UPDATED_J._9_NASM_Deductive_Options.pdf
PDF 6 MB Posted
- Solicitation number
- 18QT0010036
About this file
Attached is J.9 an updated Deductive Options which includes clarifications made for option 3 regarding flooring (see PDF page 5) and an option 13.13 is included as a deductive option which is the deletion of gallery 105 - Reinventing Flight (see PDF page 64).
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
© Haley Sharpe Design NASM Deductive Options
Table of Contents
1. General Requirements of Exercising Deductive Options
2. Option 2
3. Option 3
4. Option 4
5. Option 5
6. Option 6
7. Option 7
8. Option 8: Other Material VE:
1. Gallery 206 Destination Moon
2. Gallery 207 One World Connected
3. Gallery 102 America by Air
4. Gallery 107 Wright Brothers
9. Option 9: Level 1 AV/CI Reductions:
1. Gallery 103 Early Flight
2. Gallery 105 Reinventing Flight
3. Gallery 106 We All Fly
4. Gallery 205 Exploring the Planets
5. Gallery 206 Destination Moon
10. Option 10: Level 1 Content Reductions:
1. Gallery 206 Destination Moon
2. Gallery 107 Wright Brothers
11. Option 11: Level 2: AV/CI Reductions:
1. Gallery 205 Exploring the Planets
2. Gallery 206 Destination Moon
3. Gallery 207 One World Connected
4. Gallery 203 Nation of Speed
12. Option 12: Level 2 Content Reductions:
1. Gallery 206 Destination Moon
2. Gallery 203 Nation of Speed
13. Option 13: Last Resort Deductions:
1. Gallery 206 Destination Moon
2. Gallery 207 One World Connected
3. Gallery 105 Reinventing Flight
Page
8-10
11-12
13-14
15-17
18-19
20-21
22-23
24-25
26-27
28-31
32-33
34-35
36-38
39-40
41-43
44-51
52-53
54-58
59-60
61-62
General Requirements of Exercising Deductive Options
It is the responsibility of the Contractor to:
1. Remove any omissions and related references from all documentation, lists or other sources that may form the base of production orders, submittals or schedules.
2. Coordinate the agreed deductive scope across all disciplines.
3. Coordinate the agreed deductive scope with the black box CSC contractor, as applicable.
4. Coordinate the agreed deductive scope with Transformation subcontractors involved, as applicable.
5. hsd will identify any changes related to deductive options during the redesign process and otherwise reference the existing drawings and specifications document for any standard details. These documents cover all requirements and the Contractor should seek clarification regarding any questions or details. For further information and costing purposes please refer to the relevant gallery cover sheets.
6. Fabricate and implement any and all variations in accordance with the deductive options documents and exhibit specific technical drawings package .
7. Reroute or adequately conceal any cabling and services that may run through the area(s) of omission in accordance with the technical package where former option is not possible, subject to NASM approval.
8. Omit and/or amend all change related services and connections as relevant unless otherwise specifically stated. For further information and costing purposes please refer to the relevant gallery cover sheets.
9. Submit detailed fabrication drawings of all deductive option changes prior to proceeding with any substitution deemed necessary including reasons and details of such substitution identified on drawings and submitted for. approval to NASM .
10. Provide a complete and accurate as-built record of all approved changes, including rerouting of service cable runs, relocation of hardware or control points, and all other modifications.
Introduction
Option 1 is an additive option to the Base Bid, which adds Zone 3 to the contract. The subsequent options are deductive options that are severable and can be omitted from the scope if directed by NASM. NASM reserves the right to exercise any options or sub-options individually, as a selection or collectively, or to exercise none.
To practice any of the options as required the Contractor shall adhere to all the following criteria and seek clarification if any question arises. Any proposed deviation from criteria must be approved prior to implementation. All Contract constituents apply unless otherwise stated.
The Contractor to review in detail and familiarize with all 100% drawings relevant to the selected option prior to costing alongside with the directions provided in this document.
For each selected option hsd shall provide the Contractor with the hsd redesign intent and related documentation within the stated timeframe as specified in the details.
