Sol_140R4024R0026_Amd_0003.pdf

PDF 183 KB Posted

Attached to
SJC AZOTEA PORTAL AND DROP STRUCTURES Federal contract opportunity
Solicitation number
140R4024R0026
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document is an Amendment (Amendment 3) to Solicitation No. 140R4024R0026 for the SJC Azotea Portal and Drop Structures project issued by the Bureau of Reclamation's Upper Colorado Region. The amendment incorporates revised specifications and drawings, including Att2_SJC_Azotea_Portal_Drop_Structures_Specs3.dox, Att3_Azotea_Existing_Drawings_Revised.pdf, and Azotea Drawing Set – B&W.pdf. It also includes two key clarifications from a Q&A session: first, a detailed explanation of "Backfill, Compacted" and "Backfill, Structural" line items (with reference to an attached document for specifics), and second, confirmation that there is no Maximum Allowable Construction Cost (MACC) for the project. Bidders are instructed to prepare proposals based on their best offer using pricing schedules from Amendment 2, with a specified period of performance from 09/19/2025 to 03/15/2027.

View the file

Other files for this federal contract opportunity

Other files attached to SJC AZOTEA PORTAL AND DROP STRUCTURES, newest first.
File Type Posted
Sol_140R4024R0026_Amd_0005.pdf PDF
Sol_140R4024R0026_Amd_0004.pdf PDF
Azotea_Drawing_Set_-_B_W_0003.pdf PDF
Att_3_Azotea_Existing_Drawings_Revised_0003.pdf PDF
SJC_Azotea_Portal__Drop_Structures_Backfill_0003.pdf PDF
Att2_SJC_Azotea_Portal_Drop_Structures_Specs3_0003.docx DOCX document
Sol_140R4024R0026_updated_price_schedule_Amd_2_0002.docx DOCX document
Sol_140R4024R0026_Amd_0002.pdf PDF
Azotea_Standard_Drawings_0002.pdf PDF
Att_5_Pricing_Schedule_rev1_Amd_2_0002.xlsx XLSX spreadsheet
Blico_Floor_Door_Size_Chart-1_0001.pdf PDF
Att2_SJC_Azotea_Portal_Drop_Structures_Specs2_0001.pdf PDF
Sol_140R4024R0026_Amd_0001.pdf PDF
Sol_140R4024R0026.pdf PDF
Att_5_Pricing_Schedule.xlsx XLSX spreadsheet
Att_3_Azotea_Existing_Drawings.pdf PDF
Att6-Notice_to_Contractors-CPARS_(December_2015).docx DOCX document
Att7-SF25-16e_Performance_Bond_Form.pdf PDF
Att_4_Wage_Determination_NM20250026_4-18-25.pdf PDF
Att1-Construction_Contract_Administration_Information.pdf PDF
Att_3_Azotea_Final_Drawings_All_B_W.pdf PDF
Att7-SF25A-16e_Payment_Bond_Form.pdf PDF
Att8-DI-137_Release_of_Claims.pdf PDF
Att2_SJC_Azotea_Portal___Drop_Structures_Specs.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140R4024R0026 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Albuquerque NM 87102

R4Q

555 Broadway Blvd NE, Suite 100 Albuquerque Area Office Upper Colorado Region Bureau of Reclamation

Salt Lake City UT 84138

R40

125 South State Street, Room 8100 Regional Office Upper Colorado Region Bureau of Reclamation

06/18/20250003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/18/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SJC Azotea Portal and Drop Structures Amendment 3:

* Includes Questions and Answers

* Incorporates updated Specification and Drawings

Period of Performance: 09/19/2025 to 03/15/2027

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Mary B. Maestas

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

United States Department of the Interior

BUREAU OF RECLAMATION

140R4024R0026 SJC Azotea Portal and Drop Structures Amendment 3

Amendment 3 Incorporates the following revised specifications and drawings:

- Att2_SJC_Azotea_Portal_Drop_Structures_Specs3.dox

- Att3_ Azotea_Existing_Drawings_Revised.pdf

- Azotea Drawing Set – B&W.pdf

Question 1: There are 2 details on sheet 60114. Compacted backfill is showing around the structure which I am assuming is defining the "Backfill, Compacted" line item, and the other is just labeled "Backfill" which I assumed is for the "Backfill, Structural. What is included with the Backfill, Structural line item and what is included in the Backfill, Compacted line item?

Answer 1: See attachment “SJC Azotea Portal Drop Structures_Backfill”

Question 2: Is there a MACC – the Maximum Allowable Construction cost for this project?

Answer 2: There is no MACC, there is an estimated magnitude of construction range listed in the solicitation. Please prepare proposal based on your company’s best offer using pricing schedules included in Amendment 2.

File details come from the government source that posted it. Updated .