This document contains questions and answers related to solicitation number 191BWC21R0002 from the International Boundary and Water Commission for the rehabilitation of sewer pipelines. Specifically, the last question asked to clarify whether SDR 26 piping could be used for discharge piping given that the solicitation required piping rated for 160 psi pressure, which corresponds to SDR 13.5 piping. The answer confirmed that SDR 26 piping may be used for discharge piping, and referenced a revision to specification section 46.03.00 allowing a minimum SDR of 26 for the high density polyethylene discharge piping.

View the file

Other files

File Type Posted
191BWC21R0002 Amendment A00012.pdf PDF
191BWC21R0002 Amendment A00011.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210421.pdf PDF
191BWC21R0002 Revised Per A00011.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210414.pdf PDF
191BWC21R0002 Amendment A00010.pdf PDF
191BWC21R0002 Revised Per A00010.pdf PDF
191BWC21R0002 Revised Per A00009.pdf PDF
191BWC21R0002 Amendment A00009.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210412.pdf PDF
191BWC21R0002 Revised Per A00008.pdf PDF
191BWC21R0002 Amendment A00008.pdf PDF
191BWC21R0002 Revised Per A00007.pdf PDF
191BWC21R0002 Amendment A00007.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210406.pdf PDF
USIBWC TCE Parcel 113-38-007A_Delta_Final.pdf PDF
USIBWC TCE Parcel 140-01-005_Delta_Final.pdf PDF
USIBWC TCE Parcel 102-01-076A_Sainz_Final.pdf PDF
191BWC21R0002 Amendment A00006_draft.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210331.pdf PDF
Additional Questions and Answers Received Against 191BWC21R0002.pdf PDF
USIBWC TCE Parcel 140-01-001A_Harvey_Final.pdf PDF
USIBWC TCE Parcel 102-01-038_Delta_Final.pdf PDF
191BWC21R0002 Amendment A00006.pdf PDF
191BWC21R0002 Revised Per A00006.pdf PDF
Rio Rico Forcemain Drawings and Photos.pdf PDF
UPRR IOI MCL Folder03060-53.pdf PDF
TIOI Pre-Proposal Sign-in.pdf PDF
UPRR Requirements and Guidelines.pdf PDF
191BWC21R0002 Amendment A00005.pdf PDF
191BWC21R0002 Sol Revised Per A00005.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210317.pdf PDF
Questions and Answers Received Against 191BWC21R0002.pdf PDF
TIOI Revised Drawings_A00005.pdf PDF
TIOI PH1-3 Pre-Proposal Key Points to Contractors.pdf PDF
NIWTP Flow Reports_Jan-Dec2020.pdf PDF
Manhole 89 As-Builts_201710_Rev.pdf PDF
191BWC21R0002 Revised Per A00004.pdf PDF
191BWC21R0002 Revised Per A00004.pdf PDF
191BWC21R0002 Revised Per A00004.pdf PDF
191BWC21R0002 TIOI Rehab PH1-3 Specs 20210205.pdf PDF
191BWC21R0002 IOI MH Repair HS 20210205.pdf PDF
191BWC21R0002 Amendment A00004.pdf PDF
191BWC21R0002 IOI MH Repair FS 20210205.pdf PDF
191BWC21R0002 AMENDMENT A00001.pdf PDF
191BWC21R0002 AMENDMENT A00003.pdf PDF
191BWC21R0002 REVISED.pdf PDF
191BWC21R0002 AMENDMENT A00002.pdf PDF
191BWC21R0002 Client Authorization Letter_Rev.docx DOCX document
AZ20200036 08.21.2020.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

191BWC21R0002 Page 1 of 1

TRUNKLINE & IOI REHABILITATION PHASES 1-3

Last Question and Answer Received Against 191BWC21R0002 – Trunkline & IOI Rehabilitation

Phases 1-3

Q55: In specification section 46.03.00 Sewer Flow Control, Page 6, Item H-2, states the discharge piping shall be butt-fused high density polyethylene (HDPE) (minimum thickness SDR 26, 160 psi). However, the required SDR 26 pipe does not correspond to the required pressure rating of

160 psi. Please confirm if SDR 26 pipe may be used for discharge piping on this project, or if discharge piping rated for 160 psi must be used which corresponds to SDR 13.5 piping. Please clarify.

A55: SDR 26 may be used for discharge piping. See revision to Specification Section 46.03.00 3.2 H.2 requiring the HDPE discharge piping to have a minimum SDR of 26.