This Statement of Work (SOW) details fire protection systems inspection and testing services for 12 national parks in the Alaska Region. The contract requires a qualified contractor to perform annual inspections and tests of fire alarms, sprinkler systems, clean agent systems, pumps, and backflow preventers across approximately 172 facilities with around 390 individual inspection reports. The scope covers parks including Denali, Glacier Bay, Katmai, Kenai Fjords, and others, with inspections primarily conducted between March and May.

The contract is structured with a base year (2025) and four option years (2026-2029), with Task 2.5 involving Denali's west side facilities optional in years 3-4. Technicians must hold NICET Level II certification and have at least three years of fire system inspection experience. Inspection requirements include detailed reporting, deficiency logging, and immediate reporting of life safety concerns. Payment will be made in three installments: 50% for field work, 25% for draft inspection reports, and 25% for final approved reports with cost estimates. The total contract covers inspection and testing of fire protection systems across multiple National Park Service facilities in Alaska.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF SERVICES

Contract No. TBD, Task Order No. TBD

INSPECTION, AND TESTING of the NATIONAL PARK SERVICE

ALASKA REGION STRUCTURAL FIRE SYSTEMS

November 21, 2024

I. BACKGROUND

The purpose of this contract is to maintain fire protection systems and related components in facilities located throughout the Alaska Region of the National Park Service in a state of readiness such that if called on in the event of an emergency, there is a high level of confidence that these systems will perform their intended function. Fire Protection Systems, as used throughout this document, refers to either mechanical or electrical systems utilized for the suppression of structural fires and the notification of fires and emergencies to building occupants and firefighting personnel.

The basis of all work defined herein is taken from the most current versions of the National Fire

Protection Association (NFPA) 25, entitled Inspection, Testing, and Maintenance of Water Based

Fire Protection Systems; NFPA 72, entitled National Fire Alarm and Signal Code; UFC-3-601-02, entitled Operation and Maintenance: Inspection, Testing, and Maintenance of Fire Protection

Systems; UFC-4-021-01, entitled Design and O&M: Mass Notification Systems; and NPS RM-58.

If there is any deviation between these specifications and the current version of the International

Fire Code, the more stringent shall govern.

II. DESCRIPTION OF WORK

The Contractor shall furnish all labor, supervision, tools, materials, equipment, transportation, lodging and management necessary to provide inspection, testing, and documentation of fire suppression, fire alarm systems and all their components at 12 national parks across the Alaska

Region.

Fire suppression systems and fire alarm and notification systems vary in type and size depending on the intended service and the location of the system. There are typically multiple systems located within a single building. This contract will service fire systems at multiple facilities as per Table 1 below and Attachment 1 NPS AKR Structural Fire Asset Details.

Table 1:

Task Park Alpha

Code Towns / Areas

Approximate

Number of

Facilities**

1 Bering Land Bridge National

Preserve BELA Nome, Alaska 4

2.0 Denali National Park & Preserve -

East

DENA

Denali Front Country, C Camp, Headquarters and

Talkeetna, Alaska

2.5 Denali National Park & Preserve –

West

(Option years 3-4, 2027-2029)

DENA

Toklat and Eielson Visitor

Center Denali, Alaska

3 Gates of the Arctic National Park

& Preserve

GAAR

Marion Creek and Bettles, Alaska

4 Glacier Bay National Park &

Preserve

GLBA

Gustavus and Bartlett

Cove, Alaska

Katmai National Park & Preserve KATM

King Salmon and Brooks

Camp, Alaska

6 Kenai Fjords National Park KEFJ Seward, Alaska 2

7 Klondike Gold Rush National

Historic Park, Alaska KLGO Skagway, Alaska 29

8 Lake Clark National Park &

Preserve LACL Port Alsworth, Alaska 3

9 Sitka National Historic Park SITK Sitka, Alaska 4

10 Western Arctic National Parklands WEAR Kotzebue, Alaska 6

11 Wrangell-St. Elias National Park

& Preserve

WRST

Copper Center, Glennallen, and Kennecott, Alaska

12 Yukon-Charley Rivers National

Preserve YUCH Eagle, Alaska 1

**Note: There are approximately 172 facilities with many having multiple systems per building to be inspected. Systems include but are not limited to fire alarms, wet and dry fire suppression, pumps, clean agent systems, and backflow preventors with approximately 390 individual inspection reports.

