17-L. Heritage Hills Specifications sealed 02-20-2026 revised.pdf
PDF 1 MB Posted
- Attached to
- Heritage Hills PID New Improvement Project
- Solicitation number
- BVB 416-26 KD
- Issued by
- Orange County, Texas
About this file
Heritage Hills PID Improvements Project Summary
This specification document details the site amenities development requirements for the Heritage Hills Public Improvement District in Amarillo, Texas, issued by the City of Amarillo under Bid #BVB-416-26 and Project #P25-009. The project encompasses grading, sidewalks, concrete paving, trees, lawn, irrigation systems, masonry, and related landscape construction activities designed to enhance pedestrian connectivity and improve neighborhood aesthetics. The work includes site drainage, electrical systems, landscape irrigation installation, and landscape planting. Prepared by Turner LandArchitecture LLC and dated January 2026, the specifications establish detailed requirements for contractor performance, including preconstruction conferences to be held no later than 15 days after agreement execution, submittal of the contractor's construction schedule within 30 days of commencement, and submittal of a comprehensive submittal schedule within 10 days thereafter. The contractor must maintain 24-hour monitoring of temporary facilities and complete all work within the established contract timeline, with substantial completion required before final acceptance procedures commence.
The project specifications require contractors to provide all labor and materials for site amenities development, with particular emphasis on quality assurance, material testing, and compliance with ACI 530.1/ASCE 6/TMS 602 masonry standards. The document specifies performance requirements for concrete masonry units, reinforced masonry construction, mortar composition, and grouting procedures, with preconstruction testing conducted by owner-engaged independent testing agencies at the contractor's expense if materials fail compliance requirements. Contractors must establish temporary facilities including water service, electrical power, drainage, sanitary facilities, and protective enclosures at their own cost, with all temporary facilities to be removed by substantial completion. The specifications include a 60-day maintenance period following substantial completion, during which the landscape contractor retains control of water meters. Material sourcing requirements mandate that masonry materials, aggregates, and cementitious products be obtained from sources within 500 miles of the project site to support regional material sourcing objectives.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JAN 2026 City of Amarillo Bid # BVB-416-26 KD TLA Project # P25-009
Specifications for the Furnishing of Labor and Materials for the Site Amenities Development of
Heritage Hills PID Improvements
Amarillo, Texas
A Public Improvement District Project Amarillo, Texas
Turner LandArchitecture LLC 905 South Fillmore Street
Suite 702
Amarillo, Texas 79101
806.432.9400
The project documents for the Landscape Architectural portions of the Heritage Hills PID Improvements have been produced under the responsible control of the following Texas Registered Design Professionals:
042113 - Masonry
042200 – Concrete Unit Masonry
047200 – Cast Stone Masonry
321313 – Concrete Paving
328400 -- Planting Irrigation
329113 -- Soil Preparation
329200 -- Turf and Grasses
329300 -- Plants
02-20-2026
Heritage Hills PID Improvements 01010
Turner LandArchitecture LLC JAN 2026
DIVISION 1 General Project Conditions 01010 Summary of Work
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
PROJECT DESCRIPTION
The Project consists of grading,sidewalks, trees, lawn, irrigation, masonry, and related items for Heritage Hills, Public Improvement District, located in Amarillo, Texas as shown on Contract Documents prepared by Turner LandArchitecture, LLC dated January, 2026.
The Work includes, but is not limited to, grading, drainage, concrete, electrical systems, landscape irrigation system, and landscape planting.
CONTRACTOR USE OF PREMISES
General: During the construction period the Contractor shall have full use of the premises for construction operations, including use of the site. The Contractor's use of the premises is limited only by the Owner's right to perform construction operations with its own forces or to employ separate contractors on portions of the project.
OWNER-FURNISHED ITEMS
Sleeves crossing streets and electrical conduit to electrical panels will be provided by owner.
END OF SECTION 01010
Heritage Hills PID Improvements Page 1 of 1
DIVISION 1 General Project Conditions 01030 Alternates
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies administrative and procedural requirements for Alternates.
Definition: An Alternate is an amount proposed by Bidders and stated on the Bid Form for certain construction activities defined in the Bidding Requirements that may be added to or deducted from Base Bid amount if the Owner decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems or installation methods described in Contract Documents.
