This document is a price schedule attachment for a Request for Quote (RFQ) for the Hercules Tugboat Drydock Availability project at the San Francisco Maritime National Historical Site. The RFQ solicitation number is 140P8624Q0041.
The price schedule includes base items such as cradling and temporary services, underwater hull system maintenance, structural repairs and installation, and non-structural repairs, weldments and coatings. It also includes option items for transporting, hauling out, and additional temporary services, valve replacement, and further non-structural and structural repairs and coatings. Unit prices and total prices are provided for each line item. The total proposed price for the base items plus all options is $0. The federal agency involved is the National Park Service under the Department of the Interior.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Contract Price Schedule |
| REQUEST FOR QUOTE: 140P8624Q0041 |
| PARK - PMIS: SAFR - 255399, 341297, 317929, 215090, 215091 |
| DEVELOPED AREAS: NHL Tugboat Hercules located at Hyde Street Pier in San Francisco |
| PROJECT TITLE: Hercules Drydock Availability - 2022 - 2024 |
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE | |
| BASE ITEMS | ||||||
| 1.0 | Cradling and Temporary Services | |||||
| 1.01 | Cradling and Blocking | LS | $0 | $ - 0 | ||
| 1.02 | Temporary Services | LS | $0 | $ - 0 | ||
| 2.0 | Underwater Hull Systems Maintenance | |||||
| 2.01 | RUDDER, TAILSHAFT, STERNTUBE, AND PROPELLER REPAIRS, COATING, AND REINSTALLATION | $ - 0 | ||||
| A | Rudder Repairs | LS | $0 | |||
| B | Tailshaft Coatings | LS | $0 | |||
| C | Depth Sounder | LS | $0 | |||
| NEW | D | Scupper | LS | $0 | ||
| NEW | E | Additional Propellor Repairs | LS | $0 | ||
| 3.0 | Structural Repairs and Installation | |||||
| 3.01 | Shell Plate Insert Repair | $ - 0 | ||||
| A | Insert P-A-5 | LS | $0 | |||
| B | Insert P-B-6 | LS | $0 | |||
| CHANGE | C | Insert DOUBLER P-F-11/12 | LS | $0 | ||
| D | Insert S-A-5 | LS | $0 | |||
| E | Insert S-B-5 | LS | $0 | |||
| F | Keel Shoe | LS | $0 | |||
| 3.02 | Frame and Floor Repairs | $ - 0 | ||||
| A-U | Flatbar to Angle (FR 09-30) | LS | $0 | |||
| F | Additional Forecastle Frame Repair (FR 14) | LS | $0 | |||
| I | Additional Forecastle Frame Repairs (FR 17) | LS | $0 | |||
| K | Additional Forecastle Frame Repairs (FR 19) | LS | $0 | |||
| M | Additional Forecastle Frame Repairs (FR 21) | LS | $0 | |||
| N | Additional Forecastle Frame Repairs (FR 22) | LS | $0 | |||
| O | Additional Boiler Room Frame Repairs (FR 24) | LS | $0 | |||
| P | Deep Frame 25 | NEW | LS | $0 | ||
| Q | Additional Boiler Room Frame Repairs (FR 26) | LS | $0 | |||
| R | Additional Boiler Room Frame Repairs (FR27) | LS | $0 | |||
| S | Additional Boiler Room Frame Repairs (FR 28) | LS | $0 | |||
| T | Additional Boiler Room Frame Repairs (FR 29) | LS | $0 | |||
| U | Deep Frame 30 | NEW | LS | $0 | ||
| V | New Boiler Room Frame Repairs (FR 31) | LS | $0 | |||
| W | New Boiler Room Frame Repairs (FR 32) | LS | $0 | |||
| X | New Boiler Room Frame Repairs (FR 33) | LS | $0 | |||
| 3.03 | Additional Bilge Stringer Renewal | LS | $0 | $ - 0 | ||
| 3.04 | Bulkhead Repairs (FR 23) | NEW | LS | $0 | $ - 0 | |
| 4.0 | Non-Structural Repairs, Weldments and Coatings | |||||
| 4.01 | Prep & Paint Main/Boat Deck, Pilothouse, and Stack, Appurtenances and Fill Main Deck Voids | LS | $0 | $ - 0 | ||
| 4.02 | Topside Repairs (Includes 6.03 Credit) | LS | $0 | $ - 0 | ||
| TOTAL BASE PRICE -------------------------------------------------------------------------------------------------------------------------------------- | $0 | |||||
| OPTION ITEMS | ||||||
| 5.0 | Transporting, Haul Out and Temporary Services | |||||
