19GE5026Q0143_Attachment 1 addendum- SOW Peshawar HATS.pdf

PDF 83 KB Posted

Attached to
Peshawar Existing Consulate Compound HATS Relocation
Solicitation number
19GE5026Q0143
Issued by

About this file

This is an addendum to the Statement of Work for the Peshawar Existing Consulate Compound HATS (Hardened Area Technical Shelters) Relocation project under Solicitation No. 19GE5026Q0143. The addendum modifies two key sections of the original SOW: the materials shipping address and project-specific schedule requirements.

Under the revised C.1.1.8 section, all materials required to be shipped from the project site must be sent to the European Logistics Support Office (ELSO) in Antwerp, Belgium, with the complete shipping address referenced in Tab 2. The modified C.2.3 section establishes a 210 calendar-day Period of Performance beginning from the Notice to Proceed (NTP) issuance date. The contractor must complete all dismantling, preparation, loading, inland transportation, and associated activities to transport HATS units and applicable materials from the U.S. Consulate General in Peshawar to the Port of Karachi within the first 120 calendar days. The remaining 90 calendar days are allocated for ocean transportation from Karachi, customs and port processing, unloading, inland transportation in Belgium, and final delivery to ELSO in Antwerp. The contractor bears full responsibility for coordinating all activities to meet both the 120-day Port of Karachi milestone and the 210-day final delivery deadline. Extensions to the Period of Performance will only be granted in exceptional circumstances involving events beyond the contractor's control and require written justification submitted to the Contracting Officer.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

September 9, 2026

ADDENDUM NO. 01 TO SECTION C

STATEMENT OF WORK

Peshawar Existing Consulate Compound HATS Relocation

Islamabad, Pakistan

Solicitation No. 19GE5026Q0143

C.1.1.8 Materials Shipping Address

The material shipping address under Section C.1.1.8 is deleted in its entirety and replaced with the following:

All material that is required to be shipped from the project site shall be shipped to the European Logistics Support Office (ELSO), Antwerp, Belgium. For the complete shipping address, refer to Tab 2.

C.2.3 Project-Specific Requirements

The schedule compliance text under C.2.3(5) is deleted in its entirety and replaced with the following.

The Period of Performance (PoP) and schedule requirements below shall apply to all solicitation documents under this project.

The overall Period of Performance (PoP) for this project shall be 210 calendar days from the date of issuance of the Notice to Proceed (NTP).

The Contractor shall complete all dismantling, preparation, loading, inland transportation, and associated activities necessary to transport all HATS units and applicable materials from the U.S. Consulate General Peshawar to the Port of Karachi within 120 calendar days from the date of NTP.

The remaining 90 calendar days of the 210-day PoP shall be used for ocean transportation from the Port of Karachi, customs and port-related processing, as applicable, unloading, inland transportation in Belgium, and final delivery of all HATS and applicable materials to the European Logistics Support Office (ELSO), Antwerp, Belgium.

The Contractor shall be responsible for planning and coordinating all activities necessary to meet both the 120-day Port of Karachi milestone and the 210-day final delivery requirement. Extensions to the Period of Performance will be granted only in exceptional circumstances involving events beyond the Contractor's control. Any request for an extension must be submitted in writing to the Contracting Officer with detailed justification.