Coordination: Coordinate related Work and modify or adjust adjacent Work as necessary to ensure that Work affected by each accepted Alternate is complete and fully integrated into the project.
Notification: Immediately following the award of the Contract, prepare and distribute to each party involved, notification of the status of each Alternate. Indicate whether Alternates have been accepted, rejected or deferred for consideration at a later date. Include a complete description of negotiated modifications to Alternates.
Schedule: A "Schedule of Alternates" is included at the end of this Section. Specification Sections referenced in the Schedule contain requirements for materials and methods necessary to achieve the Work described under each Alternate.
Include as part of each Alternate, miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation whether or not mentioned as part of the Alternate.
PART 2 PRODUCTS (Not Applicable).
PART 3 EXECUTION
SCHEDULE OF ALTERNATES
END OF SECTION 01030
Heritage Hills PID Improvements Page 1 of 2
DIVISION 1 General Project Conditions 01040 Project Coordination
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies administrative and supervisory requirements necessary for Project coordination including, but not necessarily limited to:
Coordination.
Administrative and supervisory personnel.
General installation provisions.
Coordination: Coordinate construction activities included under various Sections of these Specifications to assure efficient and orderly installation of each part of the Work. Coordinate construction operations included under different Sections of the Specifications that are dependent upon each other for proper installation, connection, and operation.
Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.
Make adequate provisions to accommodate items scheduled for later installation.
Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.
Prepare similar memoranda for the Owner and separate Contractors where coordination of their Work is required.
Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
Staff Names: Within 15 days of Notice to Proceed, submit a list of the Contractor's principal staff assignments, including the Superintendent and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.
PART 2 PRODUCTS (Not Applicable).
PART 3 EXECUTION
Heritage Hills PID Improvements Page 2 of 2
GENERAL INSTALLATION PROVISIONS
Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.
Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items.
Provide attachment and connection devices and methods necessary for securing Work. Secure Work true to line and level. Allow for expansion and structure movement.
Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed Work to obtain the best visual effect. Refer questionable choices to the Landscape Architect/Architect for final decision.
Recheck measurements and dimensions, before starting each installation.
Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.
Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Landscape Architect/Architect for final decision.
CLEANING AND PROTECTION
During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where applicable, such exposures include, but are not limited to, the following:
Excessive static or dynamic loading.
Excessive internal or external pressures.
Excessively high or low temperatures.
Thermal shock.
Excessively high or low humidity.
END OF SECTION 01040
Heritage Hills PID Improvements Page 1 of 3
DIVISION 1 General Project Conditions 01200 Project Meetings
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies administrative and procedural requirements for project meetings including but not limited to:
Pre-Construction Conference.
Pre-Installation Conferences.
Coordination Meetings.
Progress Meetings.
PRE-CONSTRUCTION CONFERENCE
Schedule a pre-construction conference and organizational meeting at the Project site or other convenient location no later than 15 days after execution of the Agreement and prior to commencement of construction activities. Conduct the meeting to review responsibilities and personnel assignments.
Attendees: The Owner, the Landscape Architect, and their consultants, the Contractor and its superintendent, major subcontractors, manufacturers, suppliers and other concerned parties shall each be represented at the conference by persons familiar with and authorized to conclude matters relating to the Work.
Agenda: Discuss items of significance that could affect progress including such topics as:
Tentative construction schedule.
Critical Work sequencing.
Designation of responsible personnel.
Procedures for processing field decisions and Change Orders.
Procedures for processing Applications for Payment.
Distribution of Contract Documents.
Submittal of Shop Drawings, Product Data and Samples.
Preparation of record documents.
Use of the premises.
Office, Work and storage areas.
Equipment deliveries and priorities.
Safety procedures.
First aid.
Security.
Housekeeping.
Working hours.
Heritage Hills PID Improvements Page 2 of 3
PRE-INSTALLATION CONFERENCES
Conduct a pre-installation conference at the site before each construction activity that requires coordination with other construction. The Installer and representatives of manufacturers and fabricators involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. The Contractor is to advise the Landscape Architect & Owner of scheduled meeting dates.
Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for:
Contract Documents.
Options.
Related Change Orders.
Purchases Deliveries.
Shop Drawings, Product Data and quality control Samples.
Possible conflicts.
Compatibility problems.
Time schedules.
