Questions - Responses - R3-11.17.26.xlsx

XLSX spreadsheet 40 KB Posted

Attached to
Window Cleaning and Maintenance
Solicitation number
15F06727Q0000010
Issued by

About this file

This file is a Questions and Responses document addressing 125 inquiries from prospective quoters regarding FBI Criminal Justice Information Services (CJIS) Division window cleaning and maintenance services solicitation 15F06727Q0000010.

The requirement encompasses scheduled interior and exterior window cleaning, annual window inspections, specialized glazing maintenance, and emergency response services for the CJIS campus in Clarksburg, West Virginia (1000 Custer Hollow Rd, Clarksburg, WV 26306). The contract will be firm-fixed-price with a base year plus four one-year options, with performance beginning January 21, 2027, and the current contract expiring January 20, 2027. Quotations are due November 24, 2026, at 10:00 AM ET. This is a 100% small business set-aside. The site visit is November 6, 2026, at 9:00 AM ET, with Visitor Access Request forms due by November 2, 2026. The incumbent contractor is AFM. Quotations should be submitted to ckesselman@fbi.gov, and invoicing shall be processed via IPP.gov on a per-job basis following completion and Government acceptance. Base year cleaning covers approximately 322,049 square feet across multiple buildings including the CJIS Main Building (interior and exterior, with two annual exterior cleanings), Biometrics Technology Center (BTC), Visitors Center, Daycare Center, Service Center, Parking Garage, Police Building, and Automotive Building. Option Years 1 and 2 add specialized interior core cleaning and stair cleaning. All on-site personnel require FBI Security Programs Manager approval and escorted access with LAR (Logical Access Request) paperwork completion; the FBI will provide escorts and initiate all security processing post-award. Emergency response requires 24-hour arrival capability with separate hourly rates submitted at quotation. The contract includes limitations on subcontracting per FAR 52.219-14, with contractors unable to pay more than 50% of Government payments to non-similarly situated subcontractors.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

