fri)
100% compliance
Government monitoring of service requests
Payment reduction for noncompliance
Parts Standards New or like-new parts meeting OEM specifications used
100% compliance
Parts invoices, records review
Nonconforming parts replaced at Contractor expense
Safety/Environmental Compliance
Work performed in compliance with Navy, OSHA, and environmental regulations
100% compliance
Spot inspections, audits
Work stoppage until corrected; possible default
Recordkeeping
Accurate records submitted to CO and Maintenance Managers
100% compliance
Record audits, documentation review
Noncompliance = corrective action
Equipment Availability Maintain forklift fleet availability rate
≥ 90% availability
Downtime tracking
Escalation to CO if below threshold
5. Surveillance Methods
The Government may use one or more of the following surveillance methods:
• Random Inspections: Unannounced inspections of Contractor-performed work.
• Periodic Inspections: Scheduled reviews of records, logs, and equipment.
• 100% Inspection: Applied to critical safety-related tasks and documentation.
• Customer Feedback: Consideration of end-user/operator reports regarding equipment performance.
• Review of Records/Reports: Verification of accuracy, completeness, and timeliness.
6. Incentives and Remedies
• Incentives:
o Satisfactory performance that consistently meets or exceeds AQLs may be recognized in past performance evaluations for future contract awards.
• Remedies:
o Nonconforming services shall be corrected at no additional cost to the Government.
o Repeated nonperformance may result in a cure notice, withholding of payment, or termination for default in accordance with the Federal Acquisition Regulation (FAR).
7. Documentation and Reporting
• The COR shall document all surveillance results, including deficiencies, corrective actions, and Contractor responsiveness.
• Reports shall be maintained in the official contract file and provided to the CO as required.
• Any deficiencies impacting safety or mission readiness shall be immediately reported to the
CO.