Weather limitations.
Manufacturer's recommendations.
Compatibility of materials.
Acceptability of substrates.
Temporary facilities.
Space and access limitations.
Governing regulations.
Safety.
Inspection and testing requirements.
Required performance results.
Recording requirements.
Protection.
Record significant discussions and agreements and disagreements of each conference, along with the approved schedule. Distribute the record of the meeting to everyone concerned, promptly, including the Owner and Landscape Architect. Do not proceed if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene the conference at the earliest feasible date.
Attendees: In addition to representatives of the Owner and Landscape Architect, each subcontractor, supplier or other entity concerned with current progress or involved in planning, coordination or performance of future activities shall be represented at these meetings by persons familiar with the Project and authorized to conclude matters relating to progress.
Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the current status of the Project.
Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
Review the present and future needs of each entity present, including such items as:
Interface requirements.
Time.
Sequences.
Deliveries.
Heritage Hills PID Improvements Page 3 of 3
Off-site fabrication problems.
Access.
Site utilization.
Temporary facilities and services.
Hours of Work.
Hazards and risks.
Housekeeping.
Quality and Work standards.
Change Orders.
Documentation of information for payment requests.
Reporting: No later than 3 days after each progress meeting date, distribute copies of minutes of the meeting to each party present and to other parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.
Schedule Updating: Revise the construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue the revised schedule concurrently with the report of each meeting.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION 01200
Heritage Hills PID Improvements Page 1 of 6
01300 Submittals
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies administrative and procedural requirements for submittals required for performance of the Work, including;
Contractor's construction schedule.
Submittal schedule.
Daily construction reports.
Shop Drawings.
Product Data.
Samples.
Administrative Submittals: Refer to other Division-1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to:
Permits.
Applications for payment.
Performance and payment bonds.
Insurance certificates.
List of Subcontractors.
The Schedule of Values submittal is included in Section "Applications for Payment."
Inspection and test reports are included in Section "Quality Control Services."
Submittal of Project photographs is included under Section "Construction Photographs."
SUBMITTAL PROCEDURES
Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination. The Landscape Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
Allow two weeks for initial review. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. The Landscape Architect will promptly advise the Contractor when a submittal being processed must be delayed for coordination. If an intermediate submittal is necessary, process the same as the initial submittal. Allow two weeks for reprocessing each submittal. No extension of Contract Time will be authorized because of failure to transmit submittals to the Landscape Architect sufficiently in advance of the Work to permit processing.
Submittal Preparation: Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
Provide a space approximately 4" x 5" on the label or beside the title block on Shop Drawings to record the Contractor's review and approval markings and the action taken.
Heritage Hills PID Improvements Page 2 of 6
Include the following information on the label for processing and recording action taken.
Project name.
Date.
Name and address of Landscape Architect.
Name and address of Contractor.
Name and address of subcontractor.
Name and address of supplier.
Name of manufacturer.
Number and title of appropriate Specification Section.
Drawing number and detail references, as appropriate.
Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Transmit each submittal from Contractor to Landscape Architect/Architect using a transmittal form. Submittals received from sources other than the Contractor will be returned without action. On the transmittal Record relevant information and requests for data. On the form, or separate sheet, record deviations from Contract Document requirements, including minor variations and limitations. Include Contractor's certification that information complies with Contract Document requirements.
CONTRACTOR'S CONSTRUCTION SCHEDULE
Schedule: Prepare a fully developed, horizontal bar-chart type Contractor's construction schedule. Submit within 30 days of the date established for "Commencement of the Work".
Provide a separate time bar for each significant construction activity. Provide a continuous vertical line to identify the first working day of each week. Use the same breakdown of units of the Work as indicated in the "Schedule of Values".
Within each time bar indicate estimated completion percentage in 10 percent increments.
As Work progresses, place a contrasting mark in each bar to indicate Actual Completion.
Prepare the schedule on a sheet, or series of sheets, of stable transparency, or other reproducible media, of sufficient width to show data for the entire construction period.
Secure time commitments for performing critical elements of the Work from parties involved.
Coordinate each element on the schedule with other construction activities; include minor elements involved in the sequence of the Work. Show each activity in proper sequence.
Indicate graphically sequences necessary for completion of related portions of the Work.
Coordinate the Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests and other schedules.