15F06727Q0000010 - Window Cleaning and Maintenance Services
#ReferenceQuoter's QuestionsGovernent's ResponseAmendment 1Amendment 2Amendment 3
1GeneralIs this a brand new contract OR if there is (was) an incumbent performing these services.New contract (base year + 4 (one-year options). Current contract expires on 01/20/2027.X
2Quotation due date/SF1449The RFQ document states quotations are due November 24, 2026 at 10:00 AM ET, while the SAM.gov notice description states November 18, 2026 at 2:00 PM ET, and the SF 1449 form (Block 8) states November 16, 2026 at 11:00 AM ET. Could you please confirm which date and time governs, and whether an amendment will be issued to reconcile them?Quotes are due 11/24/2026 at 10:00AM, ET. The SF1449 and SAM.gov decription has been revised to reflect this.X
3Invoicing/Statement of WorkStatement of Work directs invoices to central_invoices@fbi.gov, while the SF 1449 states invoices should be submitted via IPP and not to central_invoices@fbi.gov. Could you please confirm the correct invoicing channel?IPP.gov is the Government's invoicing platform. The SOW has been revised to reflect this.X
4Site VisitIs attendance at the site visit mandatory for a quotation to be considered technically acceptable?Attendance is not mandatory, but strongly encouraged.X
5Site VisitWould there be any possibility of visiting the site on an alternate date?Site Visit is date has been moved to 11/06/2026, 9AM, ET, to allow time for VAR submittal and approval. No other alternate is provided.X
6Site VisitMay a subcontractor representative attend the site visit on behalf of the prime contractor?Yes. A sub can attend.X
7Site VisitWhat is the deadline for submitting the Visitor Access Request form for the site visit?VARs shall be submitted no later than 11/02/2026 in order for security to conduct review and provide approval.X
8Site VisitWill the attendee list be shared after the visit?No. The Government will not distribute the site visit attendee list.X
9Site VisitHow should we send forms that contain SSNs?VARs shall be submitted to ckesselman@fbi.gov.X
10Site VisitSite visit approval submission method, and check-in instructions for site visit?Approval will be provided by security to the CO. Once aproval is granted, CO will provided site visit instructions via email to the attending company's.X
11IncumbentFor market research purposes, could you please share the previous contract amount, the previous awardee, and the previous period of performance for this requirement, if available?AFM is the current contractor. The period of performance ends 01/20/2027.X
12X
13NAICS CodeNAICS: The RFQ letter lists 561720 ($22.0M) and the SF1449 lists 561790 ($9M). Which NAICS code and size standard apply?The NAICS code is 561720. Size standard is $22M. The SF1449 has been revised to reflect this.X
14ClausesThe SF1449 clause, provision and attachment sections are marked "intentionally left blank," and 52.212-5 is referenced but not attached. Please provide the full clause list, including whether 52.219-14 Limitations on Subcontracting, 52.222-41 with WD 2015-4353, and 52.228-5 apply.See attachment "15F06727Q0000010 - SF1449 - R1.pdf"X
15ClausesPlease provide the applicable clauses and provisions, including the FAR 52.212-5 attachment referenced in SF1449 Block 27a and any limitations-on-subcontracting clause or agency deviation. The SF1449 sections for clauses and provisions are marked intentionally blank.See attachment "15F06727Q0000010 - SF1449 - R1.pdf"X
16PricingOption prices: Does "option prices must include the special work" mean the Option 1 (Stair 6) and Option 2 (BTC interior cores) areas only, or other work too?Yes. Option Year 1 pricing shall include the additional BTC Stair 6 cleaning, and Option Year 2 pricing shall include the additional BTC interior curtain wall cores cleaning. Base and ALL option years (1/4) must also include all regularly scheduled cleaning and inspection services required by the SOW.X
17Inspection Day RateIs the inspection day rate in the supporting schedule evaluated, and how many inspection days does the Government expect?Offerors shall provide an annual firm-fixed price for all inspection services required by the SOW for each contract period. Offerors are responsible for estimating the number of inspection days necessary. The inspection day rate is supporting pricing information only; the annual firm-fixed price will be used for evaluation.X
18RepairsWould glazing repair or replacement work be ordered under this contract with Davis-Bacon wage rates, and is a West Virginia contractor license required?Glazing repairs and replacements may be ordered on a case-by-case basis, subject to separate pricing, funding, and written Contracting Officer authorization. Applicable Davis-Bacon labor requirements will be determined based on the scope of each order. Contractors are responsible for obtaining and maintaining any West Virginia licenses required for the work performed.X
19SecurityTo meet the 1/21/2027 start, by what date do personnel forms need to reach the FBI after award? Can escorted access (FD-816/FD-484) be used for the first cleaning while recurring-access paperwork is processed?See question #64X
20AnchoringWill the Government accept portable, non-penetrating davit/counterweight systems on the Main Building roof, and what does the CJIS Safety approval submittal need to include?See question #57X
21Prime contractor eligibilityMay ROA compete under the proposed arrangement? Are any tasks required to be performed directly by ROA employees?Yes. If they meet the standards of the solicitation.X
22ExperienceMay the documented experience and resources of named, committed subcontractors satisfy the technical experience requirements, or must the comparable projects have been performed by the proposing entity itself? Are there minimum years of experience or project-size requirements?See question #53X
23Sub-Contracting LimitationsWhich limitations on subcontracting apply, and how would work performed by similarly situated small-business subcontractors be treated? Please confirm the applicable clauses and measurement period.FAR 52.219-6 and FAR 52.219-14 are incorporated into the solicitation. The Contractor shall not pay more than 50% of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Work performed by qualifying similarly situated subcontractors is excluded from this limitation; however, any work further subcontracted by those entities will count toward the limitation.
