13-TECHNICAL SPECIFICATIONS BCUA C213 (REBID).pdf

PDF 441 KB Posted

Attached to
PUMP HOUSE NO. 1: PUMP 1-5 & 1-6 EVALUATION & REHABILITATION-FEMA-CONTRACT NO. C213 (REBID)
Solicitation number
BCUA-25-C213.1
Issued by
Bergen County, New Jersey

About this file

This document is a comprehensive specification for the evaluation and rehabilitation of two raw wastewater pumps (Pumps 1-5 and 1-6) for the Bergen County Utilities Authority located in Little Ferry, New Jersey. The project involves a detailed rehabilitation process for vertical centrifugal solids handling pumps manufactured by Flowserve, with specific requirements for replacing critical components including bearings, mechanical seals, wearing rings, seal rings, O-rings, and shaft sleeves. The work will be performed sequentially, with Pump 1-5 being evaluated and rehabilitated first, followed by Pump 1-6, while maintaining continuous wastewater pumping operations. The project requires a 48-hour operational test period for each pump, with testing to be witnessed by the Engineer and BCUA Operations staff.

The project includes a total of 13 specific line items for evaluation, restoration, and component replacement, with a $70,000 allowance for additional work. Payment will be structured as lump sum items, with mobilization payment recommended after pumps are transported to the evaluation shop. The contractor must use a pump repair shop certified by Flowserve and capable of providing replacement parts compatible with the existing equipment. Warranties for replaced parts are set at a minimum of 12 months from startup, and all work must comply with multiple national and local standards, including NFPA, OSHA, ASTM, and ANSI regulations. The specifications emphasize precise technical requirements for pump components, installation procedures, testing protocols, and performance standards to ensure optimal pump rehabilitation.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PUMP HOUSE No. 1

PUMP 1-5 & 1-6 EVALUATION &

REHABILITATION

One Harmon Plaza Suite 600

Secaucus, NJ 07094

RVE Project No. 0200M021

Stephanie Cuthbert, NJ PE Lic. No. 42136 Date

Prepared for

BERGEN COUNTY UTILITIES

AUTHORITY

Little Ferry, New Jersey

Revised July 2025

SPECIFICATIONS

for scuthbert Typewritten Text 7-8-25

Table of Contents

Bergen County Utilities Authority Pump Building No. 1, Pump 1-5 & 1-6 Evaluation and Rehabilitation

Division Section Title Pages

01000 GENERAL REQUIREMENTS 1

01010 SCOPE OF WORK 5

01300 SUBMITTALS 3

01414 CONTROL OF WORK 2

02902 MEASUREMENT AND PAYMENT 2

15011 VERTICAL CENTRIFUGAL SOLIDS HANDLING PUMP COMPONENTS 5

APPENDIX A

Figure 1 – PUMP HOUSE No. 1 SECTION VIEW

GENERAL REQUIREMENTS 01000-1

SECTION 01000

GENERAL REQUIREMENTS

1.01 GENERAL

A. Only major items of work are given in the Bid Form, but it is the intent of the specifications to secure a completely rehabilitated set of pumps, and if any workmanship or materials be required which are obviously necessary to carry out the full intent and meaning of the plans and specifications or to be reasonably inferred therefrom, the cost of such workmanship or materials shall be included in the unit price for the major items of work.

B. The Contractor, in the construction of any project, shall not stockpile materials or his equipment on any private property; except areas designated by the plans or as directed by the Engineer. If so required, the Engineer may direct the Contractor to have his equipment removed from any project during weekend hours.

C. The Contractor is hereby advised that Public Law 1975, Chapter 251, as amended by P.L. 1979, Chapter 459 is applicable to this project.

D. The Contractor shall apply and pay for all permits that may be required for any of the work involved with this project

E. Contractor shall notify Engineer at least forty-eight (48) hours in advance of any work on Saturdays. There will be no work permitted on Sundays or holidays. This project will receive inspections and the normal working hours for the Inspector are from 7:00 AM to 4:00 PM, Monday through Friday. Any overtime inspection costs which are avoidable will be reimbursed by the Contractor.