The Scope of this contract shall include testing and inspection services as follows:

A. INSPECTIOND AND TESTING SERVICE REQUIRED:

1. Perform annual inspections/tests of fire alarms, sprinkler and clean agent systems, pumps, and backflow preventers. Each individual alarm, fire suppression, pump, clean agent, and backflow preventor shall have its own form with the FMSS Location number and building description written clearly in the title block. The following forms and reference documents are provided:

Attachment 1: 2025 NPS AKR Structural Fire Asset Details

Attachment 2: Example NPS Structural Fire Deficiency Log

Attachment 3: DENA Coordination Requirements1-23-20

Attachment 4: BP - Back Flow Prevention Device

Attachment 5: CA - Clean Agent and CO2 Test Form

Attachment 6: DC - Dry Chemical Test Form

Attachment 7: FA - Fire Alarm Test Form

Attachment 8: FP - Fire Pump Test Form

Attachment 9: SP - Fire Sprinkler Test Form

Attachment 10: NPS FILLABLE INVENTORY FORM

2. On occasion, the deficiency is only a very minor repair or adjustment. After notifying the Contracting Officer in advance for authorization of the work, and receiving approval, the Contractor shall be prepared to make the repair or adjustment during that year’s inspection provided the necessary parts are available. Examples might include but are not limited to adjusting the orientation of a sprinkler head sidewall, “snugging up” a sprinkler head or gage with a very slow leak, resecuring a loose wire, etc. It is anticipated that this will not be a common occurrence and will be at no additional cost to the government.

3. If a deficiency is identified that relates to imminent concern for life and safety, the deficiency shall be reported immediately to the Contracting Officer, Lead Government

Representative (LGR) and Park Facility Manger or their representative. Depending on the deficiency the Contracting Officer or their representative will provide further guidance.

4. If the deficiency was not corrected while on site, provide a detailed description of the work necessary to correct the deficiency on the inspection report and in the Structural

Fire Deficiency Log.

5. For sites that report to an alarm monitoring service, the contractor is responsible for notifying the monitoring agency and restoring the system to normal status. Test devices to ensure that they are reporting alarms, supervisory signals, and trouble signals (where applicable) properly to the alarm monitoring service. For a list of fire alarm locations in this contract see Attachment 1: 2025 NPS AKR Structural Fire Asset Details.

6. Glycol filled fire suppression systems must be tested annually to confirm the system meets current NFPA requirements and findings reported to include type of test performed and high and low sample values.

7. Where glycol freeze protection is determined to be above -20 deg F, the contractor must contact the LGR immediately following the site visit to determine whether a contract modification is required to refill the systems with an approved -25 deg F (or lower)

NFPA product. The contractor will legally dispose of any drained freeze protection mixture.

8. When a system is due or past due the periodic (5-year and 10-year) Obstruction

Inspection or internal inspection of piping, it shall be documented on the inspection form as a deficiency and a cost estimate will be provided to conduct this inspection and return the sprinkler system to fully operational and ensure no leaks are present.

9. When non-functional systems are encountered, investigate and provide a report of repairs or improvements that are likely needed in order to make the system operational.

Report shall include a detailed description of the work that is necessary to repair the system and a cost estimate for the work.

10. Any discrepancy between NPS data provided and conditions found in the field shall be documented with the attachment FILLABLE INVENTORY FORM - Structural Fire

Classifications to document new systems.

11. Utilities: Anytime any utilities (water, heat, AC, gas etc.) will need to be shut down for any period during the life of the contract, the contractor shall provide 48 hours advance notice to the LGR/PM. No system will be left out of service at the end of a workday or over a weekend without written permission from the LGR.