Option 2
2.0 Non-reflective glass with the exception of the following cases:
Display cases across all nine galleries will have to be constructed with the use of reflective ASTM C1172 - Laminated Architectural Flat Glass as per Specification Division 10 requirements.
The following display cases however will be an exception to this change, and shall retain non-reflective ASTM C1172 - Laminated Architectural Flat Glass:
2.1 G102 America by Air DC-102-19a
2.2 G102 America by Air DC-102-19b
2.3 G102 America by Air DC-102-22
2.4 G102 America by Air DC-102-21a-b
2.5 G205 Exploring the Planets DC-205-08
2.6 G206 Destination Moon DC-206-31
2.7 G206 Destination Moon DC-206-42a
2.8 G206 Destination Moon DC-206-42b
2.9 G206 Destination Moon DC-206-42c
2.10 G206 Destination Moon DC-206-42d
Option 3
Option 3.1 - All floor graphic marmoleum to be replaced with graphic-free marmoleum
Option 3.2 - All floor graphic marmoleum to be replaced with carpet with select graphics to remain
Explorations
a. G205, Exploring the Planets
Replace marmoleum with direct print broadloom carpet. Floor graphics to be translated to direct print broadloom carpet.
b. G206, Destination Moon
Replace marmoleum with broadloom carpet. Floor graphics to be translated to direct print broadloom carpet.
c. G207, One World, Connected
Replace marmoleum with direct print broadloom carpet. Floor graphics to be translated to direct print broadloom carpet.
Revolutions
a. G103 Early Flight
Replace marmoleum with broadloom carpet.
b. G105 Reinventing Flight
Replace marmoleum with broadloom carpet. Omit floor graphics.
c. G106 We All Fly
Replace marmoleum with direct print broadloom carpet. Floor graphics to be translated to direct print broadloom carpet.
Specialty
a. G107, Wright Brothers
Replace marmoleum with broadloom carpet.
b. G203, Nation of Speed
Replace marmoleum with broadloom carpet, retain inset floor graphics and/or scenic floor material as originally specified.
Option 3.3 - All floor graphic marmoleum to be replaced with graphic-free broadloom carpet (Option 3 as currently defined in the Deductive Options and in the RFP).
The following flooring options are to be retained for all Options:
102 America by Air is to remain terrazzo as originally specified.
203 Nation of Speed Shop Floor to remain marmoleum as originally specified
Option 4
4.0 Omit AV-206-06 Humans Reach the Moon Video Wall in
Gallery 206 Destination Moon
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-06 G206 and A-6-01 G206 showing omission of AV.
• Date provided by: award date + 5 working days.
Option 5
5.0 Omit DC-206-31 Apollo Command Module case and
replace with glass barrier in Gallery 206 Destination Moon
• Replace display case with 6ft tall glass barrier with a single panel access door with no visual obstruction to the artifact.
• Omit small artifacts, retain Apollo Command Module.
• hsd Redesign: hsd to provide details of glass barrier and plinth that will surround the Apollo Command Module.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• New detail drawing showing details of the glass barrier and plinth.
• Date provided by: award date + 35 working days.
Option 6
6.0 Omit DC-206-38 Lunar Roving Vehicle case and replace
with a frontal glass barrier only in Gallery 206 Destination
Moon
• Replace front glass panel only with a single panel access door with no visual obstruction to the artifact.
• Omit small artifacts, retain Lunar Roving Vehicle only.
• hsd Redesign: hsd to provide details of glass barrier for the Lunar
Roving Vehicle.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• New detail drawing showing details of the front glass panel.
• Date provided by: award date + 35 working days.
Option 7
7.0 Omit DC-206-16 Bezos case and replace with glass
barrier in Gallery 206 Destination Moon
• Replace display case with 6ft tall glass barrier with a single panel access door with no visual obstruction to the artefact.
• hsd Redesign: hsd to provide updated elevation drawing of glass barrier and plinth that will surround the Bezos.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• Amended elevation EX-2-02 G206 showing glass barrier and plinth.