1.02 PRE-CONSTRUCTION PHOTOGRAPHS

A. Contractor shall be responsible of taking pre-construction videotapes or photographs prior to the commencement of operations. The Contractor shall be responsible for providing the locations and dates of each photo and/or video in an attached report. The pre-construction photos and videotapes shall be mailed and submitted to the Engineer on a USB device prior to mobilization. Contractor shall provide the engineer (2) USB devices with copies of the photos, videos and supporting report.

1.03 QUANTITY AND PAYMENT

Unless otherwise provided for in these contract specifications, no separate payment will be made for work associated with this section and all costs shall be included in the various items of the bid proposal.

END OF SECTION

01010-1

SECTION 01010

SCOPE OF WORK

PART 1 - GENERAL

1.01 GENERAL

A. In general, the project consists of evaluating, rehabilitating, reinstalling, and placing into service two (2) existing raw wastewater pumps in Pump Building No. 1 at the Bergen County Utilities Authority (BCUA) Wastewater Plant in the Borough of Little Ferry, New Jersey. The pumps to be evaluated, rehabilitated, reinstalled, and placed back into service are the pumps labeled as 1-5 and 1-6. Pump 1-5 shall be repaired first. Once it has been accepted and returned to service, pump 1-6 will be evaluated and repaired. Existing pump motors are not included in this evaluation or rehabilitation and are to remain onsite. Motors will be deenergized (lock out tag out) by BCUA operations.

B. Sequence: Pumps 1-5 and 1-6 are currently in use; they shall be evaluated and repaired in series.

C. The pumps to be rehabilitated under this Contract shall meet the performance standards as outlined in the bid documents. The Contractor is responsible for all labor, materials, and equipment included in evaluating and rehabilitating the existing pumps.

D. It is the intent of these Specifications for the Contractor to evaluate and rehabilitate the pumps.

Contractor shall provide a written report with an assessment of all major components and a recommendation regarding the need to repair or replace other components. Report shall be in the form of a letter on the pump repair shop’s letterhead and shall include photos of the disassembled pump components and photos of any problems identified. Repair and replacement components recommended shall include a cost estimate and an estimated time for their repair in the written report.

E. The rehabilitated pumps shall be operational and able to perform their rated capacity.

Evaluate, and re-install the pumps completely, which includes all the necessary improvements as set forth in the Contract Documents.

F. Pump Building No. 1 shall remain active at all times. Pumping of wastewater shall remain uninterrupted. After a pump is put back in service, it shall be operational for 48 consecutive hours prior acceptance by the Engineer and Owner.

01010-2

PART 2 - DESCRIPTION OF WORK

2.01 DESCRIPTION

The Scope of Work below outlines the general items and distribution of work and shall not be construed as being all inclusive. The work of this project consists of the following:

A. Evaluate and rehabilitate the two (2) raw wastewater pumps complete (excluding motor).

Pumps 1-5 and 1-6 are in service and shall be evaluated and repaired in series (1-5 first then 1-6).

B. The price bid shall include furnishing all labor, material and equipment required to perform the following for each pump:

a. The pump rotating assemblies will be removed by BCUA operations and volute caps installed to isolate flow.

b. The pumps will be removed from the dry well and located on the grade level.

Contractor shall be responsible for loading and transporting to the pump repair shop.

c. Contractor shall verify with BCUA operations that the motors have be de-energized (lock out tag out).

d. Isolate the pump’s seal water flow and disconnect the seal water supply line.

e. Remove shaft intermediate guards and supports, as needed.

f. Set up and remove the existing coupling from the shaft of the existing rotating assembly.

g. Send the existing pump rotating assembly to a certified pump service shop.

Rehabilitation work shall include the following:

i. Replace the bearings.

ii. Replace the existing packing with mechanical seals.

iii. Replace the wearing rings, seal rings, and O rings.

iv. Replace the shaft sleeves.

v. Perform an evaluation of all other pump and shaft components as required.

Provide a written report with an assessment of all major components and a recommendation regarding the need to repair or replace other components.

Repair and replacement components recommended shall include a cost estimate and an estimated time for their repair in the written report. The evaluation shall include, but not be limited to, all of the items listed in the bid proposal. A written report for each pump shall be submitted within 14 days after receipt at the evaluation and repair facility.