Compliance will be measured at the end of the base contract period and each subsequent option period. The solicitation will be amended to reflect the appropriate selection under FAR 52.219-14(f)(1).X
24Cleaning quantities and inspection scope:Do the listed square-footage totals include both interior and exterior glass surfaces and the Main Building’s second annual cleaning? Could you provide a building-by-building breakdown and confirm that annual inspections cover both the Main Building and BTC?See question #56X
25Personnel access and startupWhich screening requirements and forms apply to recurring personnel and emergency responders? How should contractors reconcile the SOW’s 60-day advance submission requirement with the anticipated award date and January 21, 2027 start?Packets of forms for site access will be provided to the selected/awarded contractor. Typically there is a 2 week turnaround once completed forms are turned in to security access.X
26Emergency response and repair pricing:Please confirm that emergency labor rates must be submitted initially, while repairs and replacements are quoted separately after a requirement is identified. How will written authorization, funding and site access be coordinated to meet the 24-hour response requirement?If an emergency happens the contractor has a 24 response to to arrive onsite to evaluate and make safe a broken window and then provide an estimate for the repair.X
27Additional qualification requirementsPleaase identify any required licenses, insurance limits, bonds or specific personnel certifications beyond the safety and access requirements already described.The solicitation does not establish specific insurance limits, bonding requirements, or additional personnel certifications beyond those identified in the solicitation and SOW Contractors are responsible for obtaining and maintaining all applicable federal, state, and local licenses, permits, and insurance required to perform the services.X
28IncumbentCould you provide the current incumbent’s legal name, contract number, most recent annual recurring contract value, and any publicly releasable historical emergency-service volume?AFM is the current contractor. The period of performance ends 01/20/2027. The Government will not provide incumbent historical emergency-service volume as part of this solicitation. Publicly available contract award information may be obtained through open source searches by the Contractor as part of their own Market Research. Offerors shall prepare their quotations based on the requirements identified in the solicitation and SOW.X
29Sub-ContractingBeyond the standard limitations on subcontracting applicable to a 100% small business set-aside, does this requirement impose any additional restriction on the use of subcontractors? We also confirm our understanding that all personnel performing on site must meet the SOW Section 8.2 access requirements (FBI Security Programs Manager approval, including escorted access where applicable).The Government does not impose additional restrictions on the use of subcontractors beyond those established in the solicitation and applicable federal regulations. The prime contractor remains responsible for contract performance and compliance with all contractual requirements.
All personnel, including subcontractor personnel, performing work on-site must comply with the security and access requirements outlined in Section 8.2 of the SOW, including FBI Security Programs Manager approval and escorted access, as applicable.X
30InsurancePlease state the required minimum insurance types and amounts.The solicitation does not establish specific minimum insurance types or coverage amounts. Contractors are responsible for maintaining any insurance required by applicable federal, state, and local laws and regulations.X
31Relevant ExperienceMay the offeror's relevant experience examples include work performed by a proposed subcontractor?See question #53X
32Square FootageFor the twice-a-year Main Building cleaning, how many square feet of glass are on the Main Building versus the other buildings? Could you share building heights, the number of floors, and any elevation drawings?Drawings will be provided as needed to the successful bidder.X
33Attachment 2 - Pricing ScheduleAttachment 2’s “Recurring FFP Pricing” sheet has no base-year annual-total formula in F5, while F11 sums F5. The SF1449 also appears to omit base inspection CLIN 0002. Please provide a corrected workbook/form confirming all ten recurring CLINs.Attachment 2, Recurring FFP Pricing, and the SF 1449 will be corrected through a solicitation amendment to ensure all ten recurring CLINs are accurately reflected, including Base Year Inspection CLIN 0002. Offerors shall use the revised documents when preparing and submitting their quotations.X
34Section 7 of SOWPlease confirm whether the stated annual square footage includes both glass faces and the Main Building’s second annual cleaning. Could you provide a building-level area/frequency schedule and the available curtain-wall drawings referenced in SOW Section 7?See question #38 and #56X
35AccessSOW Section 8 references forms submitted 60 days before tasks. Please confirm the onboarding process supporting the January 21 start and approved backup personnel needed for 24-hour emergency response.See question #70X
36InvoicingCould you please clarify the invoicing and payment schedule for these services? Specifically, may the contractor submit an invoice after each scheduled cleaning event has been completed and accepted by the Government, including the two annual cleanings of the CJIS Main Building? Alternatively, are monthly progress invoices permitted, or must the contractor wait until all services under each annual CLIN have been completed and accepted before invoicing?The Contractor shall submit invoices following completion of the required services and acceptance by the Government. Monthly progress invoicing is not permitted.X
37ExperienceCan we use our named subcontractors’ comparable project experience for Factor 3?See question #53X
38Section 7 of SOWSection 7 of the SOW mentions the unclassified curtain wall drawings can be provided on request. Could we request those, along with a campus site plan showing each building, so we and our team can plan equipment access and the 9-foot perimeter wall openings?Drawings will be provided as needed to the successful bidderX
39DrawingsCould you please provide the available curtain-wall drawings for our review? The drawings will assist us in evaluating access requirements, equipment selection, fall-protection needs, and the overall technical approach.Drawings will be provided as needed to the successful bidderX