Indicate completion in advance of the date established for Substantial Completion.
Indicate Substantial Completion on the schedule to allow time for the Landscape Architect/Architect's procedures necessary for certification of Substantial Completion. have completed their assigned portion of the Work and are no longer involved in construction activities.
Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.
SUBMITTAL SCHEDULE
After development and acceptance of the Contractor's construction schedule, prepare a complete schedule of
Heritage Hills PID Improvements Page 3 of 6 submittals. Submit the schedule within 10 days of the date required for establishment of the Contractor's construction schedule.
Coordinate submittal schedule with the list of subcontracts, schedule of values and the list of products as well as the Contractor's construction schedule.
Prepare the schedule in chronological order; include submittals required during the first 90 days of construction. Provide the following information:
Scheduled date for the first submittal.
Related Section number.
Submittal category.
Name of subcontractor.
Description of the part of the Work covered.
Scheduled date for resubmittal Scheduled date the Landscape Architect/Architect's final release or approval.
Distribution: Following response to initial submittal, print and distribute copies to the Landscape Architect, Owner, subcontractors, and other parties required to comply with submittal dates indicated. Post copies in the Project meeting room and field office.
When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.
Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.
Orders and requests of governing authorities.
Change Orders received, implemented.
Services connected, disconnected.
Equipment or system tests and start-ups.
Partial Completions, occupancies.
Substantial Completions authorized.
SHOP DRAWINGS
Submit newly prepared information, drawn to accurate scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not considered Shop Drawings.
Shop Drawings include fabrication and installation drawings, setting diagrams, schedules, patterns, templates and similar drawings. Include the following information:
Dimensions.
Identification of products and materials included.
Compliance with specified standards.
Notation of coordination requirements.
Notation of dimensions established by field measurement.
Sheet Size: Except for templates, patterns and similar full- size Drawings, submit Shop Drawings on sheets at least 8-1/2" x 11" but no larger than 24” x 36”".
Initial Submittal: Submit 2 blue or black line prints for the Landscape Architect’s review; one will be returned.
Final Submittal: Submit 3 blue line prints and 2 additional prints where required for maintenance manuals, Heritage Hills PID Improvements Page 4 of 6 plus the number of prints needed by the Landscape Architect for distribution. 2 prints will be retained; the remainder returned.
One of the prints returned shall be marked-up and maintained as a "Record Document".
Do not use Shop Drawings without an appropriate final stamp indicating action taken in connection with construction.
Coordination drawings are a special type of Shop Drawing that show the relationship and integration of different construction elements that require careful coordination during fabrication or installation to fit in the space provided or function as intended. Preparation of coordination Drawings is specified in section "Project Coordination" and may include components previously shown in detail on Shop Drawings or Product Data. Submit coordination Drawings for integration of different construction elements. Show sequences and relationships of separate components to avoid conflicts in use of space.
PRODUCT DATA
Collect Product Data into a single submittal for each element of construction or system. Product Data includes printed information such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams and performance curves. Where Product Data must be specially prepared because standard printed data is not suitable for use, submit as “Shop Drawings”.
Mark each copy to show applicable choices and options. Where printed Product Data includes information on several products, some of which are not required, mark copies to indicate the applicable information. Include the following information:
Manufacturer's printed recommendations.
Compliance with recognized trade association standards.
Compliance with recognized testing agency standards.
Application of testing agency labels and seals.
Notation of dimensions verified by field measurement.
Notation of coordination requirements.
Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed.
Preliminary Submittal: Submit a preliminary single-copy of Product Data where selection of options is required.
Submittals: Submit 2 copies of each required submittal; submit 4 copies where required for maintenance manuals.
The Landscape Architect/Architect will retain one, and will return the other marked with action taken and corrections or modifications required. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
Distribution: Furnish copies of final submittal to installers, subcontractors, suppliers, manufacturers, fabricators, and others required for performance of construction activities.
Show distribution on transmittal forms. Do not proceed with installation until an applicable copy of Product Data applicable is in the installer's possession. Do not permit use of unmarked copies of Product Data in connection with construction.
SAMPLES
Submit full-size, fully fabricated Samples cured and finished as specified and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture and pattern.
Mount, display, or package Samples in the manner specified to facilitate review of qualities indicated. Prepare Samples to match the Landscape Architect's Sample. Include the following:
Generic description of the Sample.