01010-3

h. All hardware to be replaced with stainless steel grade hardware as noted in Section 15001, and the pumps shall be cleaned.

i. To replace the wear ring in the volute the water level in the wet well needs to be depressed by BCUA operations. As the suction valves do not close 100%, there will be some residual flow from the wet well into the volute. Residual water in the volute shall be managed by the contractor. During the pump removal (by BCUA staff) the volute wear ring was accessible by opening the volute drain valve and placing a small sump pump in the suction elbow to manage the residual valve leakage flow. Work on the volute wear ring shall require early morning access (3AM – 6AM) and shall be coordinated with BCUA operations to lower the wet well.

j. Rig in the rehabilitated pump rotating assembly and mechanically connect it to the existing piping and volute.

k. Unsecure the lower section of the drive shaft and mechanically connect it to the pump coupling and align.

l. Reinstall shafts and intermediate guards as required.

m. Reconnect and activate the seal water system.

n. Reconnect pump bearing vibration sensor.

o. Install new ¾” SS nipple and ball valve air relief in one of the ports on the existing volute.

p. Manufacturer’s inspection and approval to operate received by the Engineer.

Testing and start up in accordance with Specification Section 15001, Paragraph 3.04.

q. Remove lock out/tag out and energize the system. Coordinate with BCUA staff.

r. Start-up the equipment.

C. The Contractor shall be responsible for all post-installation testing during the 48 hour operational test period per Section 1.01.F above to document that each pump operates with the same or better performance prior to their removal for evaluation and rehabilitation. Testing shall be witnessed by the Engineer and BCUA Operations staff. Contractor shall provide vibration analysis per specification 15001, section 1.02, F.

2.02 All parts and materials required shall be new and unused.

2.03 Contractor is responsible for field verifying all dimensions.

2.04 BCUA shall be responsible for unbolting and disconnecting pump components, rigging and removing the pump from the Pump Room floor up to the Pump Motor Room. Contractor shall load onto a truck for delivery to the certified pump evaluation shop, and all costs associated with transportation of its components, as well as its return to the plant and rigging

01010-4 and reinstallation. There are overhead hoists located inside Pump Building #1 that are available for raising and lowering the pump components. Contractor shall coordinate with BCUA Operations staff on the use of these hoists.

2.05 Material Storage Area: A material storage area for the Contractor’s use shall be coordinated with the Owner. The Contractor is responsible for securing his work area and stored equipment. The Contractor shall coordinate with all other work that may be under construction at the plant. All material shall be stored in methods to maintain the integrity of the existing materials.

2.06 Upon receipt of the evaluation report provided by the Contractor for each pump to the Engineer, the Owner and Engineer will review and will provide direction to the Contractor within fourteen (14) days of receipt of the report.

2.07 The above Scope of Work outlines the general items and distribution of work and shall not be construed as being all inclusive.

2.08 Allowances: Any unused portions of the allowance shall be retained by the Owner.

Allowances do not include security deposits. Utilization of the allowance shall only be as approved in writing by the Engineer.

2.09 The Contractor shall obtain permission of the Owner prior to removing any equipment from service for performance of the work required under this Contract.

2.10 A reference project drawing is attached in Appendix A (Figure 1) and hereby included with the project specification.

PART 3 - BID ITEMS

3.01 The Bid Form lists “Evaluation, Wastewater Pump 1-X” lump sum items on which the Bidder will present their cost to perform the Work. Upon award of the Contract, the Contractor will be required to submit a Schedule of Values.

3.02 The Bid Form line items shall be all inclusive of the labor, materials, and equipment that is required for a full and functioning system as shown and specified. For Work that is not specifically listed as part of a line item, but required to complete the scope, payment shall be made as part of the various items in the Contractor’s bid.

PART 4 - PAYMENT

4.01 Costs for all coordination shall be included in the various items of the Contractor's Bid Price.

Coordination of the project shall include the following:

A. The contractor shall be responsible for coordinating his or her work and that of his or her subcontractors on the project. The contractor shall also coordinate all work with the Owner to ensure no disruption to the overall plant process occurs. Cooperation will be required in the arrangement for the storage of materials and in the detailed execution of the work.