12. Any damages to Park property resulting from the Contractor’s performance of the contract shall be repaired to the Park’s satisfaction at the Contractor’s expense. All repairs must be approved by the LGR prior to being initiated.

13. Government Transportation: The Government will provide the following transportation:

DENA – Option years 1-3: Ground transportation at Denali for access to “west district” is restricted. Contractor shall be required to obtain a Denali Park Road permit for transportation from the park headquarters area to the “west district” facilities, see attached “DENA Coordination Requirements”.

KATM – Ground transportation at King Salmon and at Brooks Camp shall be provided by the government. Transportation from King Salmon to Brooks Camp and back to King Salmon shall be at the contractors expense and should be included in the bid.

WEAR – Ground transportation in Kotzebue shall be provided.

YUCH – Ground transportation in Eagle shall be provided.

WRST – Kennecott – Ground transportation to Kennecott is restricted. Contractor may be provided Government transportation from the bridge in McCarthy to the

Kennecott Mill site or by local concessionaires.

14. Government Lodging: The Contractor and their subcontractors are responsible for their own lodging. In extremely rare circumstances, the Contractor may make a request to the Contracting Officer or their representative consideration for Government Lodging.

If granted the contractor shall pay the Government nightly rate.

15. New Systems: It is likely that the NPS will add alarm and fire suppression systems during the period of this contract. An adjustment in the contract cost for Inspection and

Testing of the added systems will be made for the contract year the systems are first inspected and any contract out years.

16. Inspection Schedule:

a. After contract award, the Contractor shall coordinate a fire protection system inspection and testing schedule with the Lead Government Representative (LGR) and park representatives as designated by the LGR.

b. The LGR may or may not choose to set up a brief virtual meeting with the

Contractor and park staff approximately one week prior to the Contractor’s inspection visit at each park.

c. The Contractor should plan to work within each park’s work hours, typically 7:00 am to 5:30 pm, Monday through Thursday. Requests to work outside these hours may be grated on a rare case by case basis with prior approval from the park at least one week in advance. Work on Federal Holidays is not allowed.

d. The field inspection and testing work of this contract is expected to occur for all parks in the spring during March through May except for WRST which may be delayed until early June. This is to ensure summer staff housing has been inspected prior to staff arrival. Most park fire suppression systems are charged year-round except for GAAR, KATM, SITK, and WRST as per below:

PARK System Operations

GAAR Systems are back online mid-May?

GLBA

Systems charged year-round but ideally ITM's are done before they are occupied in April.

KATM

King Salmon systems are year-round; the water is on at Brooks typically by the middle of May

SITK

Systems are charged year-round. Ideally inspection dates would be mid-March to mid-April before the first cruise ship on April 25th.

WRST

Typically, all systems are up and running by the first week of June; Kennecott is the last one up.

17. Delays in Travel: The contractor shall always keep weather conditions in mind when making travel plans throughout the life of this contract. Travel delays in March through

May due to weather should not be included in the contract Proposal. Rather, up to two

“instances” of travel delays per park can be billed to the Government with proper documentation at a rate of 8 work hours per day, per employee, the standard government per diem rate, and travel expenses incurred. If a group of employees traveling together to a park are all delayed, it will be considered one “instance”. Travel delays that occur outside of the expected spring work period is the responsibility of the contractor.

18. Coordination of Inspection Work: Work in general and where multiple subcontractors will be performing inspections at a single park, the Contractor will make every effort possible to schedule their visits to coincide to limit the impact to park resources, and disruption to park operations.

19. Inspection Reports:

a. Each system/component identified on Attachment 1: 2025 NPS AKR Structural Fire

Asset Details shall have its own report.

b. Draft inspection reports shall be submitted for review and comment within 21 days of the completion of inspection at each specific site. Final inspection reports shall be submitted within 30 days of receipt of comments from NPS.

c. All final inspection reports shall be submitted electronically in Adobe.pdf format no later than September 30th of each year.

d. All professional and technical information developed under this contract, and all work sheets, reports, and related data shall become the property of the National Park

Service.

