1501000 F Facility Management_V2.docx

DOCX document 25 KB Posted

Attached to
AMENDMENT 0003 - Facility Management (Annex 1501) & Facility Investment (Annex 1502) Services for MCBCB, GUAM
Solicitation number
N4019224R6000
Issued by

About this file

This document outlines deliverables and reporting requirements for facility management services at Marine Corps Base Camp Blaz in Guam. The contractor must provide electronic copies of various deliverables on a regular basis, including a system access personnel listing within 30 days of award, a new facility sustainability strategy with monthly updates, a monthly report for facilities in caretaker status, a weekly MAXIMO work order report, a planned maintenance program plan with annual updates, a MAXIMO asset changes report monthly, an annual facility energy and water evaluation report, building energy manager training materials and attendance sheets, overrides and alarm reports from building automation systems within one hour of incidents, engineering document packages within 30 days as required, a standard operating procedure for dig permits with annual updates, copies of dig permits and requests, and munitions and explosives of concern work plans as needed. The solicitation seeks proposals for facility management and investment services at Camp Blaz and other Department of Navy and Department of Defense facilities in Guam, under solicitation number N4019224R6000 issued by the Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
Future Bldg Enrollment.pdf PDF
N4019224R6000_0003.pdf PDF
PWS Note - Next Gen Intent.docx DOCX document
CBA Wages.xlsx XLSX spreadsheet
1501000 C Facility Management_V7 rev1.docx DOCX document
N4019224R6000_0002.pdf PDF
0200000 J Management and Administration.docx DOCX document
PIEE_Registration.pdf PDF
B40011 weld rm exhaust PPI 35.pdf PDF
Posting_Offer_PIEE-Training.pdf PDF
B40000 Hangar door motor PPI 30.pdf PDF
B40000 Mech Rm PPI 32.pdf PDF
CBA-2019-12614 Rev 5.pdf PDF
N4019224R6000_0001.pdf PDF
B40011 Mech rooms PPI 33.pdf PDF
J-0200000-07 - Asset Information.xlsx XLSX spreadsheet
J-1501000-12.D (PMG Appendix D) Asset Names_Abbrv.xlsx XLSX spreadsheet
J-1501000-12 Planned Maintenance Guide.docx DOCX document
J-1501000-08 MCBCB Work Classification Playbook_V2.xlsx XLSX spreadsheet
1501000 J Facility Management_V4.docx DOCX document
Attachment J-0200000-02-SCA WD_2015-5693 Rev20.pdf PDF
N4019224R6000_JM1_CorporateExperience.docx DOCX document
N4019224R6000_JL3_Site_Visit_Itinerary.docx DOCX document
J-1502000-07F Electrical Demarcation E6.pdf PDF
N4019224R6000.pdf PDF
Attachment J-0200000-05 Contractor Significant Incident Report.pdf PDF
J-1502000-07C Electrical Demarcation E3.pdf PDF
1502000 F MCCB R1.docx DOCX document
1501000 C Facility Management_V7.docx DOCX document
J-1502000-07G Electrical Demarcation E7.pdf PDF
J-1501000-17 Dynamic Assets Requiring Condition Assessment_V7.xlsx XLSX spreadsheet
J-1502000-07A Electrical Demarcation E1.pdf PDF
N4019224R6000_JL4_Directions.pdf PDF
J-1501000-23 Sample Energy and Water Evaluation Report.xlsx XLSX spreadsheet
J-0200000-09 - Characteristic Meter Reading Information.xlsx XLSX spreadsheet
J-1502000-07D Electrical Demarcation E4.pdf PDF
N4019224R6000_JL2_PPI.xls XLS spreadsheet
0200000 F Management and Administration.docx DOCX document
0100000 C General Information.docx DOCX document
N4019224R6000_JM2_PPQ.doc DOC document
N4019224R6000_JL1_Labor_Hours.xlsx XLSX spreadsheet
J-1502000-07J Electrical Demarcation E9.pdf PDF
J-1501000-21 Non-Dynamic Assets Requiring Condition Assessment_V7.xlsx XLSX spreadsheet
J-1502000-05 Planned Maintenance (PM) Program Services Matrix .xlsx XLSX spreadsheet
J-1502000-07L Gas Demarcation G2.pdf PDF
J-1502000-07B Electrical Demarcation E2.pdf PDF
J-1501000-13 (PMG Appendix E) Prescriptive UNIFORMAT List.xlsx XLSX spreadsheet
J-0200000-13 ELINs 6_01_2023_V9_ Auto (with Ext).xlsx XLSX spreadsheet
J-1502000-07H Electrical Demarcation E8.pdf PDF
1502000 C Facility Investment MCBCB.docx DOCX document
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

a 1501000 – Facility Management

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

The Contractor Shall Provide Electronic Copies of All Deliverables Listed in Section F

Annex/ Spec Item Form Attachment Number

Deliverable Title
Date (s) of Submission
Distribution
Frequency
1501000/ 2.3.1
N/A
System Access Personnel Listing
Within 30 calendar days after contract award
KO
Upon award and any change in personnel
1501000/ 2.3.3
N/A
New Facility Sustainability Strategy
Within 30 calendar days after contract award with monthly status updates
KO
Upon award and updated monthly

1501000/ 2.3.3

N/A
Monthly Report for Facilities in Caretaker status.
By the third workday of each month
KO
Monthly

1501000/ 3.1.3

N/A
Weekly MAXIMO Work Order Report
By 0900 the first workday of each week
KO
Weekly

1501000/ 3.1.4

N/A
Planned Maintenance (PM) Program Plan
Initial Plan developed and entered into NAVFAC Maximo –

45 calendar days after contract award; Annual update – 1 October each year

KO
Upon award and updated annually

1501000/ 3.2.1

N/A
MAXIMO Asset Changes Report
By COB the third workday of each month
KO
Monthly

1501000/ 3.3.1

N/A
Facility Energy and Water Evaluation Report
1 October each year
KO
Annually

1501000/ 3.3.2

N/A
BEM Training Presentation
Initial – 30 working days prior to the first training session; Annual update – 15 October each year
KO
Annually

1501000 – Facility Management

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

The Contractor Shall Provide Electronic Copies of All Deliverables Listed in Section F

1501000/ 3.3.2

N/A
BEM Training

Attendance Sheet Two working days after completion of Training Session

KO
Quarterly

1501000/ 3.4

N/A
FRCS System Override Report
Within one hour of discovery
KO
Per incidence

1501000/ 3.4

N/A
FRCS System Alarm Report
Within one hour of discovery
KO
Per incidence

1501000/ 3.5.1

N/A
Engineering Document Packages
Within 30 working days or as directed by the KO
KO
As required

1501000/ 3.5.3

N/A
Dig Permit Standard

Operating Procedure (SOP)

Within 30 calendar days after contract award
KO
Annually

1501000/ 3.5.3

N/A
Copy of dig permits that identify ESS
Upon issuance of dig permit
KO
As required

1501000/ 3.5.3

N/A
Copy of dig requests
Upon receipt of request for dig permit
KO
As required
1501000/ 3.5.3
N/A
Copy of dig permits
Upon issuance of dig permit
KO
As required
1501000/ 3.5.3
N/A
Dig Permit

Monthly Summary

Fifth working day of each month
KO
Monthly
1501000/ 3.5.4
N/A
Munitions and Explosives of Concern (MEC) Work Plan and Site-

Specific Work Plans

Within 30 calendar days after contract award and as required
KO
Once for initial submittal, then as required