01010-5

B. Contractor shall, at no additional cost:

1. Assume full responsibility for protection and safekeeping of equipment and products stored on and off premises.

2. Make as many trips to the pump storage facility as necessary to unload, haul, and store received replacement parts. Contractor is responsible for timing of and coordinating equipment deliveries, including providing equipment to unload deliveries.

3. Not store products in locations that interfere with the operations of Owner.

4. Properly store all equipment onsite and insure against damage, fire and/or explosion.

5. Assume full responsibility for site safety within the work area. The volute drain valve is only accessible at the sump level below the main pump floor and is an access restricted area. The contractor shall supply their own confined space air monitors for working on and below the Pump Room floor.

6. Provide a Job Hazards Analysis (JHA) for review and approval by the Engineer and BCUA Operations prior to beginning work.

7. Retain all existing materials for inspection by the Engineer until the Engineer indicates that the replaced materials can be disposed. Contractor is responsible for disposal of all replaced/unused materials in accordance with Federal, State, and Local laws.

01300- 1

SECTION 01300

SUBMITTALS

PART 1 – GENERAL

1.01 Summary: This section specifies requirements for handling submittals.

1.02 General Procedures: Coordinate submittal preparation with performance of construction activities, and with purchasing or fabrication, delivery, other submittals and related activities.

Transmit in advance of performance of related activities to avoid delays.

Coordinate transmittal of different submittals for related elements so processing will not be delayed for coordination with other submittals. The Engineer reserves the right to withhold action on a submittal requiring coordination until related submittals are received.

Processing: Allow two weeks for review. Allow more time if processing must be delayed for coordination with other submittals. The Engineer will advise the Contractor when a submittal must be delayed for coordination. Allow two weeks for re-processing each submittal.

No extension of time will be authorized because of failure to transmit submittals sufficiently in advance of the Work to permit processing.

Submittal Preparation: Place a label or title block on each submittal for identification. Provide a 4” x 5” space on the label or beside the title block on shop drawings to record Contractor’s review and approval markings and action taken. Include the following information on the label for processing and recording action taken:

Project Name Date Name and address of Engineer Name and address of Subcontractor Name and address of Supplier Name of Manufacturer Bid Item Number

1.03 Submittal Transmittal: Package submittals appropriately for transmittal and handling. Transmit with a transmittal form. Submittals received from other than the Contractor will be returned without action.

1.04 Contractor’s Construction Schedule: Submit a fully developed, bar-chart type construction schedule at the pre-construction conference. Provide a separate bar for each construction activity and a vertical line to identify the first working day of each week.

Coordinate the construction schedule with the list of subcontracts, submittal schedule, progress reports, payment requests and other schedules.

Indicate completion in advance of the date established for substantial completion. Indicate substantial completion on the schedule to allow time for the Engineer’s procedures necessary for certification of substantial completion.

01300- 2

1.05 Distribution of Schedules: Distribute approved copies of the construction schedules to the

Engineer, Owner, Subcontractors, and other parties required to comply with scheduled dates.

Post copies in the temporary field office. When revisions are made, distribute to the same parties and post in the same locations.

Updating: Revise each schedule after each meeting or activity, where revisions have been made.

Issue the updated schedules concurrently with report of each meeting. The revised schedule must be approved by the engineer.

1.06 Shop Drawing: Submit new information, drawn to an accurate scale. Indicate deviations from contract documents. Do not reproduce contract documents or copy standard information as the basis of shop drawings. Include the following information:

Dimensions Identification of products and materials included.

Notation of coordination requirements.

Notation of dimensions established by field measurement.

Sheet Size: Except for templates, patterns and similar full-size drawings, submit shop drawings on sheets at least 8 1/2“ x 11” but no larger than 30” x 42”.

Do not use shop drawings without a final stamp indicating action taken indicating action taken in connection with construction.

1.07 Product Data: Collect product data into a single submittal for each element or system. Mark each copy to show applicable choices and options. Where product data includes information on several products, some of which are not required, mark copies to indicate the applicable information.

Include the following information:

Manufacturer’s printed recommendations.

