This is a Statement of Work for hazardous tree removal and trimming services at Boulder Beach within Lake Mead National Recreation Area. The project scope encompasses approximately 70 acres across five subareas (BB Picnic Area, BB Housing, VIP BB Campground, BB Campground, and Boulder Harbor) and requires removal of approximately 42 dead trees and trimming of approximately 278 living trees, including 88 palm trees. Work includes pruning, deadwood removal, canopy thinning, palm trimming, stump grinding, debris hauling, site protection, and restoration of disturbed areas. The contractor must provide all labor, supervision, equipment, rigging, aerial lifts, cranes, traffic control, and debris disposal necessary to complete the work.

Key requirements include engagement of an ISA Certified Arborist serving as site superintendent with minimum three years' experience in commercial tree maintenance and present on-site minimum eight hours daily during operations. All pruning must comply with ISA Tree Pruning Guidelines and ANSI A300 standards. Tree removal operations must comply with ANSI Z133, OSHA 29 CFR 1926, and NFPA 241. Large limbs and trunk sections over eight inches in diameter must be lowered using ropes, rigging devices, cranes, or aerial lifts; free-fall felling is prohibited in developed areas. Stumps must be ground to 12 inches below finished grade in turf areas and 6 inches in desert landscape areas. The contract is a firm fixed price lump sum award with 13 contract line items addressing removal and trimming by subarea, disposal, and mobilization/demobilization. Performance period is 120 days from award (approximately July 9 through November 6, 2026). Work must be conducted Monday through Friday, 7:00 a.m. to 5:00 p.m., excluding federal holidays, with the campground remaining open to public use during operations. The contractor must comply with park regulations, resource protection requirements, endangered species protocols (desert tortoise awareness training required), nesting bird monitoring during March 1 through August 31, archaeological resource protection, and invasive species prevention measures.

View the file

Other files

File Type Posted
Sol_140P8126Q0027_Amd_0004.pdf PDF
B09_Q_A__4_0004.docx DOCX document
B09_Q_A__3_0003.docx DOCX document
Sol_140P8126Q0027_Amd_0003.pdf PDF
B09_Q_A__2_0002.docx DOCX document
A04_SOW_349175_BB_Hazardous_Tree_Removal_(Revised_6_8_26)_0002.docx DOCX document
Sol_140P8126Q0027_Amd_0002.pdf PDF
B09_Revised_Price_Schedule_(6_8_26)_0002.docx DOCX document
B09_Q_A__1_0001.docx DOCX document
Sol_140P8126Q0027_Amd_0001.pdf PDF
Sol_140P8126Q0027.pdf PDF
A06_Appendix_Compressed.pdf PDF
B03_Wage_Determination_2015-5593_(Rev__31)_Clark_County__Nevada_(5_27_26).pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAKE MEAD NATIONAL RECREATION AREA

BOULDER CITY, NEVADA

PMIS No. 349175 safety

Remove Hazardous Trees at Boulder Beach

Statement of Work

NATIONAL PARK SERVICE

PACIFIC WEST REGION

May 26, 2026

Table of Contents PAGE NO.

01 11 00Summary of Work3
01 27 00Definition of Contract Price Items11
Appendix12

APPENDIX ATTACHMENT(S)

1. Map with Project Locations

2. Tree Example Photos

3. CM16 Submittal Form

SECTION 01 11 00

SUMMARY OF WORK

1.1 WORK COVERED BY CONTRACT DOCUMENTS

Project Location: This project is in the Boulder Beach area of Lake Mead National Recreation Area (LAKE). The work is divided into several subareas as depicted on the site map (Appendix). The areas include BB Picnic Area, BB housing, VIP BB Campground, BB Campground, and Boulder Harbor. Boulder City is the nearest town, and Las Vegas is the nearest major metropolitan area.