• Date provided by: award date + 35 working days
Option 8: Other Material VE
Gallery 206 – Destination Moon
8.1 Change Display Case DC-206-46 with Glass Box
• Replace cases with three glass box(es), mount catalogue code
B-56, one for each painting.
• hsd Redesign: hsd to provide updated direction for glass box security because two of the paintings are medium security and one is high security. A19740161000, A20100241000 and
A20000455000.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• Date provided by: award date + 15 working days.
8.2 Omit lenticular graphic in Display Case
DC-206-31 (GL-206-670-006)
• Lenticular floor graphic underneath the Apollo 11 Command
Module to be omitted and steel plates forming the display case floor to be powder coated, color will be confirmed following update.
• hsd Redesign: hsd to provide updated floor color.
• Documents provided by hsd:
• Amended drawing EX-5-06 G206 and EX-5-08 G206
• Date provided by: award date + 5 working days.
8.3 Reduce height of large graphics in front of
mezzanine
• Panel heights to be reduced to 4267mm (14’-0”) height, retaining the lower level section that hosts exhibition elements.
• Panels that are effected can be referenced from:
EX-2-01 G206 - A8
EX-2-03 G206 - C1 & C2
EX-2-05 G206 - E3
and detail construction drawing EX-5-24 G206
• hsd Redesign: hsd to issue details depicting new fixing method for shortened panels, and issue artwork and graphic design.
• Documents provided by hsd:
• Amended elevation drawings and graphic reference.
• Amended drawings EX-5-24 G206; EX-2-01 G206; EX-2-03
G206; EX-2-05 G206.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 8: Other Material VE: Gallery 206 Destination Moon
8.4 Change display case DC-206-25 (Starball) to glass
barrier
• Replace display case with extended 6ft tall glass barrier of
Control Panel on its right with a single panel access door with no visual obstruction to the artifact. Retain plinth under artifact and structural mount.
• hsd Redesign: hsd to provide updated elevations showing relocated graphics from wall.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• Additional graphic support structure drawing.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 8: Other Material VE: Gallery 206 Destination Moon
Gallery 207 – One World Connected
8.5 Change display case DC-207-01 (Turbofan Engine) to glass
barrier
• Replace display case with 6ft tall glass barrier around the Turbofan Engine with a single panel hinge access door with no visual obstruction the artifact and structural mount.
• hsd Redesign: hsd to provide details of glass barrier and structural mount.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• New detail drawing showing details of the glass barrier.
• Date provided by: award date + 35 working days.
Option 8: Other Material VE: Galley 207 One World Connected
Gallery 102 – America by Air
8.6 Change curved structures around engines to glass
barrier
• Replace curved structures around engines, Rolls Royce RB211-
22 Turbofan Cutaway and General Electric CF6-6 Turbofan
Cutaway with glass barrier but replace with a square barrier.
• hsd Redesign: hsd to provide details of glass barrier.
• Documents provided by hsd:
• Amended drawing EX-5-03 and EX-5-08 showing omitted curved structures.
• Updated Elevation drawings EX-2-04 and EX-2-05 with glass barrier.
• Date provided by: award date + 25 working days
8.7 Reuse existing 3D human figures
• Retain existing 3D figures and refurbish.
• hsd Redesign: N/A
• Documents provided by hsd: N/A
• Date provided by: N/A
8.8 Reuse existing tactiles for MO-102-01-04
• Retain tactiles and refurbish.
• hsd Redesign: N/A
• Documents provided by hsd: N/A
• Date provided by: N/A
Option 8: Other Material VE: Galley 102 America By Air
Gallery 107 – Wright Brothers
8.9 Change all 3D wall graphics to Wallpaper Print
• Replace all 3D graphics as marked with wallpaper print approx.
surface area 700 sqft.
• hsd Redesign: hsd to review Artwork
• Documents provided by hsd:
• New artwork files.
• New elevation drawings with new graphic references.
• Date provided by: award date + 35 working days.
Option 8: Other Material VE: Gallery 107 Wright Brothers
8.9 Change all 3D wall graphics to Wallpaper Print
• Replace all 3D graphics as marked with wallpaper print approx.
surface area 700 sqft.