Compliance with recognized trade association standards.

Compliance with recognized testing agency standards.

Application of testing agency labels and seals.

Notation of dimensions verified by filed measurement.

Notation of coordination requirements.

Submittals: Submit shop drawings electronically. Provide one hard copy of the O&M manual and submit electronically.

Unless noncompliance with contract document provisions is observed, the submittal may serve as the final submittal.

Distribution: Furnish copies of final approved or approved as noted submittal to installers, and other required for performance of construction activities. Show distribution on transmittal forms.

Do not proceed with installation until an applicable copy of product data is in the installer’s possession. Do not permit use of unmarked copies of product and data in connection with construction.

1.08 Distribution: Prepare additional sets for subcontractors, manufacturers, fabricators, installers, and others as required for performance. Show distribution on transmittal forms.

01300- 3

1.09 Engineer’s Action: Except for submittals for record, information, or similar purposes, where action and return are required, the Engineer will review each submittal, mark to indicate action taken and return. Compliance with specified characteristics is the contractor’s responsibility. The Engineer will stamp each submittal with a self-explanatory action stamp. The stamp will be appropriately marked to indicate action taken.

PART 2 – MATERIALS

A. Not Applicable

PART 3 – EXECUTION

PART 4 – QUANTITY AND PAYMENT

A. No separate payment will be made for work performed under this section.

01414-1

SECTION 01414

CONTROL OF WORK

PART 1 - GENERAL

1.01 PLANT AND HOURS OF CONSTRUCTION

A. Furnish labor and equipment which will be efficient, appropriate, and large enough to secure a satisfactory quality of work and a rate of progress that will ensure the completion of the work within the Contract Time. If at any time such labor and equipment appears to the Engineer to be inefficient, inappropriate, or insufficient for securing the quality of work required or for producing the rate of progress aforesaid, the Engineer may order the Contractor to increase the efficiency, change the character, or increase the plant equipment, and the Contractor shall conform to such order at his expense. Failure of the Engineer to give such order shall in no way relieve the Contractor of his or her obligations to secure the quality of the work and rate of progress required.

1.02 CARE AND PROTECTION OF PROPERTY

A. The Contractor shall be responsible for the preservation of all property in his or her work area and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to property in the Contractor’s work area by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be restored by the Contractor, at his or her expense, to a condition similar or equal to that existing before the damage was done, or he or she shall make good the damage in other manner acceptable to the Engineer and the Owner.

1.03 INTERFERENCE WITH EXISTING PLANT OPERATIONS

A. The Contractor shall, at all times, conduct his or her operations so as to interfere as little as possible with existing plant operations. The Contractor shall develop a program, in cooperation with the Engineer and the Owner, which shall provide for the work performed under this Contract in the most orderly manner possible. This program shall be adhered to except as deviations therefrom are expressly permitted. Before starting work that will interfere with the operation of existing facilities, the Contractor shall do all possible preparatory work and shall see that all tools, materials, and equipment are made ready and at hand.

B. The Contractor shall have no claim for additional compensation by reason of delay or inconvenience in adapting his or her operations to the need for continuous treatment of wastewater at the existing plant.

1.04 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND UTILITIES

A. Any damage to existing plant structures, utilities, equipment, or roadways resulting from the Contractor's operations shall be repaired by him or her at his or her expense.

B. The Contractor shall bear full responsibility for obtaining all locations of underground structures and utilities, as needed (including existing water services, drain lines, and sewers).

01414-2

Services to buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by the Contractor.

C. Protection and temporary removal and replacement of existing utilities and structures as described in this Section shall be a part of the work under the Contract and all costs in connection therewith shall be included in the Total Price Bid in the Bid Form.

1.05 CLEANUP AND DISPOSAL OF EXCESS MATERIAL

A. During the course of the work, the Contractor shall keep the site of his or her operations in as clean and as neat a condition as is possible. He or she shall dispose of all residue resulting from the work and shall leave the entire site of the work in a neat and orderly condition.

B. In order to prevent environmental pollution arising from the activities related to the performance of this Contract, the Contractor and his or her subcontractors shall comply with all applicable Federal, State, and local laws, and regulations concerning waste material disposal, as well as the specific requirements stated in this Section and elsewhere in the Specifications.