40DrawingsCould you also provide the available unclassified curtain-wall drawings and confirm inspections cover both the Main Building and BTC?Drawings will be provided as needed to the successful bidderX
41Ceiling Height/Number of light fixturesFor the hanging ceiling lights and high dusting in the Visitors Center and the two atriums, about how high are the ceilings, and how many hanging fixtures are there?18 Lights in the Barrel vault and 32 in the Visitors atrium.X
42IncumbentCould you share the current contract number for the AFM contract and its annual value, if available?Publicly available federal contract award information may be obtained through FPDS-NG or other open source/public sources available as part of contractor's market research.X
43Roughly how often have emergency window-securing calls come up under the current contract (for example, per year)? This would help us set reasonable emergency rates.At most once a year.X
44Window countSee question #56X
45For the annual inspection of the CJIS Main Building and BTC, about how many window units or linear feet of curtain wall should we plan to inspect?See question #56X
46Glass Sq. FeetCould you share an approximate breakdown of the 230,000 sq ft of glass by building (CJIS Main, BTC, Visitors Center, Service Center, Police Services Building and Daycare Center), and the approximate height or number of stories of each?See question #59. Square footage update is on sheet #2 and approx. sq. ft. totals in SOW, Section 2.1.6.X
47Security/accessHow should we handle the 60-day personnel-screening lead time if award is closer to the January 21 start?See question #70X
48SF1449Should the SF1449’s zero quantities be one annual lot per CLIN?Yes. Quantities have been updated.X
49Six-month extensionHow should the six-month extension be priced/evaluated?The solicitation will be amended to clarify this methodology.X
50Sub-contractingIs the subcontracting limit measured by each contract year or each order?Compliance with the limitations on subcontracting will be measured at the end of the base contract period and at the end of each subsequent option period, in accordance with FAR 52.219-14(f)(1). The solicitation will be amended to reflect the appropriate measurement period.X
51ClausesCould you provide the complete clause set, including the referenced FAR 52.212-5? Please confirm paid sick leave/H&W, option-year wage adjustments, insurance and applicable security/FASCSA requirements.Duplicate. Clauses have been added/updated. See SF1449 attachment.X
52GeneralWould you consider a WOSB/EDWOSB set-aside under the rule of two in FAR 19.1505 (a reasonable expectation of offers from two or more WOSBs/EDWOSBs at a fair market price, where the NAICS is on SBA's eligible list), and a 15-minute capability conversation, by email if you prefer? A one-line pass is fine, and if another office handles this, a name is plenty.This requirement has been established as a 100% small-business set-aside based on its acquisition planning and market research. The Government does not anticipate changing the set-aside designation for this solicitation. All eligible small businesses, including WOSBs and EDWOSBs, are encouraged to submit quotations in accordance with the solicitation requirements.
The Government will not conduct individual capability discussions during the solicitation period. All solicitation-related questions must be submitted in accordance with the instructions established in the RFQ.X
53ExperienceCleaning would be done by our subcontractor, can the relevant experience examples come from jobs they've done?Yes, that experience would be acceptable; however, the general contractor should possess sufficient relevant experience to effectively oversee and guide the subcontractor throughout the performance of the work. At a minimum, the general contractor should be able to demonstrate successful completion of at least three similar projects within the past five years that are comparable in scope, complexity, and technical requirements to the work being performed. This ensures the contractor has the expertise necessary to provide appropriate oversight, direction, and quality control for the subcontractor's activities.X
54SOW 7SOW 7 says the curtain wall drawings may be provided on request, and we'd love to get a copy if possible. They'd help a lot with planning the fall protection, especially since we weren't sure which building is Building 5 or where the fixed cable system is on it and the BTC.The Sucessful bidder would be provided drawings if work on the curtain wall system is needed. The fall protection is not identified on the curtain wall drawings.X
55Pricing/Hanging LightsFor pricing, could you share how the 230,000 square feet breaks down by building? It would also help to know roughly how many hanging lights are in the Visitors Center and the two Main Building atriums, and about how high up they are.The Barrel Vault hallway has 18 hanging lights, the Visitors Atrium has 32 hanging lights, the Visitors Center has 10 hanging lights. See Sheet #2X
56SOW Section 2.1SOW Section 2.1 states the campus has approximately 230,000 square feet of window glass cleaned once a year, and SOW Section 2 requires two cleanings yearly of the CJIS Main Building. What is the approximate glass square footage for each building, and does the 230,000 square feet include the second yearly cleaning of the Main Building?See Sheet #2X
57SOW Section 2.1.5SOW Section 2.1.5 refers to "Building 5" and its partial fixed fall protection system. Which of the buildings listed in SOW Section 2 is Building 5, and where is the fixed fall protection located on Building 5 and the BTC?See updated SOW. The Main Building is Building 5.X
58SOW Section 2SOW Section 2 lists a yearly window inspection of the CJIS Main Building and the BTC Building, while SOW Section 2.1.2 refers only to the Main Building. Does the yearly inspection cover the Main Building only, or both the Main Building and the BTC?The yearly window inspection covers both the CJIS Main Building and the BTC.X
59SOW Section 2.1/RFQ Section 5.BHow many stories, or what height, is each building, and is roof access allowed for rope access or swing stage work? (SOW Section 2.1; RFQ Section 5.B)CJIS Main is 3 stories (~16'-6"each) aboveground and the BTC is 4 stories (~18' per floor) above ground.X