• hsd Redesign: hsd to review Artwork.
• Documents provided by hsd:
• New artwork files.
• New elevation drawings with new graphic references.
• Date provided by: award date + 35 working days.
Option 8: Other Material VE: Gallery 107 Wright Brothers
Option 9: Level 1 AV/CI Reductions
Gallery 103 – Early Flight
9.1 Omit one projector from AV-103-03
• Omit one projector and retain software and two projectors, to be reconfigured.
• hsd Redesign: hsd to co-ordinate with sub-consultants to review repositioning of the two remaining projectors and adaptation of software to new ratio.
• Documents provided by hsd:
• Amended AV plan, A-1-06 G103 and A-6-01 G103 showing omission of one projector.
• Date provided by: award date + 15 working days.
Option 9: Level 1 AV/CI Reductions: Gallery 103 Early Flight
Gallery 105 – Reinventing Flight
9.2 Omit two projectors from AV-105-01-04
• Omit two projectors and retain software and two projectors, to be reconfigured.
• hsd Redesign: hsd to co-ordinate with sub-consultants to review repositioning of two remaining projectors and adaptation of software to new ratio.
• Documents provided by hsd:
• Amended AV plan, A-1-06 G105 and A-6-01 G105 showing omission of two projectors.
• Date provided by: award date + 15 working days.
Option 9: Level 1 AV/CI Reductions: Gallery 105 Reinventing Flight
Gallery 106 – We All Fly
9.3 Change CI-106-06 (Flying Cars) with a Flipbook
• Replace CI with one tabloid size flipbook and reader rail.
• hsd Redesign: hsd to review Content co-ordination and adaptation, new graphic layout design and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Flipbook artwork files.
• Reader rail artwork files.
• Amended drawing A-1-07 G106 and A-602 G106 showing omission of CI.
• Updated Graphic Elevation EX-2-06 G106 showing updated graphic layout.
• Reference drawing EX-5-22 G000 showing the Flipbook details.
• Date provided by: award date + 35 working days.
Option 9: Level 1 AV/CI Reductions: Gallery 106 We All Fly
Gallery 205 – Exploring the Planets
9.4 Omit AV-205-01 (Exoplanet) hardware only
• AV hardware to be removed and add software and content to AV-205-09
Drake Equation.
• hsd Redesign: hsd to co-ordinate with sub-consultants, adaptation of software to new ratio and content expansion.
• Documents provided by hsd:
• Amended AV plan, A-1-06 G205 and A-6-01 G205 showing omission of AV hardware.
• Date provided by: award date + 15 working days, software is as per media contract.
Option 9: Level 1 AV/CI Reductions: Gallery 205 Exploring the Planets
9.6 Change CI-206-01 (Early Moon Movies) with new
graphic
• Replace CI with new graphic and extend reader rail.
• hsd Redesign: hsd to provide new graphic design and updated elevations showing extended reader rail. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Updated plan, A-1-07 G206 and A-6-01 G206 showing omission of AV and elevation drawing EX-2-01 G206 with new graphic reference.
• New artwork files.
• Date provided by: award date + 35 working days.
9.7 Omit AV-206-03 (Apollo Explores the Moon)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-06 G206 and A-6-1 G206 showing omission of CI.
• Date provided by: award date + 5 working days.
Option 9: Level 1 AV/CI Reductions: Gallery 206 Destination Moon
Option 10: Level 1 Content Reductions
10.1 Reduce Display Case size DC-206-33 (Lunar
Experiments) by approx. 50%
• Approx. 50% reduction of display case with all artifacts remaining with the exception of the Passive Seismic Experiment
A19730062000 which will be omitted.
• hsd Redesign: hsd to review case layout, content placement, in-case graphics and artwork.
• Documents provided by hsd:
• Amended case layout EX-8-14 G206 and EX-1-08 G206 with updated case sizes, Any related artwork if changes are relevant.
• Date provided by: award date + 35 working days.
10.2 Omit Display Case DC-206-36 (Fuel Transfer Tools)
• Remove case and shorten table to the length of the omitted case.