Sample source.
Product name or name of manufacturer.
Heritage Hills PID Improvements Page 5 of 6
Compliance with recognized standards.
Availability and delivery time.
Submit Samples for review of kind, color, pattern, and texture, for a final check of these characteristics with other elements, and for a comparison of these characteristics between the final submittal and the actual component as delivered and installed.
Where variation in color, pattern, texture or other characteristics are inherent in the material or product represented, submit multiple units (not less than 3), that show approximate limits of the variations.
Preliminary submittals: Where Samples are for selection of color, pattern, texture or similar characteristics from a range of standard choices, submit a full set of choices for the material or product. Preliminary submittals will be reviewed and returned with the Landscape Architect/Architect's mark indicating selection and other action.
Submittals: Except for Samples illustrating assembly details, workmanship, fabrication techniques, connections, operation and similar characteristics, submit 3 sets; one will be returned marked with the action taken. Maintain sets of Samples, as returned, at the Project site, for quality comparisons throughout the course of construction. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
Sample sets may be used to obtain final acceptance of the construction associated with each set.
Distribution of Samples: Prepare and distribute additional sets to subcontractors, manufacturers, fabricators, suppliers, installers, and others as required for performance of the Work. Show distribution on transmittal forms.
Field Samples: specified in individual Sections are special types of Samples. Field Samples are full-size examples erected on site to illustrate finishes, coatings, or finish materials and to establish the standard by which the Work will be judged.
Comply with submittal requirements to the fullest extent possible. Process transmittal forms to provide a record of activity.
LANDSCAPE ARCHITECT/ARCHITECT'S ACTION
Except for submittals for record, information or similar purposes, where action and return is required or requested, the Landscape Architect/Architect will review each submittal, mark to indicate action taken, and return promptly.
Compliance with specified characteristics is the Contractor's responsibility.
Action Stamp: The Landscape Architect/Architect will stamp each submittal with a uniform, self-explanatory action stamp. The stamp will be appropriately marked, as follows, to indicate the action taken:
Final Unrestricted Release: Where submittals are marked "Approved," that part of the Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.
Final-But-Restricted Release: When submittals are marked "Approved as Noted," that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents; final acceptance will depend on that compliance.
Returned for Resubmittal: When submittal is marked "Not Approved, Revise and Resubmit," do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity.
Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.
Do not permit submittals marked "Not Approved, Revise and Resubmit" to be used at the Project site, or elsewhere where Work is in progress.
Other Action: Where a submittal is primarily for information or record purposes, special processing or other activity, the submittal will be returned, marked "Action Not Required".
PART 2 PRODUCTS (Not Applicable).
Heritage Hills PID Improvements Page 6 of 6
PART 3 EXECUTION (Not Applicable).
END OF SECTION 01300
Heritage Hills PID Improvements Page 1 of 5
01500 Temporary Facilities
PART 1 - GENERAL
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies requirements for temporary services and facilities, including utilities, construction and support facilities, security and protection.
Temporary utilities required include but are not limited to:
Water service and distribution.
Temporary electric power and light.
Telephone service.
Storm and sanitary sewer.
Temporary construction and support facilities required include but are not limited to:
Temporary heat.
Field offices and storage sheds.
Temporary roads and paving.
Sanitary facilities, including drinking water.
Dewatering facilities and drains.
Temporary enclosures.
Hoists and temporary elevator use.
Temporary Project identification signs and bulletin boards.
Waste disposal services.
Rodent and pest control.
Construction aids and miscellaneous services and facilities.
Security and protection facilities required include but are not limited to:
Warning signs, lights.
Environmental protection.
SUBMITTALS
QUALITY ASSURANCE
Regulations: Comply with industry standards and applicable laws and regulations if authorities having jurisdiction, including but not limited to:
Building Code requirements.
Health and safety regulations.
Utility company regulations.
Police, Fire Department and Rescue Squad rules.
Environmental protection regulations.
PROJECT CONDITIONS
Conditions of Use: Keep temporary services and facilities clean and neat in appearance. Operate in a safe and efficient manner. Take necessary fire prevention measures. Do not overload facilities, or permit them to interfere with progress. Do not allow hazardous dangerous or unsanitary conditions, or public nuisances to develop or persist on the site.