60SOW Section 2.1SOW Section 2.1 states a restriction on the size and weight of equipment and a nine-foot width limit. What is the equipment weight or ground-load limit, and which lift types are allowed, such as boom lifts, scissor lifts, or swing stages? (RFQ Section 5.B)On CJIS Square the GVW limit is 19,000 lbs. During a recent cleaning the contractor used a JCB S4046E with success while cleaning the interior of CJIS Main barrel vault and Visitors Atrium.X
61SOWSOW Section 2.1 requires cleaning inside and outside of all exterior windows "except where otherwise noted." Are all interior faces included, and what are the approximate ceiling heights in the Visitors Center, Main Building Visitor Atrium, and Main Building Employee Atrium, where SOW Section 2.1.5 requires high dusting and hanging-light cleaning?The majority of interior wall surfaces are approximately 9 feet high. Notable exceptions include the Building 5 hallway, which is approximately 33 feet in height, and portions of the Visitor Center, where wall surfaces reach approximately 20 feet in height.X
62SOWWill water and electrical power be available to the contractor on site? (SOW Section 2.1)Yes, water and power are available. Some locations do not have easy access, so use long hoses.X
63SOWWhere may contractor crews park and stage lifts, equipment, and trailers? (SOW Section 2.1 states that storage space on site may be available.)FBI will designate a temporary laydown area for equipment.X
64SOWSOW Section 8.2 states that the FBI Security Programs Manager determines whether access is escorted or unescorted. Will window cleaning crews be escorted or unescorted, will the FBI provide escorts, and which of the security forms listed in SOW Section 8.2 will apply?All window cleaning crews will be escorted by an FBI employee. Workers will need to complete LAR paper work before starting.X
65SOWSOW Section 8.2 states that the FBI Security Programs Manager determines whether access is escorted or unescorted. Will window cleaning crews be escorted or unescorted, will the FBI provide escorts, and which of the security forms listed in SOW Section 8.2 will apply?All window cleaning crews will be escorted by an FBI employee. Workers will need to complete LAR paper work before starting.X
66SOWCan the most recent window inspection findings report (SOW Section 2.1.3) be shared with quoters? (Q&A item 11 identifies AFM as the current contractor.)The Sucessful bidder would be provided a complete set.X
67Could you confirm whether a qualified proposed subcontractor's representative may attend the site visit on behalf of the prime offeror, how to submit the visit request form and the deadline for access approval? Also, can the proposed subcontractor's directly relevant window maintenance and glazing repair experience be used to establish technical acceptability, subject to prime oversight and all applicable small-business subcontracting rules?Yes, the qualified subcontractor can attend the site visit. all paperwork will need completed before the 11/2/26 deadline. Please see the response to question #53X
68RFQUnder RFQ sections 5–6, may a prime demonstrate relevant experience/resources through a named proposed subcontractor performing that work, with experience clearly attributed, or must the prime independently possess that experience? What commitment evidence is required?Please see the response to question #53X
69For recurring cleaning, glazing inspections/repairs and emergency responders, which escorted/unescorted access and investigation tiers apply? RFQ section 7 says classified information and FBI system access are not required, while SOW section 8.2 describes several tiers. Does the FBI initiate and sponsor required processing after award, and must any personnel already hold approvals at quotation or award?The FBI will initiate and sponsor all required processing following contract award. All personnel working on site must be granted LAR access prior to the commencement of any work.X
70SOW Section 8.2SOW section 8.2 describes post-award forms based on assignment length/nature and a 60-day submission lead time, alongside separate short-visit provisions. Which personnel does that lead time cover here? If counted from January 21, 2027, it falls on November 22, before the November 24 quote deadline. What onboarding schedule should quoters use?There will be time post award for the contractor to submitt access forms to get crews approved.X
71How should approved primary and backup emergency responders obtain after-hours access to meet the requirement to secure damaged openings within 24 hours? Are escorts/interim approvals available, or must responders be fully preapproved before performance?The COR for the contract would arrainge access, but the responding crew would already need have an approved LAR to be placed on the access list.X
72Square footageCould you provide the approximate glass area by building? Please also confirm whether the 230,000 sq. ft. figure includes the second annual cleaning of the CJIS Main Building.See Sheet #2, updated SOW, solicitaiton documents.x
73CLIN QuantitiesCLIN quantities: Attachment 2 shows a quantity of 0 and no unit for each CLIN. Should each CLIN be priced as 1 Job, or as 1 Year?Quantity updated. Each CLIN covers the complete required annual scope, including multiple scheduled visits where applicable. See Attachment 2 - Pricing Schedule that shall be submitted as pricing submittal per RFQ.x
74DrawingsAre unclassified curtain wall or elevation drawings available, as referenced in SOW Section 7? They would help us plan anchorage and lift positions.Drawings will be provided as needed to the successful bidderx
75Daycare Center WindowsAre there required work windows or exclusion-zone restrictions for the Daycare Center?We would just have to work around nap time.x
76InspectionIs the annual inspection of the CJIS Main Building a 100% unit-by-unit inspection? Does the BTC inspection have the same scope?Yes 100% for both buildingsx
77Utilities and StagingWill the Government provide water and electrical connections, and can you designate a lay-down or staging area for equipment?Water and Electrical connections are available. A lay-down/ staging area can be available.x
78SOW Section 2Five smaller structures on top of the parking garage attached to the BTC appeared to be glass-covered stairwell tops during the site visit. We could not identify them expressly in the October 29 SOW or Questions/Responses R1. SOW sections 2 and 2.1 include BTC cleaning and broadly describe exterior windows and sloped glass, while sections 2.1.5 and 2.1.6 separately identify BTC Stair 6 as Option Year 1 work.