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• Date provided by: award date + 5 working days.
Option 10: Level 1 Content Reductions: Gallery 206 Destination Moon
10.3 Change display case DC-206-50 (Collins
Chronograph) to niche
• Omit display case and place object on mount in niche within the existing upright structure.
• hsd Redesign: hsd to review niche and mount.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• Date provided by: award date + 35 working days.
10.4 Omit display case DC-206-29 (Map Apollo 8)
• Remove case and artifact and replace with one graphic specified for reader rail.
• Omit artifact, Map Apollo 8.
• hsd Redesign: hsd to provide new graphic design. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
10.5 Omit case DC-206-22 (EMU Repair Kit)
• Replace case with one graphic specified for reader rail.
• Omit artifact, EMU Repair Kit.
• hsd Redesign: hsd to review graphic design, artwork and backwall graphic artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 10: Level 1 Content Reductions
Gallery 107 – Wright Brothers
10.6 Omit pylons
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing EX-2-03 G107 showing omission of pylons.
• Date provided by: award date + 5 working days.
10.7 Omit seats
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd: N/A
• Date provided by: N/A
10.8 Omit tactiles
MO-107-01
MO-107-02
MO-107-03
• Replace RR-107-10 with glass barrier. Retain RR-107-07 and add graphic (due to reaching distance in this section).
• hsd Redesign: technical drawing changes, graphic design and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• New detail drawing.
• New plan drawing.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 10: Level 1 Content Reductions: Gallery 207 Wright Brothers
Option 11: Level 2 AV/CI Reductions
Gallery 205 Exploring the Planets
11.1 Omit CI-205-01/02 ( Tour of the Solar System) and
retain one Touchscreen
• Omit CI kiosk and retain one touchscreen on the opposite end of table. Table to reduce in size as per CI Kiosk dimensions defined in drawing A-1-08 G205.
• hsd Redesign: hsd to co-ordinate with sub-consultants and redesign table end where the CI has been removed.
• Documents provided by hsd:
• Amended drawing A-1-07 G205, A-1-08 G205 and A-6-02
G205 showing omission of CI.
• Detailed table end drawing.
• Date provided by: award date + 35 working days.
11.2 Omit CI-205-04 (Hostile Worlds)
• Omit case and finish end of table with material defined in drawing
EX-5-29 G000
• hsd Redesign: hsd to co-ordinate with sub-consultants and redesign table end where the CI has been removed.
• Documents provided by hsd:
• Amended drawing A-1-07 G205 and A-6-03 showing omission of CI.
• Detailed table end drawing.
• EX5-29 G000 Material Finishes List providing list of materials and finishes.
• Date provided by: award date + 15 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 205 Exploring the Planets
Gallery 206 Destination Moon
11.3 Omit island unit CI-206-02 with table, vertical
upstand and case DC-206-11a&b up-light illumination
(aimed at F1 engine) recessed in vertical upright
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing EX-2-05 G206
• Date provided by: award date + 5 working days.
11.4 Omit CI-206-04 (Bezos Recovery)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-07 G206 and A-6-02 G206 showing omission of CI.
• Date provided by: award date + 5 working days.
11.5 Omit CI-206-05 (A Huge Challenge)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-07 G206 and A-6-01 G206 showing omission of CI.
• Amended elevation drawing EX-2-02 G206.
• Date provided by: award date + 15 working days.
11.6 Omit CI-206-09 (MET Tools)
• Omit CI kiosk and shorten table. Table to reduce in size as per CI
Kiosk dimensions as defined in drawing A-1-08 G205
• hsd Redesign: hsd to review additional graphics and artwork
• Documents provided by hsd:
• Amended drawing A-1-07 G206 and A-6-03 G206 showing omission of CI.
• Amended elevation drawing EX-2-05 G206.
• Date provided by: award date + 15 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 206 Destination Moon
11.7 Omit AV-206-11 (Starball)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-06 G206 showing omission of
AV.
• Date provided by: award date + 5 working days.
11.8 Omit CI-206-06 (Spacesuits/New Equipment &
Skills)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-07 G206 showing omission of
CI.