| 5.01 | A | Transportation and Delivery (To MINSY vs HSP) | LS | $0 | $ - 0 | |
| B | Steaming Escort to MINSY | LS | $0 | $ - 0 | ||
| 5.02 | A | Haul Out and Blocking (Additional Lay days) | 1 | Day | $0 | $ - 0 |
| B | Wet Berthing (Lay days) | 1 | Day | $0 | $ - 0 | |
| 5.03 | Additional Temporary Services | 1 | Day | $0 | $ - 0 | |
| 6.0 | Valve Replacement | |||||
| 6.01 | 1 1/2" valve | 1 | EA | $0 | $ - 0 | |
| 6.02 | 2" valve | 1 | EA | $0 | $ - 0 | |
| 6.03 | 2 1/2" valve | 1 | EA | $0 | $ - 0 | |
| 6.04 | 3" valve | 1 | EA | $0 | $ - 0 | |
| 6.05 | 6" valve | 1 | EA | $0 | $ - 0 | |
| 6.06 | 8" valve | 1 | EA | $0 | $ - 0 | |
| 6.07 | Main Sea Suction Spool Pipe | 1 | EA | $0 | $ - 0 | |
| 7.0 | Non-Structural Repairs, Weldments and Coatings | |||||
| 7.01 | HFO Tank Coatings | LS | $0 | $ - 0 | ||
| CHANGE | 7.02 | Guard Rail - Oak Angle Iron | LS | $0 | $ - 0 | |
| 7.03 | Prep and Paint Anchor Windlass | LS | $0 | $ - 0 | ||
| 7.04 | R/R Boiler Lagging | LS | $0 | $ - 0 | ||
| 7.05 | Epoxy Void Filling | 1 | SqFt | $0 | $ - 0 | |
| 8.0 | Structural Shell Plate Renewal | |||||
| 8.01 | Renew Plate P-K-3 | LS | $0 | $ - 0 | ||
| 8.02 | Renew Plate P-A-3 | LS | $0 | $ - 0 | ||
| 8.03 | Renew Plate P-A-4 | LS | $0 | $ - 0 | ||
| 8.04 | Renew Plate P-B-4 | LS | $0 | $ - 0 | ||
| 8.05 | Renew Plate P-B-5 | LS | $0 | $ - 0 | ||
| 8.06 | Renew Plate S-K-4 | LS | $0 | $ - 0 | ||
| 8.07 | Renew Plate S-A-2 | LS | $0 | $ - 0 | ||
| 8.08 | Renew Plate S-A-3 | LS | $0 | $ - 0 | ||
| 8.09 | Renew Plate S-A-4 | LS | $0 | $ - 0 | ||
| 8.10 | Renew Plate S-B-4 | LS | $0 | $ - 0 | ||
| 8.11 | Renew Plate S-C-4 | LS | $0 | $ - 0 | ||
| 9.0 | Structural Component Repairs and Installation | |||||
| 9.01 | A | 3" x 3" x 3/8" Angle Iron | 1 | Lbs. | $0 | $ - 0 |
| B | 5" x 3" x 3/8" Angle Iron | 1 | Lbs. | $0 | $ - 0 | |
| 9.02 | A | 3/8" Plate Steel - Doubler (Welded) | $ - 0 | |||
| 1 | S-A-2 | LS | $0 | |||
| 2 | S-A-2 | LS | $0 | |||
| 3 | S-A-2/S-K-3 | LS | $0 | |||
| 4 | S-A-3/S-K-3 | LS | $0 | |||
| 5 | S-K-4 | LS | $0 | |||
| 6 | S-A-4/S-K-4 | LS | $0 | |||
| 7 | S-K-5 | LS | $0 | |||
| 8 | S-K-6/7 | LS | $0 | |||
| 9 | S-C-6 | LS | $0 | |||
| 10 | S-C-8 | LS | $0 | |||
| 11 | P-K-3 | LS | $0 | |||
| 12 | P-B-4 | LS | $0 | |||
| 13 | P-C-5 | LS | $0 | |||
| 14 | P-B-7 | LS | $0 | |||
| 15 | P-C-8 | LS | $0 | |||
| 16 | P-B-9 | LS | $0 | |||
| 17 | P-B-8 | LS | $0 | |||
| B | 3/8" Plate Steel - Insert (Welded/Riveted) | 1 | Lbs. | $0 | $ - 0 | |
| C | 3/8" Plate Steel - Full Component Plate (Riveted) | 1 | Lbs. | $0 | $ - 0 | |
| D | 1/2" Plate Steel - Insert (Welded/Riveted) | 1 | Lbs. | $0 | $ - 0 | |
| E | 1/2" Plate Steel - Full Component Plate (Riveted) | 1 | Lbs. | $0 | $ - 0 | |
| 9.03 | A | MC 6X12 C-Channel | 1 | Lbs. | $0 | $ - 0 |
| B | C 5X9 C-Channel | 1 | Lbs. | $0 | $ - 0 | |
| 9.04 | CLAD Welding (25 pits per) | 25 | CLAD Weld | $0 | $ - 0 | |
| 9.05 | Additional Rivet Repairs | |||||
| 9.05.1 | Bobbing, Groups of 50 | 50 | EA | $0 | $0.00 | |
| 9.05.2 | Frenching, Groups of 25 | 25 | EA | $0 | $0.00 | |
| 9.05.3 | Ring Welding, Groups of 50 | 50 | EA | $0 | $0.00 | |
| 9.05.4 | Replacement, Groups of 25 | 25 | EA | $0 | $0.00 | |
| 10.0 | Tankage and New FO Piping | |||||
| 10.1 | Heavy Fuel Oil Tank Survey (Additional Diesel) | 1200 | Gallons | $ - 0 | ||
| 10.2 | New Diesel Fuel Oil Tanks and Piping Installation | LS | $ - 0 | |||
| TOTAL PRICE FOR ALL OPTIONS -------------------------------------------------------------------------------------------------------------------- | $0 | |||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS -------------------------------------------------------------------------------------------- | $0 |
File details come from the government source that posted it. Updated .