Are these five garage stairwell structures included in the recurring cleaning scope? If so, please identify the glass surfaces to clean, including interior and/or exterior faces, frequency, and applicable contract periods.

Are their areas already included in the published square-foot totals, and are these structures separate from the Option Year 1 BTC Stair 6 work? Please provide their approximate glass area and any available unclassified detail showing the scope and access/fall-protection constraints.

Are these structures also included in the BTC annual inspection and findings-report scope?These stairwells are now included in the cleaning. But not included in the inspection. See Sheet 2 and updated SOW.x
79Window CleaningAre there any required cleaning seasons, spacing between Main Building cleanings, or completion windows?Spring and Fallx
80InvoicingCan completed visits can be invoiced separately?Yes.x
81ClausesOption-year wage adjustments. Which clause or mechanism governs changes to required wages and fringe benefits?See Clause 52.222-43 and 52.222-41x
82Place of PerformanceCan you post a map or provide addresses for the listed locations in the RFP?1000 Custer Hollow Rd, Clarksburg, WV 26306x
83SOW Section 8.2- AccessFacility access processing for off-site contract management. Our firm would perform as prime contractor with all contract administration performed remotely from our North Carolina office. All on-site work would be performed by subcontractor personnel, who will complete the access processing described in SOW Section 8.2. Please confirm whether a responsible manager who will not require access to FBI facilities, information, or IT systems must also submit the SF-85, FD-857a, and FD-258 fingerprint package, or whether that processing applies only to personnel requiring access. Relatedly, the SAM.gov notice summary states that the Project Manager must hold a current CJIS Security Awareness Training certificate. Please advise whether that certificate is required for a manager who performs no on-site work and requires no facility or system access.The manager would still need to complete the access forms.x
84Insurance CertificateInsurance certificates. Please confirm whether certificates of insurance evidencing the coverage listed in the notice are required with the quotation, or whether they may be provided after award and before performance begins.This can be provided after award.x
85The SOW provides for inspections and repair/replacement as needed, but we have not identified a fixed number of windows requiring replacement or their measurements. Our potential glazing subcontractor indicates that the actual glass types and dimensions are important to quote replacement work reliably.