• Date provided by: award date + 5 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 206 Destination Moon
Gallery 207 One World Connected
11.9 Omit one touchscreen from CI-207-07 (Future Earth)
• Omit one touchscreen, retain two touchscreens and one projector.
• hsd Redesign: hsd to co-ordinate with sub-consultants to reconfigure the remaining units.
• Documents provided by hsd:
• Amended drawing A-1-07 G207 and A-6-01 G207 showing omission of one touchscreen.
• Amended elevation drawing EX-2-05 G207.
• Date provided by: award date + 35 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 207 One World Connected
Gallery 203 Nation of Speed
11.10 Omit AV-203-04-09
• Omit all AV hardware (large projection screen and projectors) and retain lighting with additional lighting tracks.
• hsd Redesign: hsd to co-ordinate with sub-consultants to review lighting and potential support structure once screen has been omitted.
• Documents provided by hsd:
• Amended drawing EX-1-03 G203 and A-1-06, A-6-01
G203 and A-6-02 G203 showing omission of AV.
• Amended drawing EL-1-02 G203 showing lighting layout.
• Date provided by: award date + 35 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 203 Nation of Speed
11.11 Omit CI-203-03
• Replace CI with one graphic specified for reader rail.
• hsd Redesign: hsd to review graphic design and artwork.
Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing A-1-07 G203 and A-6-02 G203 showing omission of CI.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 11: Level 2 AV/CI Reductions: Gallery 203 Nation of Speed
Option 12: Level 2 Content Reductions
12.1 Change display case DC-206-37 (Tools Carrier) with supporting table and graphic.
• Replace display case and supporting table with graphic.
• Omit artifact, Tools Carrier.
• hsd Redesign: hsd to review backwall graphic and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.2 Omit display case DC-206-28 (Apollo TV Camera)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Apollo TV Camera.
• hsd Redesign: hsd to review graphic design and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.3 Omit display case DC-206-40 (Toy, Lunokhod)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Toy, Lunokhod.
• hsd Redesign: hsd to review graphic design and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 12: Level 2 Content Reductions: Gallery 206 Destination Moon
12.4 Omit display case DC-206-41 (Camera Lunar Mapping Apollo)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Camera Lunar Mapping Apollo.
• hsd Redesign: hsd to review graphic design for additional graphic and backwall, new artwork for both. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.5 Omit display case DC-206-01 (Rotating Display of Books)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Rotating Display of Books
• hsd Redesign: hsd to review graphic design and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.6 Omit MO-206-05 (SLS Orion)
• Add/retain: N/A
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing A-1-08 G206 showing omission of MO.
• Date provided by: award date + 5 working days.
12.7 Omit display case DC-206-06 (Primate Capsule Mercury)
• Replace case with graphics and retain reader rail.
• Omit artifact, Primate Capsule Mercury
• hsd Redesign: hsd to review graphic design and artwork. Reader rail to be configured to match existing run
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files
• Date provided by: award date + 35 working days.
12.8 Omit display case DC-206-03 (Toys)
• Omit display case and artifact and retain vertical text panel, re-artworking will be required.
• Omit artifact, Toys.
• hsd Redesign: hsd to review graphic design and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.9 Omit reader rail RR-206-13&14 (under DC-206-40,41,44) with graphic content
• Add: wall mounted case back for DC-206-44
• hsd Redesign: hsd to review case layout, in-case graphic design and artwork
• Documents provided by hsd:
• Amended drawing A-1-09 G206 showing omission of reader rail.
• New case layout drawing.
• New case artwork files, if relevant.
• Date provided by: award date + 35 working days.
12.10 Omit reader rail RR-206-05-09 with graphic content
• Omit all four reader rails with all content, and support display case DC-206-02 with a plinth
• hsd Redesign: hsd to design DC-206-02 case plinth and review content rearrangement inside of case and artwork.
• Documents provided by hsd:
• Amended drawing A-1-09 206 showing omission of reader rail.
• New case layout drawing.
• New case artwork files, if relevant.