Heritage Hills PID Improvements Page 2 of 5
PART 2 - PRODUCTS
General: Provide new materials; if acceptable to the Landscape Architect/Architect, undamaged previously used materials in serviceable condition may be used. Provide materials suitable for the use intended.
EQUIPMENT
General: Provide new equipment; if acceptable to the Landscape Architect/Architect, undamaged, previously used equipment in serviceable condition may be used. Provide equipment suitable for use intended.
Water Hoses: Provide 3/4" heavy-duty, abrasion-resistant, flexible rubber hoses 100 ft. long, with pressure rating greater than the maximum pressure of the water distribution system; provide adjustable shut-off nozzles at hose discharge.
Electrical Outlets: Provide properly configured NEMA polarized outlets to prevent insertion of 110-120 volt plugs into higher voltage outlets. Provide receptacle outlets equipped with ground-fault circuit interrupters, reset button and pilot light, for connection of power tools and equipment.
Electrical Power Cords: Provide grounded extension cords; use "hard-service" cords where exposed to abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords, if single lengths will not reach areas where construction activities are in progress.
Lamps and Light Fixtures: Provide general service incandescent lamps of wattage required for adequate illumination.
Provide guard cages or tempered glass enclosures, where exposed to breakage. Provide exterior fixtures where exposed to moisture.
Heating Units: Provide temporary heating units that have been tested and labeled by UL, FM or another recognized trade association related to the type of fuel being consumed.
Temporary Offices: Provide prefabricated or mobile units or similar job-built construction with lockable entrances, operable windows and serviceable finishes. Provide heated and air- conditioned units on foundations adequate for normal loading.
Temporary Toilet Units: Provide self-contained single-occupant toilet units of the chemical, aerated recirculation, or combustion type, properly vented and fully enclosed with a glass fiber reinforced polyester shell or similar nonabsorbent material.
First Aid Supplies: Comply with governing regulations.
Fire Extinguishers: Provide hand-carried, portable UL-rated, class "A" fire extinguishers for temporary offices and similar spaces. In other locations provide hand-carried, portable, UL-rated, class "ABC" dry chemical extinguishers, or a combination of extinguishers of NFPA recommended classes for the exposures.
Comply with NFPA 10 and 241 for classification, extinguishing agent and size required by location and class of fire exposure.
PART 3 - EXECUTION
INSTALLATION
Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve the Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.
Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed, or are replaced by authorized use of completed permanent facilities.
TEMPORARY UTILITY INSTALLATION
General: Engage the appropriate local utility company to install temporary service or connect to existing service.
Where the company provides only part of the service, provide the remainder with matching, compatible materials and equipment; comply with the company's recommendations. Arrange with the company and existing users for a time when service can be interrupted, where necessary, to make connections for temporary services. Provide adequate capacity at each stage of construction. Prior to temporary utility availability, provide trucked-in services. Obtain easements to bring temporary utilities to the site, where the Owner's easements cannot be used for that purpose.
Heritage Hills PID Improvements Page 3 of 5
Use Charges: Cost or use charges for temporary facilities are not chargeable to the Owner or Landscape Architect/Architect, and will not be accepted as a basis of claims for a Change Order.
Water Service: Install water service and distribution piping of sizes and pressures adequate for construction until permanent water service is in use.
Sterilization: Sterilize temporary water piping prior to use.
Temporary Electric Power Service: Provide weatherproof, grounded electric power service and distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload protected disconnects, automatic ground-fault interrupters and main distribution switch gear. Except where overhead service must be used, install electric power service underground.
Power Distribution System: Install wiring overhead, and rise vertically where least exposed to damage. Where permitted, wiring circuits not exceeding 125 Volts, AC 20 ampere rating, and lighting circuits may be nonmetallic sheathed cable where overhead and exposed for surveillance.
Temporary Lighting: Whenever overhead floor or roof deck has been installed, provide temporary lighting with local switching. Install and operate temporary lighting that will fulfill security and protection requirements, without operating the entire system, and will provide adequate illumination for construction operations and traffic conditions.
Temporary Telephones: Provide temporary telephone service for all personnel engaged in construction activities, throughout the construction period. Install telephone on a separate line for each temporary office and first aid station.