Could the Government please advise whether existing window schedules, glazing drawings, standard or typical dimensions, previous inspection reports, or estimates of anticipated repairs/replacements are available to offerors? If so, could these be furnished through a SAM.gov amendment or official question-and-answer posting for equal access?

If no dimensions or quantities are available, please clarify which repair/replacement unit rates must be included before award and how varying quantities or sizes will be priced and authorized under this requirement. We understand individual replacements may require inspection and Government approval; we do not want to assume how pricing must be structured.Please see the response to question #32x
86What are the minimum insurance requirements (general liability, automobile liability, workers' compensation, and any umbrella), if any, for this contract?See Question #27x
87Is a performance bond and/or payment bond required?See Question #27.x
88May background forms (SF-85, fingerprints, and related packages) be submitted immediately after award so contractor personnel can be cleared before the January 21, 2027 start date?Yesx
89My understanding is that the campus staff prefers total crew of ~4 people for ease of management since they need to be escorted. Also, I understand that the previous contractor conducted the cleaning/ high dusting work in about 3 weeks for the whole campus. Is that generally correct?Yes that is correct. The latest cleaning took 11 business days. But there were no weather delays.x
90FAR 52.217-8Six-month extension (FAR 52.217-8, Q&A 49). Q&A 49 says the solicitation will be amended to explain how the extension is priced and evaluated. Will that amendment be issued before 11/24/2026, and will the extension be added to the evaluated price?Six month extension pricing is not part of the quote submission or evaluation.x
91InspectionAnnual inspection (SOW 2.1.2, Q&A 58). For the exterior of the CJIS Main Building and the BTC, does the Government expect a hands-on, lift-access inspection of every window unit each year, or a visual inspection of all units with close-up checks where defects are seen?Correct, visual only. With close-up inspection of defects. A lift is not required for the inspection.x
92CJIS Main second cleaning (Q&A R2, Sheet 2). Sheet 2 lists the second Main Building cleaning as outside only (79,776 sq ft). Please confirm the Main Building interior glass is cleaned once a year.Yes.x
93Quantities/FrequncyQ&A Sheet2 lists annual totals of 320,049 / 322,299 / 466,697 / 320,049 / 320,049 square feet, while the RFQ/SOW summaries retain approximately 230,000 / 234,000 / 377,000. Should quotations use Sheet2's building-level quantities and annual totals? Sheet2 includes a second Main Building exterior cleaning but no second interior-cleaning row; please confirm whether Main Building interior glass is cleaned once or twice annually.See Updated Sheet 2 and the updated SOW Section 2.x
94MeasurementsWould you be able to provide the approximate dimensions (height and width) and/or total square footage of the windows for each building?See question #59. Square footage update is on sheet #2 and approx. sq. ft. totals in SOW, Section 2.1.6.x
95General/Document RequestIf available, any existing window schedules, building specifications, or other documentation containing these measurementsSee all updated solicitation documents/amendments/Q&A/associated documents for this requirement on SAM.govx
96TravelFor an out-of-area prime contractor, is travel reimbursable with pre-approval, or must travel be included inside the firm-fixed prices?SOW Section 10 - Travel and Other Direct Costsx
97PriceConfirm the evaluated price is the sum of the 10 recurring cleaning and inspection FFP CLINs only, with emergency hourly rates excluded.Yes. Please follow the insturctions and evaluation criteria within the RFQ.x
98Equipment IngressWhat is the designated ingress and egress route for equipment required to clean the interior barrel windows on the front side of CJIS? Which specific doorway or entrance is expected to be used, and what are the clear opening dimensions (width and height) of that doorway?The door in question is a double door. Approxiametly 6 foot opening. The center post is removable. The JCB S4046E fit with the railing folded.x
99Upper Atrium Deck AccessWhat is the expected route for moving equipment to and from the upper deck of the atrium? Will the same entrance and route referenced above be used? If a different entrance is required, please identify the designated doorway and provide its clear opening dimensions (width and height).The lift is tramed through the building.x
100Lower Atrium Deck AccessWhat are the clear opening dimensions (width and height) of the doorway providing equipment access to the lower atrium deck? Please also confirm whether this is a single-door or double-door entrance. If it is a double door entryway, is there a stationary support post in between both doors when opened? If there is a stationary post, can it be temporarily removed for equipment entry.The door in question is a double door. Approxiametly 6 foot opening. The center post is removable. The JCB S4046E fit with the railing folded.x
101EquipmentIf entry for equipment is a standard single door, can you confirm the manufacturer and model number of the equipment previously used to clean the interior atrium windows? JCB S4046E, is 46" wide and will not fit through a standard single door opening as stated previously.The door in question is a double door. Approxiametly 6 foot opening. The center post is removable. The JCB S4046E fit with the railing folded.x
102Blinds and Window AccessWill the opening and closing of blinds, window coverings, and/or window casings be handled by the contractor or by FBI personnel? If the contractor is expected to handle these items, please clarify which party will assume responsibility and liability in the event that a blind, window covering, frame, casing, or related component is damaged during normal opening, closing, or access.FBI Personnel will operate the blinds.x
103Pedestrian Traffic and Work-Area Safety:During window cleaning operations, will the applicable walkways and work areas be temporarily restricted to cleaning personnel for safety purposes? If pedestrian traffic will continue through or near the work area, will FBI personnel provide someone to monitor or control access, or will the contractor be responsible for providing personnel and/or establishing the necessary barriers and traffic-control measures?This would depend on the area in question. If the area can not be closed FBI Personnel will assist the contractor to maintain a safe working environment.x
104InvoicingCould you please clarify the response to Question 36 regarding invoicing for the two separate cleanings performed during the year?Invoicing shall be submitted/processed on a per job/work completed basis.x
105InvoicingWill the contractor submit a separate invoice upon completion of each cleaning—one invoice after the first annual cleaning is completed and a second invoice after completion of the second cleaning?Invoicing shall be submitted/processed on a per job/work completed basis.x
106InvoicingClarify the payment terms and expected payment timeframe to the primary contractor following submission and approval of each invoice, including any documentation or acceptance requirements that must be completed before payment can be processed.Invoicing shall be submitted/processed on a per job/work completed basis.x
107Quote submittalPlease confirm quotes go to ckesselman@fbi.gov and whether quotes may be submitted by a prime that has not attended the siteYes.x
108Glass Sq. FeetPlease provide the glass square footage by building and the number of floors/roof anchor points used by the incumbent for the Main Building second cleaning.See Sheet 2.x
109Will the Government permit the use of a tethered or untethered small, unmanned aircraft system (drone) to perform exterior window cleaning on CJIS campus buildings, operated under FAA Part 107 by certified remote pilots and using NDAA-compliant equipment? If permitted, please identify any additional approvals, airspace or security requirements, or restrictions on flight areas, hours or data capture (for example, cameras) that would apply.No.x
110FAR 52.219-14FAR 52.219-14: Amendment 2 revised the limitations-on-subcontracting clause per the Q&A. Please confirm the percentage of the contract price the prime contractor must perform with its own employees under the revised clause, and whether specialized glazing repair work is treated differently from routine cleaning for that calculation.See question #23 and #50. In accordance with FAR 52.219-14, for services contracts, the Contractor shall not pay more than 50% of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities.x
111Sheet 2 - AmendementAmendment 2 added an updated Sheet 2 with revised square footage. Please confirm the Sheet 2 figures are the final quantities for pricing each building, and the total exterior glass square footage.See recent updated Sheet 2 and solictation document attachments.x
112TransitionIs there a phase-in period with the incumbent before the January 21, 2027 start?Yes.x
113Emergency Securing of Bullet-Resistant GlazingFor damaged bullet-resistant glazing or other security-sensitive openings, are there specific requirements for temporary securing or weatherproofing, beyond standard commercial board-up procedures? Must temporary protection maintain a specified level of ballistic or physical security?This would depend on the situation. And location of the BR glass.x
114Bullet-Resistant Glazing Specifications and Qualifications - SOWCould the Government identify the applicable ballistic protection ratings, glazing specifications, and any specialized installer qualifications required for these systems?Typically level 3. The glass would need to be replaced by an actual glazing company.x
115Historical Emergency Repair Types/Clarify Question 43Without requesting specific security-sensitive information, could the Government indicate whether previous emergency calls have generally involved conventional window glass, curtain wall systems, or specialized bullet-resistant glazing?Generally previous calls concerned conventional glass.x
116Is interior window cleaning limited exclusively to high or elevated glass surfaces, as indicated during the walkthrough, or does it include the interior-facing surfaces of all exterior windows, regardless of height?Clean interior-facing surfaces of all exterior windows above 8'x
117Interior Glass Square FootageSheet 2 identifies 41,679 SF of interior cleaning at the CJIS Main Building and 9,665 SF at the Biometrics Technology Center (BTC). Do these quantities represent only elevated interior glass, or do they include all interior-facing exterior window surfaces, including those accessible from floor level?Clean interior-facing surfaces of all exterior windows above 8'x
118Interior Glass Square FootageCould the Government identify the specific areas and glass surfaces included in these quantities?Refere to Sheet 2 of the Q&A document for building specific quanitities. Interior cleaning includes the applicable interior-facing exterior glass surfaces above eight (8) feet, as clarified in Questions 116 and 117.x
119Does the interior cleaning scope include the undersides (interior-facing surfaces) of skylights, sloped glass roof systems, barrel-vault glazing, and overhead atrium glass?Yes.x
120Does the interior cleaning scope include the undersides (interior-facing surfaces) of skylights, sloped glass roof systems, barrel-vault glazing, and overhead atrium glass?