• New display case plinth drawing.
• Date provided by: award date + 35 working days.
12.11 Omit display case DC-206-24 (Mercury
Capsule Model)
• Add/retain: N/A
• Omit artifact, Mercury Capsule Model
• hsd Redesign: hsd to design backwall graphic and artwork
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files
• Date provided by: award date + 35 working days.
12.12 Omit Starball artifact and plinth (with
associated graphic panels) and extended glass barrier of Command Module Simulator (CMS)
• Retain glass barrier around CMS only.
• hsd Redesign: hsd to design backwall graphic design and artwork
• Documents provided by hsd:
• Amended drawing EX-2-02 G206 showing omission of startball artifact.
• New artwork files
• Date provided by: award date + 15 working days.
12.13 Omit MO-206-09a-d and table
• Retain vertical text panel and re-artwork table side
• hsd Redesign: hsd to review graphic design and artwork
• Documents provided by hsd:
• Amended drawing A-1-08 G206 showing omission of
AV
• New artwork files
• Date provided by: award date + 35 working days.
12.14 Omit display case DC-206-18 (Space Food)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Space Food.
• hsd Redesign: hsd to design back wall and reader rail graphic and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.15 Change display case DC-206-19 (Apollo 11 knob, casing
Syringe, needle, ampule) with graphic
• Replace case with one graphic specified for reader rail.
• Omit artifact., Apollo 11 knob, casing Syringe, needle, ampule
• hsd Redesign: hsd to design back wall and reader rail graphics and artwork.
Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.16 Omit display case DC-206-20 (Astronaut Hygiene)
• Replace case with one graphic specified for reader rail.
• Omit artifact, Astronaut Hygiene
• hsd Redesign: hsd to design back wall and reader rail graphic and artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
12.17 Omit display case DC-206-21 (Medical Kit) and full reader rail
• Omit display case and reader rail RR-206-17.
• Omit artifact, Medical Kit.
• hsd Redesign: hsd to review back wall graphic design and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case and A-1-09
G206 showing omission of reader rail.
• New artwork files.
• Date provided by: award date + 35 working days.
12.18 Omit display case DC-206-23 (Survival Kit)
• Add/retain: N/A
• Omit artifact, Survival Kit.
• hsd Redesign: back wall graphic design and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 12: Level 2 Content Reductions
Gallery 203 Nation of Speed
12.19 Change display case DC-203-31 with graphic
12.20 Change display case DC-203-34 with graphic
12.21 Change display case DC-203-05 with graphic
12.22 Change display case DC-203-08 with graphic
12.23 Change display case DC-203-26 with graphic
12.24 Change display case DC-203-35 with graphic
12.25 Change display case DC-203-38 with graphic
12.26 Change display case DC-203-44 with graphic
Action for all the above:
• Replace case with one graphic specified for reader rail.
• hsd Redesign: hsd to review graphic design, artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G203 showing omission of all cases.
• New artwork files.
• Date provided by: award date + 35 working days.
12.28 Change case DC-203-42 with graphic
• Replace case with graphic as per the size of case as defined in EX-1-08 G203.
• Omit artifact, Toy Toyota Supra.
• hsd Redesign: hsd to review wall graphic design, artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G203 showing omission of case.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 12: Level 2 Content Reductions: Gallery 203 Nation of Speed
Option 13: Last Resort Deductions
13.1 Omit DC-206-02 (Goddard Flash Powder Experiment) and
plinth
• Add/retain: N/A
• Omit artifact, Goddard Flash Powder Experiment.
• hsd Redesign: hsd to review content revision, backwall graphic design and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New backwall artwork files.
• Date provided by: award date + 35 working days.
13.2 Omit DC-206-07 (Gagarin Bronze Bust)
• Add/retain: N/A
• Omit artifact, Gagarin Bronze Bust.
• hsd Redesign: hsd to design backwall graphic and artwork
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New backwall artwork files.
• Date provided by: award date + 35 working days.
13.3 Change display case DC-206-08 (Mercury freedom 7) to glass barrier
• Replace case with 6ft tall glass barrier.