Where an office has more than two occupants, install a telephone for each additional occupant or pair of occupants.
At each telephone, post a list of important telephone numbers. Cellular telephones may be used in lieu of conventional land line telephone service.
Sewers and Drainage: If sewers are available, provide temporary connections to remove effluent that can be discharged lawfully. If sewers are not available or cannot be used, provide drainage ditches, dry wells, stabilization ponds and similar facilities. If neither sewers nor drainage facilities can be lawfully used for discharge of effluent, provide containers to remove and dispose of effluent off the site in a lawful manner. Filter out excessive amounts of soil, construction debris, chemicals, oils and similar contaminants that might clog sewers or pollute waterways before discharge. Connect temporary sewers to the municipal system as directed by the sewer department officials.
Maintain temporary sewers and drainage facilities in a clean, sanitary condition. Following heavy use, restore normal conditions promptly. Provide earthen embankments and similar barriers in and around excavations and subgrade construction, sufficient to prevent flooding by runoff of storm water from heavy rains.
TEMPORARY CONSTRUCTION AND SUPPORT FACILITIES INSTALLATION
Locate field offices, storage sheds, sanitary facilities and other temporary construction and support facilities for easy access. Maintain temporary construction and support facilities until near Substantial Completion. Remove prior to Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to the Owner.
Provide incombustible construction for offices, shops and sheds located within the construction area, or within 30 feet of building lines. Comply with requirements of NFPA 241.
Temporary Heat: Provide temporary heat required by construction activities, for curing or drying of completed installations or protection of installed construction from adverse effects of low temperatures or high humidity. Select safe equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce the ambient condition required and minimize consumption of energy.
Heating Facilities: Except where use of the permanent system is authorized, provide vented self-contained LP gas or fuel oil heaters with individual space thermostatic control. Use of gasoline-burning space heaters, open flame, or salamander type heating units is prohibited.
Field Offices: None required for this project.
Heritage Hills PID Improvements Page 4 of 5
Storage and Fabrication Sheds: Install storage and fabrication sheds, sized, furnished and equipped to accommodate materials and equipment involved, including temporary utility service. Sheds may be open shelters or fully enclosed spaces within the building or elsewhere on the site.
Temporary Paving: Construct and maintain temporary roads and paving to adequately support the indicated loading and to withstand exposure to traffic during the construction period. Locate temporary paving for roads, storage areas and parking where the same permanent facilities will be located. Review proposed modifications to permanent paving with the Landscape Architect/Architect.
Sanitary facilities include temporary toilets, wash facilities and drinking water fixtures. Comply with regulations and health codes for the type, number, location, operation and maintenance of fixtures and facilities. Install where facilities will best serve the Project's needs. Provide toilet tissue, paper towels, paper cups and similar disposable materials for each facility. Provide covered waste containers for used material.
Toilets: Install self-contained toilet units. Shield toilets to ensure privacy. Use of pit-type privies will not be permitted.
Wash Facilities: Install wash facilities supplied with potable water at convenient locations for personnel involved in handling materials that require wash-up for a healthy and sanitary condition. Dispose of drainage properly. Supply cleaning compounds appropriate for each condition.
Drinking Water Facilities: Provide containerized tap-dispenser bottled-water type drinking water units, including paper supply.
Dewatering Facilities and Drains: For temporary drainage and dewatering facilities and operations not directly associated with construction activities included under individual Sections, comply with dewatering requirements of applicable Division-2 Sections. Where feasible, utilize the same facilities. Maintain the site, excavations and construction free of water.
Temporary Enclosures: Provide temporary enclosure for protection of construction in progress and completed, from exposure, foul weather, other construction operations and similar activities. Where heat is needed provide temporary enclosures where there is no other provision for containment of heat. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects. Install tarpaulins securely, with incombustible wood framing and other materials. Close openings of 25 square feet or less with plywood or similar materials. Close openings through floor or roof decks and horizontal surfaces with load-bearing wood-framed construction.
Project Identification and Temporary Signs: Prepare project identification and other signs of the size indicated; install signs where indicated to inform the public and persons seeking entrance to the Project. Support on posts or framing of preservative treated wood or steel. Do not permit installation of unauthorized signs.
Project Identification Signs: Engage an experienced sign painter to apply graphics.
Comply with details indicated.