PART 2 – MATERIALS

PART 3 – EXECUTION

PART 4 – QUANTITY AND PAYMENT

A. No separate payment will be made for work performed under this section.

02902-1

SECTION 02902

MEASUREMENT AND PAYMENT

PART l - GENERAL

1.01 DESCRIPTION

A. Summary: Section describes the measurement of and payment for the work to be done under the items listed in the BID FORM.

B. Each unit or lump sum price stated in the BID FORM shall constitute full compensation as herein specified for each item of work completed in accordance with the Drawings and specifications, including cleaning up.

1.02 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.03 REFERENCES

Not used.

1.04 SCHEDULE OF VALUES

A. Item 1: Lump sum cost for mobilization B. Item 2: Lump sum to evaluate and restore wastewater pump 1-5, complete.

C. Item 3: Lump sum to replace bearings in wastewater pump 1-5 D. Item 4: Lump sum to replace mechanical seals in wastewater pump 1-5 E. Item 5: Lump sum to replace wearing rings, seal rings and O-rings in wastewater pump 1-5 F. Item 6: Lump sum to replace shaft sleeve in wastewater pump 1-5 G. Item 7: Lump sum to install air relief valve pump 1-5.

H. Item 8: Lump sum to evaluate and restore wastewater pump 1-6, complete.

I. Item 9: Lump sum to replace bearings in wastewater pump 1-6 J. Item 10: Lump sum to replace mechanical seals in wastewater pump 1-6 K. Item 11: Lump sum to replace wearing rings, seal rings and O-rings in wastewater pump 1-6 L. Item 12: Lump sum to replace shaft sleeve in wastewater pump 1-6 M. Item 13 Lump sum to install air relief valve pump 1-6.

N. Item 14: Lump sum cost for allowance ($70,000)

1.05 MEASUREMENT

02902-2

A. General

1. The lump sum price for Item 1 shall constitute full compensation for all costs associated with the Contractor mobilizing onsite.

2. The lump sum price for Items 2 through 13 shall constitute full compensation for all work associated with removal, evaluation, and rehabilitation of the specified pumps, including but not limited to labor, materials, and equipment required.

3. The lump sum price for Item 14 shall constitute full compensation for all work associated with the allowance.

1.06 APPLICATIONS FOR PAYMENT

A. The following subsections describe the measurement of and payment for the work to be done under the items listed in the BID.

1. Estimates for payment under Item 1 shall be based on a lump sum cost for mobilization. Mobilization payment will be recommended by the Engineer once the existing pumps are loaded and transported to the pump evaluation shop.

2. Estimates for payment under Item 2A through 3F shall be based on a percentage of completion of the work times the lump sum price, during the period of payment.

3. Estimates for payment under Item 4 shall be based on the actual work performed, not to exceed the allowance.

15011-1

SECTION 15011

VERTICAL, CENTRIFUGAL SOLIDS HANDLING PUMP COMPONENTS

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. Refer to Section 01010 for a description of the Scope Of Work.

B. Existing pump characteristics (approximate):

Pump

Flow, MGD

TDH,

ft.

Power, Hp

Flowserve Model No.*

Flowserve Serial No.*

1-5 40 45 400 30MC-1 0405MT000313-1

1-6 40 45 400 30MC-1 0307MT000249

*From Pump Nameplate

1.02 QUALITY ASSURANCE

A. Reference standards: All material, equipment and installation shall comply with these specifications and the applicable requirements of the following:

1. New Jersey Uniform Construction Code

2. National Standard Plumbing Code

3. National Fire Protection Association (NFPA)

4. Underwriter's Laboratories, Inc (UL)

5. National Electrical Code (NEC)

6. Occupational Safety and Health Administration (OSHA)

7. American Society for Testing & Materials (ASTM)

8. American National Standards Institute (ANSI)

9. American Society of Mechanical Engineers (ASME)

10. Hydraulic Institute

11. National Electrical Manufacturers Association (NEMA)

12. Institute of Electrical and Electronic Engineers (IEEE)

13. American Water Works Association (AWWA)

B. Based on the evaluation report provided by the Contractor, as described in Section 01010, major pump components, if required for additional rehabilitation, shall be supplied by an authorized Flowserve manufacturer’s representative pump supplier and shall be compatible with the make and model of the existing pumps.

