The document contains a terrazzo floor detail drawing and color legend for the Hoover Dam Visitor Center exhibit level and renovation project. The drawing depicts the proposed terrazzo floor design including metal inlay dividers, arrows, lettering, and color breaks. The related federal contract opportunity is solicitation number 140R3023R0003 from the Department of the Interior Bureau of Reclamation to renovate the office space and exhibit level at the Hoover Dam Visitor Center. The solicitation seeks contractors to design and install the terrazzo floor as depicted in the drawing along with completing the overall renovation project.

View the file

Other files

File Type Posted
E6_02_ELECTRICAL_SCHEDULES_122022_0004.pdf PDF
140R3023R0003_-_Questions_and_Responses_-Amd_No__0004_0004.pdf PDF
A2_41_EXHIBIT_LEVEL_-_FINISH_FLOOR_PLAN_-_122022_0004.pdf PDF
A7_03_WALL_SECTIONS_-_122022_0004.pdf PDF
E0_01_ELECTRICAL_LEGEND__ABBREVIATIONS____SHEET_INDEX_-_122022_0004.pdf PDF
Sol_140R3023R0003_Amd_0004.pdf PDF
E3_02_ELECTRICAL_CEILING_DEVICE_POWER_PLAN_-_122022_0004.pdf PDF
X0_300_-_WALL_FINISHES_AND_PAINT_PLAN_0003.pdf PDF
A2_41_EXHIBIT_LEVEL_-_FINISH_FLOOR_PLAN_0003.pdf PDF
E6_02_ELECTRICAL_SCHEDULES_0003.pdf PDF
E3_02_ELECTRICAL_CEILING_DEVICE_POWER_PLAN_0003.pdf PDF
A2_45_EXHIBIT_LEVEL_-_WALL_FINISH_PLAN_0003.pdf PDF
A2_46_OFFICE_LEVEL_-_WALL_FINISH_PLAN_0003.pdf PDF
Sol_140R3023R0003_Amd_0003.pdf PDF
140R3023R0003_-_Questions_and_Responses_-Amd_No__0003_0003.pdf PDF
E0_01_ELECTRICAL_LEGEND__ABBREVIATIONS____SHEET_INDEX_0003.pdf PDF
140R3023R0003_-_Questions_and_Responses_-Amd_No__0002_0002.pdf PDF
Sol_140R3023R0003_Amd_0002.pdf PDF
140R3023R0003_-_Amendment_No__0001_-_Revised_Sections_L___M_0001.pdf PDF
140R3023R0003_-_Questions_and_Responses_-Amd_No_0001_0001.pdf PDF
Attachment_9_-_Design_Drawings_0001.pdf PDF
Site_Visit_PowerPoint_Presentation_-_140R3023R0003_0001.pdf PDF
Sol_140R3023R0003_Amd_0001.pdf PDF
Final_Attendee_List_140R3023R0003_0001.pdf PDF
Attachment_3_-_Wage_Decision_No__NV20220038_-_10-21-2022.pdf PDF
Attachment_6_-_Waste_Diversion_FORM_E.pdf PDF
Attachment_5_-_Construction_Payment_Requirements.pdf PDF
Attachment_8_-_Past_Performance_Questionnaire.pdf PDF
Attachment_7_-_DI-137_Release_of_Claims.pdf PDF
_Solicitation_No__140R3023R0003_-_HD_VC_Exhibit_Level_-_Renovated_Office_Space.pdf PDF
Attachment_1_-_Specifications_-_Final_3-2022.pdf PDF
Sol_140R3023R0003.pdf PDF
Attachment_2__-_Drawings.pdf PDF
Attachment_4_-_Bond_Forms.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hoover Dam Visitor Center July 21, 2022Turbine Terrazzo Floor Detail SK_02 00

REV

TERRAZZO DETAIL

Scale: 1/2" = 1'-0"1

METAL INLAY

DIVIDERS

METAL INLAY

ARROWS

METAL INLAY

LETTERING

TERRAZZO COLOR KEY

Scale: 1/4" = 1'-0"2

EXPOSED

CONCRETE

FLOOR

NOTE: Colors shown to indicate proposed color breaks.

final color selection TBD.

METAL INLAY

EDGE

T-1

T-2

T-3

T-4

T-5

T-6

T-7

T-8

T-9

COLOR LEGEND

File details come from the government source that posted it. Updated .