Specifically, please clarify whether these surfaces are included in the following areas:

- CJIS Main Building — Barrel Vault hallway

- CJIS Main Building — Visitors Atrium

- CJIS Main Building — Employee Atrium

- Visitors Center

- Biometrics Technology Center, where applicable

If included, are these surfaces incorporated into the interior square footage quantities in Sheet 2, or are they additional to those quantities?Sheet #2 it incorporates all SF to be cleaned.x
121Sheet 2 identifies two exterior cleanings for the CJIS Main Building but only one interior cleaning quantity.
Please confirm that interior window cleaning is required once annually at the CJIS Main Building, while exterior window cleaning is required twice annually.This is correct.x
122Would the Government be able to provide photographs, architectural drawings, elevations, or other available documentation identifying the interior atrium glass, skylights, and elevated glazing surfaces included in the cleaning scope?
This can be provided after award.x
123Would the Government consider including elevated interior partition glass, glass walls, and high ledges as a separately priced optional service?
If so, could the Government identify the applicable locations and approximate quantities, or establish a separate pricing provision for these additional services?Any additional work will be discussed at a later date.x
124Working Hours1. Are there restrictions on working hours, weekends, or overtime? 2. Employee Eligibility Are employees with valid Employment Authorization Documents (EADs) or permanent resident cards (Green Cards) eligible to work at this facility, or is U.S. citizenship required? 3. Cell Phones Are contractor personnel allowed to use cell phones to send reports of broken windows, caulking issues, or other observed incidents during contract performance? 4. NAICS Code Please clarify why NAICS 561720 applies rather than NAICS 561210. 5. Contract Scope Please confirm whether the Base Year requires exterior window cleaning only and identify which Option Years require interior and exterior cleaning. 6. Square Footage Please provide the exact cleanable glass square footage for each building. 7. Building Access What roof access, anchorage systems, and equipment are available for window cleaning? 8. Interior Glass Please clarify the cleaning requirements for the BTC curtain-wall interior cores. 9. Additional Services Are high dusting, cleaning of hanging light fixtures, and annual inspections included in the contract scope? 10. Emergency Services How will emergency cleaning requests and the 24-hour response requirement be authorized and compensated? 11. Security What background checks, escorts, or security clearances are required for contractor personnel?Please see the SOW and other solicitation douments. Please refer to the SOW, RFQ, applicable solicitation attachments, and previously issued Government responses for information regarding working hours, contract scope, cleaning requirements, square footage, building access, additional services, emergency services, and security requirements. All contractor personnel must comply with applicable FBI facility access and security procedures. Any matters concerning employee eligibility or the use of electronic devices within FBI facilities are subject to review and approval by FBI Security.x
125Amdendment to #53 - ExperienceRevision to Question #53The Government has revised Sections 5.C and 6 of the RFQ to clarify the relevant experience requirements.

The revised requirements are incorporated into the RFQ through this amendment. x

Sheet2

Cost AreaApprox. Total square feet per cost itemBase year square feet cleanedOut Year 1 square feet cleanedOut Year 2 square feet cleanedOut Year 3 square feet cleanedOut Year 4 square feet cleaned
CJIS Main inside cleaning41,67941,67941,67941,67941,67941,679
CJIS Main outside cleaning79,77679,77679,77679,77679,77679,776
CJIS Main 2nd outside cleaning79,77679,77679,77679,77679,77679,776
BTC Inside cleaning10,66510,66510,66510,66510,66510,665
BTC Outside Cleaning106,109106,109106,109106,109106,109106,109
BTC Interior Core Cleaning Adds146,648146,648
Stair #6 Cleaning Adds4,2504,250
Visitors Center2,1382,1382,1382,1382,1382,138
Daycare outside cleaning1,3701,3701,3701,3701,3701,370
Service Center outside cleaning224224224224224224
Automotive676767676767
Parking Garage Outside Cleaning8,3458,345
Parking Garage Inside Cleaning8,3458,345
RA Building Outside Cleaning105810581058
RA Building Inside Cleaning105810581058
Police building outside cleaning245245245245245245
Total Square Feet Cleaned by Year322,049328,415468,697340,855322,049