C. Installation History: The parts supplied shall be manufactured by a pump supplier with a minimum of 1,000 wastewater pumps installed and operating for no less than five (5) years in the United States.

D. The single source supplier of the parts/equipment shall be fully responsible for the design, arrangement and operation of all connected rotating components to ensure that neither harmful nor damaging vibrations occur at any speed within the specified operating range.

E. Warranties:

15011-2

1. Replaced pump parts shall be warranted for a minimum of twelve (12) months from start-up.

2. All manufacturer warranties shall be in published form and shall extend to all similar units. A copy of the warranty shall be provided to the Owner prior to startup of each rehabilitated pump. Alternate manufacturers' standard warranties shall be modified to meet specified coverage or shall exceed the specified coverage.

3. Subsequent to notice of a deficiency identified by the Owner to the Contractor, the

Contractor, if under the Maintenance Bond period, will be responsible for shipping the pumping unit to an authorized pump manufacturer's service facility. Pump manufacturer shall be responsible to return the pump (with shipping costs prepaid by the manufacturer) to the Owner.

F. Vibration, when measured in the direction of maximum amplitude on the pump and motor bearing housings, shall not exceed the limits given in the latest ANSI/HI nomograph for the applicable pump type.

1.03 SUBMITTALS

A. Submit shop drawings and product data in accordance with Specification Section 01300 for major equipment items. Based on the repairs recommended in the Contractor’s evaluation reports and ONLY where directed by the Engineer, Contractor shall provide the following (where applicable):

1. Certified dimensional drawings of each item of equipment and auxiliary apparatus to be furnished, including equipment weights and location and size of anchor bolts.

2. Literature and drawings describing the equipment, including parts list and materials of construction, in sufficient detail to indicate full conformance with the detail specifications.

3. Cut sheets on accessory items.

B. Operation and Maintenance Data

1. Complete operating and maintenance instructions shall be furnished for major equipment components.

1.04 DELIVERY, STORAGE AND HANDLING

A. All parts shall be properly protected so that no damage or deterioration will occur during a prolonged delay from the time of shipment until installation is completed and the unit and equipment are ready for operation.

B. All equipment and parts must be properly protected against any damage during shipment. The

Contractor shall store equipment in accordance with the manufacturer's instruction.

1.05 MAINTENANCE

A. Furnish all special tools and test equipment required for the proper servicing of all equipment.

15011-3

PART 2 - PRODUCTS

2.01 MANUFACTURER

A. Existing pumps are manufactured by Flowserve. Replacement components shall be compatible with existing pumping equipment.

B. “Replacement” is defined as, but is not limited to, providing a new part(s), installation of new part(s) and installation of the pumping unit back in place and operating satisfactorily.

2.02 MATERIALS OF CONSTRUCTION

A. BEARINGS (REQUIRED): Each pump shall be provided with bearings both radial and thrust, of the tapered spherical roller type, of ample size to carry all loads imposed under continuous operation without overheating. All bearings shall be accessible while the pump is in operation.

Bearings shall be designed in accordance with the ABMA standards for a minimum L-10 life of 100,000 hours, without the addition of external cooling. The bearings shall be grease lubricated, and a relief plug shall be provided so that excessive grease pressure will not damage the bearings.

C. MECHANICAL SEALS (REQUIRED): Replace pump packing with mechanical seal. All metal components shall be 300 series stainless steel. Mechanical seals shall be compatible with the pump. Proprietary stuffing box sealing systems are not acceptable. Mechanical seal shall be of the split type. Acceptable manufactured and model include Flowserve PSS4 split seal, Chesterton 442 split seal or equal.

D. WEARING RINGS/SEAL RINGS/O-RINGS (REQUIRED): Removable hardened stainless steel wearing rings shall be provided for both the suction and the impeller, with the wearing surfaces normal to the axis of rotation to accommodate the adjustment feature specified further herein.