20. Consolidated NPS Structural Fire Deficiency Log:

a. Deficiencies identified on inspection reports shall be consolidated into a single Excel workbook with one sheet for each park. Attachment 11: Example NPS Structural

Fire Deficiency Log is largely fictitious but is provided for the contractor to see the format and level of document required for this contract.

b. Once the contract has been awarded, the Contractor shall request from the LGR a copy of the most recent NPS Structural Fire Deficiency Log so the Contractor can update with each year’s inspection deficiencies. Each deficiency shall be individually documented in the spreadsheet and shall include an estimated cost for the repair.

c. The updated NPS Structural Fire Deficiency Log shall be returned to the LGR no later than October 30th of each year.

21. Correspondence:

a. Correspondence including technical issues (where technical issues relate to compliance with the requirements herein), invoices, (that which proposes or otherwise involves waivers, deviations or modifications to the requirements, terms, or conditions of this SOW) will be addressed to both the Contracting Officer and the LGR.

b. Deliverables including fire system inspection reports, yearly list of consolidated fire system deficiencies, and inventory sheets will be addressed to the LGR.

III. PERSONNEL REQUIREMENTS

All workmanship shall meet the standards specified herein and shall be accomplished in conformance with approved and accepted standards of the industry; equipment manufacturers; all applicable Federal, State, and Local standards; and all applicable building and safety codes, including the National Fire Protection Association, National Electrical Code, International

Plumbing Code, International Building Code, etc.

A. Qualifications: Fire Suppression and Alarm System technicians/inspectors performing work under this contract must hold a current Institute for Certification in Engineering

Technologies (NICET) Level II certification. Additionally, the craftsman must have at least three years of experience in fire system inspection and testing in buildings and equipment comparable to the buildings and equipment covered by this contract. All tasks requiring work within a fire alarm panel program shall be performed by a technician certified by the manufacturer of the corresponding panel.

B. At the start of the Contract Base year and each Option year submit qualifications for approval. Provide a list of the parks at which each personnel will be performing tests.

C. Experience: Contractor shall have continuously performed inspection and testing of fire alarm systems, their components and appurtenances for the past five years.

D. Alarm Systems at DENA and GLBA: Inspections and testing of the alarm systems at

DENA and GLBA must be performed by a factory trained technician with the ability to reprogram Edwards System Technology (EST) alarm systems.

E. QA/QC: All inspection reports shall be reviewed for correctness and to provide references to NFPA codes by an independent Fire Protection Engineer.

IV. PERIOD OF PERFORMANCE: The work of this task order shall be provided from approximately date of execution of task order through October 30th of each contract period.

V. DEFINITION OF BID ITEMS

A. BASE BID ITEM 1: 2025 Inspection and Testing Services of all systems as identified in

Attachment 1: NPS AKR Structural Fire Asset Details - Lump Sum Price separated out by

Task number as per Table 1.

B. OPTION 1: 2026 Inspection and Testing Services of all systems as identified in Attachment

1: NPS AKR Structural Fire Asset Details - Lump Sum Price separated out by Task number as per Table 1.

C. OPTION 2: 2027 Inspection and Testing Services of all systems as identified in Attachment

1 and to include Task 2.5 of Table 1 for 7 facilities on Denali’s west side: NPS AKR

Structural Fire Asset Details - Lump Sum Price separated out by Task number on Table 1.

D. OPTION 3: 2028 Inspection and Testing Services of all systems as identified in Attachment

E. OPTION 4: 2029 Inspection and Testing Services of all systems as identified in Attachment

VI. FEE AND PAYMENT

A. Request for progress payment shall be made on monthly-itemized invoices submitted for completed work. Invoices shall include a description of the work, the cost for the billing cycle, and the cost to date for each item of service performed correlated to Task number on Table 1.

B. Services for Inspection and Testing Services of Task 1 through Task 12 shall be made at the

Fixed Price/Lump Sum with progress payments as follows:

i. Field work - 50%

ii. Submittal of draft inspection reports – 25%

iii. Approval of final inspection reports with cost estimates – 25%

END SECTION