Collection and Disposal of Waste: Collect waste from construction areas and elsewhere daily. Comply with requirements of NFPA 241 for removal of combustible waste material and debris. Enforce requirements strictly. Do not hold materials more than 7 days during normal weather or 3 days when the temperature is expected to rise above 80 deg F (27 deg C). Handle hazardous, dangerous, or unsanitary waste materials separately from other waste by containerizing properly. Dispose of material in a lawful manner.
Stairs: Until permanent stairs are available, provide temporary stairs where ladders are not adequate. Cover finished permanent stairs with a protective covering of plywood or similar material so finishes will be undamaged at the time of acceptance.
Heritage Hills PID Improvements Page 5 of 5
Temporary Fire Protection: Until fire protection needs are supplied by permanent facilities, install and maintain temporary fire protection facilities of the types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 10 "Standard for Portable Fire Extinguishers," and NFPA 241 "Standard for Safeguarding Construction, Alterations and Demolition Operations."
Locate fire extinguishers where convenient and effective for their intended purpose.
Store combustible materials in containers in fire-safe locations.
Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire protection facilities, stairways and other access routes for fighting fires. Prohibit smoking in hazardous fire exposure areas. Provide supervision of welding operations, combustion type temporary heating units, and similar sources of fire ignition.
Security Enclosure and Lockup: Install substantial temporary enclosure of partially completed areas of construction.
Provide locking entrances to prevent unauthorized entrance, vandalism, theft and similar violations of security.
Storage: Where materials and equipment must be stored, and are of value or attractive for theft, provide a secure lockup. Enforce discipline in connection with the installation and release of material to minimize the opportunity for theft and vandalism.
Environmental Protection: Provide protection, operate temporary facilities and conduct construction in ways and by methods that comply with environmental regulations, and minimize the possibility that air, waterways and subsoil might be contaminated or polluted, or that other undesirable effects might result. Avoid use of tools and equipment which produce harmful noise. Restrict use of noise making tools and equipment to hours that will minimize complaints from persons or firms near the site. Comply with all provisions of the EPA National Pollution Discharge Elimination Standard (NPDES) and all measures shown and required on the soil erosion and sedimentation control plan. The Contractor is responsible for securing copies of the Owner’s SWPPP & NOI and for complying with and supplementing any additional measures as may be required by law. Contractor is also responsible for filing any additional permits to the EPA and binding all of his subcontractors to that process.
Maintenance: Maintain facilities in good operating condition until removal. Protect from damage by freezing temperatures and similar elements. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation and similar facilities on a 24-hour day basis where required to achieve indicated results and to avoid possibility of damage.
Protection: Prevent water filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations.
Termination and Removal: Unless the Landscape Architect/Architect requests that it be maintained longer, remove each temporary facility when the need has ended, or when replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with the temporary facility. Repair damaged Work, clean exposed surfaces and replace construction that cannot be satisfactorily repaired. Materials and facilities that constitute temporary facilities are property of the Contractor. The Owner reserves the right to take possession of Project identification signs.
Where the area is intended for landscape development, remove soil and aggregate fill that does not comply with requirements for fill or subsoil in the area. Remove all materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances which might impair growth of plant materials or lawns. Repair or replace street paving, curbs and sidewalks at the temporary entrances, as required by the governing authority.
At Substantial Completion, clean and renovate permanent facilities that have been used during the construction period, including but not limited to:
A. Replace significantly worn parts and parts that have been subject to unusual operating conditions.
B. Replace lamps that are burned out or noticeably dimmed by substantial hours of use.
END OF SECTION 01500
Heritage Hills PID Improvements Page 1 of 4
01700 Project Closeout
PART 1 GENERAL
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
This Section specifies administrative and procedural requirements for project closeout, including but not limited to:
Inspection procedures.
Project record document submittal.
Operating and maintenance manual submittal.
Submittal of warranties.
Final cleaning.
Closeout requirements for specific construction activities are included in the appropriate Sections in Divisions-2 through -16.
SUBSTANTIAL COMPLETION
Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request.
Advise Owner of pending insurance change-over requirements.
Submit specific warranties, workmanship bonds, maintenance agreements, final certifications and similar documents.
Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities; include occupancy permits, operating certificates and similar releases.
Make final change-over of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of change-over in security provisions.
Compl…