• hsd Redesign: hsd to provide updated elevation drawing of plinth and glass barrier.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New detail drawing.
• Date provided by: award date + 35 working days.
13.4 Omit display case DC-206-27 (Hatches)
• Omit display case, extend reader rail with graphics to join current reader rails.
• Omit artifact, Hatches.
• hsd Redesign: hsd to review content, reader rail and backwall graphic design and re-artwork. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• New backwall artwork files.
• New reader rail artwork files.
• Date provided by: award date + 35 working days.
Option 13: Last Resort Deductions: Gallery 206 Destination Moon
13.5 Change display case DC-206-13 (Gemini
Capsule) to glass barrier
• Replace case with 12ft tall glass barrier, retain DC-206-12.
• hsd Redesign: plinth and glass barrier, amend DC-206-12 case height to be in line with glass barrier.
• Documents provided by hsd:
• Amended drawing EX-1-08 G 206 showing omission of case.
• New detail drawing.
• Date provided by: award date + 35 working days.
13.6 Omit display case DC-206-44 (Cernan Boots)
• Add/retain: N/A
• Omit artifact, Cernan Boots.
• hsd Redesign: hsd to review content, backwall graphic design and artwork.
• Documents provided by hsd:
• Amended drawing EX-1-08 G 206 showing omission of case.
• New backwall artwork files.
• Date provided by: award date + 35 working days.
13.7 Omit Apollo Command Module glass barrier
• Omit glass barrier and retain ACM and suspend it from ceiling, adding approximately 3 strong backs, also retain graphic panels and media units.
• hsd Redesign: hsd to provide graphic panels and media units re-configuration and structure review.
• Documents provided by hsd:
• New detail drawings as relevant.
• Structural analysis.
• Date provided by: award date + 40 working days.
13.8 Omit display case DC-206-17 (Spacesuit for the
Moon)
• Omit display case and provide corrugated wall cover to mezzanine to size defined in drawing EX-2-02 G206
• Omit artifact, Spacesuit for the Moon
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of case.
• Date provided by: award date + 5 working days.
13.9 Omit Control Panel and glass barrier
• Add/retain: N/A
• Omit artifact, Command Module Simulator.
• hsd Redesign: hsd to design backwall graphics and artwork
• Documents provided by hsd:
• Amended drawing EX-2-02 G206.
• Date provided by: award date + 15 working days.
13.10 Omit mezzanine wall graphics
• Replace mezzanine wall graphics with corrugated mezzanine wall cover to the floor to size defined in drawing EX-2-02 G206.
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended plan EX-2-08 G206 showing omission of wall graphics.
• Date provided by: award date + 5 working days.
13.11 Omit display DC-206-26a-c
• Omit display cases and surrounding built out structure and cover mezzanine wall with corrugated to size defined in drawing EX-2-
02 G206
• Omit artifacts, Canister, Lithium Hydroxide, Command Module, Cartridge, Lithium Hydroxide Canister, Lithium Hydroxide
Canister, Gene Kranz Vest and Apollo 13 Mission Patch.
• hsd Redesign: N/A
• Documents provided by hsd:
• Amended drawing EX-1-08 G206 showing omission of display case.
• Date provided by: award date + 5 working days.
Gallery 207 One World Connected
13.12 Omit CI-207-09 (Globe Annulus)
• Omit touch screens and replace with one push button for each touchscreen (6) and angled graphic structures to the size of the specified reader rail on drawing EX-5-02 G207.
• hsd Redesign: hsd to co-ordinate with sub-consultants to review push buttons and review graphic design and artwork, development of angled graphics. Reader rail to be configured to match existing run.
• Documents provided by hsd:
• Amended drawing A-1-07 G207 showing omission of CI
• Detail drawing of angled graphic fixtures replacing touch screens.
• New artwork files.
• Date provided by: award date + 35 working days.
Option 13: Last Resort Deductions: Gallery 207 One World Connected
Gallery 105 Reinventing Flight
13.13 Omit Gallery 105 Reinventing Flight
Option 13: Last Resort Deductions: Gallery 105 Reinventing Flight