19-ADDENDUM NO. 1 REVISED SPEC SECTION 02902 (REBID) FINAL.pdf
PDF 85 KB Posted
- Attached to
- PUMP HOUSE NO. 1: PUMP 1-5 & 1-6 EVALUATION & REHABILITATION-FEMA-CONTRACT NO. C213 (REBID)
- Solicitation number
- BCUA-25-C213.1
- Issued by
- Bergen County, New Jersey
About this file
This document is a Measurement and Payment section (Section 02902) for a wastewater pump rehabilitation project involving two specific pumps (pumps 1-5 and 1-6). The project includes a comprehensive scope of work with 15 distinct line items covering mobilization, evaluation, restoration, and reinstallation of wastewater pumps, including detailed component replacements such as bearings, mechanical seals, wearing rings, shaft sleeves, and air relief valves. The contract includes a $70,000 allowance for additional work or unexpected expenses.
The payment structure is based on lump sum pricing for each line item, with mobilization payment recommended after existing pumps are loaded and transported to an evaluation shop. Payment estimates for most items will be calculated based on a percentage of completion multiplied by the respective lump sum price during the payment period. The allowance (Item 16) will be paid based on actual work performed, not to exceed the $70,000 allocated. The contract ensures full compensation for all associated labor, materials, and equipment required for pump removal, evaluation, and rehabilitation.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02902-1
SECTION 02902
MEASUREMENT AND PAYMENT
PART l - GENERAL
1.01 DESCRIPTION
A. Summary: Section describes the measurement of and payment for the work to be done under the items listed in the BID.
B. Each unit or lump sum price stated in the BID shall constitute full compensation as herein specified for each item of work completed in accordance with the Drawings and specifications, including cleaning up.
1.02 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.03 REFERENCES
Not used.
1.04 SCHEDULE OF VALUES
A. Item 1: Lump sum cost for mobilization B. Item 2: Lump sum to evaluate and restore wastewater pump 1-5, complete.
C. Item 3: Lump sum to replace bearings in wastewater pump 1-5 D. Item 4: Lump sum to replace mechanical seals in wastewater pump 1-5 E. Item 5: Lump sum to replace wearing rings, seal rings and O-rings in wastewater pump 1-5 F. Item 6: Lump sum to replace shaft sleeve in wastewater pump 1-5 G. Item 7: Lump sum to install air relief valve pump 1-5.
H. Item 8: Lump sum to reinstall wastewater pump 1-5 I. Item 9: Lump sum to evaluate and restore wastewater pump 1-6, complete.
J. Item 10: Lump sum to replace bearings in wastewater pump 1-6 K. Item 11: Lump sum to replace mechanical seals in wastewater pump 1-6 L. Item 12: Lump sum to replace wearing rings, seal rings and O-rings in wastewater pump 1-6 M. Item 13: Lump sum to replace shaft sleeve in wastewater pump 1-6 N. Item 14: Lump sum to install air relief valve pump 1-6.
O. Item 15: Lump sum to reinstall wastewater pump 1-6.
P. Item 16: Lump sum cost for allowance ($70,000)
02902-2
1.05 MEASUREMENT
A. General
1. The lump sum price for Item 1 shall constitute full compensation for all costs associated with the Contractor mobilizing onsite.
2. The lump sum price for Items 2 through 15 shall constitute full compensation for all work associated with removal, evaluation, and rehabilitation of the specified pumps and shafting, including but not limited to labor, materials, and equipment required.
3. The lump sum price for Item 16 shall constitute full compensation for all work associated with the allowance.
1.06 APPLICATIONS FOR PAYMENT
A. The following subsections describe the measurement of and payment for the work to be done under the items listed in the BID.
1. Estimates for payment under Item 1 shall be based on a lump sum cost for mobilization. Mobilization payment will be recommended by the Engineer once the existing pumps are loaded and transported to the pump evaluation shop.
2. Estimates for payment under Item 2 through 15 shall be based on a percentage of completion of the work times the lump sum price, during the period of payment.
3. Estimates for payment under Item 16 shall be based on the actual work performed, not to exceed the allowance.
END OF SECTION