Radial wear rings are not an acceptable alternate. Rings shall be securely fastened to prevent any relative motions and designed for easy replacement. Both wearing rings shall be hardened 400 series stainless steel, with the impeller ring hardened to 200 to 250 Brinell and the casing ring hardened to 300 to 350 Brinell, designed to compensate for a minimum of ¼ inch wear.

E. SHAFT SLEEVE (REQUIRED): Renewable ASTM A743 hardened stainless steel shaft sleeves extending from the impeller hub through the stuffing box shall be provided. Sleeve material shall be 316 stainless steel. The shaft sleeves shall be internally ground to approved tolerances and positively secured to the shaft to prevent relative rotation. Passage of water between the shaft and sleeve shall be prevented. Shrink fit shaft sleeves will not be acceptable.

PART 3 - EXECUTION

3.01 GENERAL

A. Pumping equipment shall be installed by skilled personnel in a neat and workmanlike manner, true to alignment and elevation to match piping and fittings and in accordance with the pump manufacturer’s latest version of instructions.

B. Existing pump shall not be removed and relocated on-site until all replacement components specified herein have been received by the Contractor or his certified pump repair shop.

15011-4

3.02 PROTECTION

A. All pumping equipment shall be carefully handled and stored to prevent damage, theft, weathering, etc., until final acceptance. All units shall be left in shipping containers where applicable until the time of installation.

3.03 REMOVAL AND INSTALLATION

A. Once the existing pump and shafting is removed, Contractor shall work continuously (at least eight hours per day on site, Monday through Friday), with adequate labor, equipment, and materials to perform the work.

3.04 FIELD QUALITY CONTROL & TESTING

A. Initial testing of all pumping equipment shall only be performed by a factory-trained representative (minimum on site time of three hours). Tests shall only be conducted with units fully lubricated, with an adequate seal water supply, and pumping raw wastewater. Lubrication is necessary for electrical verification of direction of rotation by "bumping" the motor. No pump shall be run dry under any circumstances.

B. All pumping equipment shall operate smoothly without undue noise and vibration, and without binding, slippage or overloading.

C. Contractor shall retain a third-party testing company to measure the actual lateral and torsional critical speeds of the pump during the 48 hour in-service testing period per Specification Section 01010, Paragraph 1.01.F , to ensure these analyses are within the thresholds provided in the pump submittal. Contractor is responsible for making adjustments to the pump and shafting as needed if these measurements are out of spec.

D. Final testing and demonstration shall be performed in the presence of the Engineer. Contractor shall provide Engineer with at least 48 hours noticed prior to final testing. Operating parameters such as pump rotation speed, pressure, flow rates, etc., shall be verified.

E. Failure of the pump or shafting to pass any test shall be cause for the Contractor to repair, replace or otherwise properly correct the malfunction or defect and to similarly reschedule, isolate the pump, and retest that entire pumping unit in conjunction with the existing motor and drive assembly complete.

PART 4 - PAYMENT

4.1 QUANTITY AND PAYMENT

A. Refer to Section 02902 of these Specifications.

APPENDIX A

FIGURE 1 – PUMP HOUSE No. 1, SECTION VIEW

FIGURE 1

PUMP HOUSE No. 1 SECTION VIEW, TYPICAL (PUMP ROOM & WET WELL)

(From Sheet 10 of the drawing set titled “Overpeck Valley Joint Sewer Works, Bergen County Sewerage Authority”, by Bogert-Childs, dated November 1948)

1. COVER July 2 2025
2. TECH SPEC TOC july 2 2025
3. 01000 General Requirements_Pumps 1-5 1-6 July 2 2025
4. 01010 SCOPE OF WORK_Jul 2 2025
5. 01300 SUBMITTALS July 2 2025
PART 1 – GENERAL
PART 2 – MATERIALS
PART 3 – EXECUTION
PART 4 – QUANTITY AND PAYMENT
6. 01414 CONTROL OF WORK July 2 2025
PART 2 – MATERIALS
PART 3 – EXECUTION
PART 4 – QUANTITY AND PAYMENT
7. 02902 MEASUREMENT AND PAYMENT July 2 2025
8. 15011 Pump Spec_July 2 2025
9. Appendix A- Fig 1 July 2 2025