Project Background: The Boulder Beach Area at Lake Mead National Recreation Area is a heavily used developed recreation area encompassing approximately 70 acres and containing more than 500 mature trees, including cottonwood, palm, eucalyptus, desert willow, palo verde, mesquite and tamarisk species. Over time, many trees within the campground have experienced unmanaged growth, resulting in excessive canopy weight, dead limbs, basal suckers, and standing dead trees. These conditions create increasing safety concerns in areas frequently occupied by visitors and staff. Routine maintenance has not fully addressed the accumulation of hazardous tree conditions, and a comprehensive trimming and removal effort is necessary to restore safe operating conditions within the campground. This project represents a planned corrective maintenance action to address identified hazards and maintain the safe use and functionality of this developed visitor facility.

Scope Summary: Work under this contract consists of providing all labor, supervision, equipment, rigging, aerial lifts, cranes, traffic control, debris hauling, and disposal necessary to perform hazardous tree mitigation and canopy maintenance within the Boulder Beach developed area of Lake Mead National Recreation Area. The work includes pruning, deadwood removal, canopy thinning, palm trimming, removal of standing dead trees, stump grinding, debris hauling, site protection, and restoration of disturbed areas. Work shall be performed in developed recreation areas that remain open to visitors during operations. The contractor shall coordinate work sequencing to maintain safe public access and minimize disruption to campground operations, park housing, and harbor facilities.

A. Work Areas:

1. Boulder Beach Campground – 42 Acres

i. Remove approximately 21 dead trees, sizes vary.

ii. Trim approximately 145 trees

1. Sizes of trees vary, species include but are not limited to cottonwood, gum, eucalyptus, desert willow, palo verde, and mesquite.

iii. Trim palm trees

1. Approximately 60, sizes range from below 10 ft to the greatest extent of growth a palm can achieve.

2. Boulder Beach Picnic Area – 14 Acres

i. Remove approximately 8 dead trees, sizes vary.

ii. Trim approximately 15 trees

1. Sizes of trees vary, species include but are not limited to cottonwood, gum, eucalyptus, desert willow, and palo verde.

iii. Trim 28 palm trees

1. Sizes range from below 10 ft to mature canopy height.

3. Boulder Beach Housing – 8 Acres

i. Remove approximately 6 dead trees, sizes vary.

ii. Trim approximately 85 trees

1. 30 large cottonwood or similar trees and 55 desert willows.

2. Sizes of trees vary, species include but are not limited to cottonwood, gum, eucalyptus, desert willow, African Sumac, Mesquite, and palo verde.

4. Boulder Beach VIP Campground - 3.5 Acres

i. Remove approximately 6 dead trees, sizes vary.

ii. Trim approximately 30 trees

1. Sizes of trees vary, species include but are not limited to cottonwood, gum, eucalyptus, desert willow, and palo verde.

5. Boulder Harbor - 1.5 Acres

i. Remove 1 (one) dead palm tree

ii. Trim 8 living palms

B. Project Requirements

1. Key Personnel: Certified Arborist, an expert in the cultivation and care of trees. A “Certified Arborist” shall serve as the “site superintendent” for this contract and will be present on site a minimum eight (8) hours per day whenever tree work is being performed. The Certified Arborist must have not less than three (3) years’ experience as a direct supervisor of a commercial tree maintenance operation that included tree removal, pruning, and stump removal in industrial, commercial or public sites and must be certified by International Society of Arboriculture (ISA). Experience must be of similar size and scope as the project being quoted. The Certified Arborist will ensure all pruning specifications are performed according to ANSI standards for tree pruning, ensure contract work does not conflict with events, and ensure employees are adequately supervised and proper conduct is maintained. ISA certification document must be provided by the Contractor when bidding on the contract.

2. Work shall be performed around the campground users and will be performed within active public recreation areas. If closures are necessary, a minimum of 3-week notice must be provided to the COR for closure of campsites and loops. Campgrounds are at minimum capacity in August. This would be the best month to perform work.

3. The project will be under a single prime contract.

4. Work areas include paved campground loops, pedestrian areas, and landscaped zones. Contractor shall utilize equipment capable of operating within confined areas without damaging pavement, utilities, irrigation systems, or park infrastructure. Vehicle travel is restricted to existing routes.

5. Provide a schedule to the COR before starting work.

6. A pre-work meeting will be held prior to commencing work.

7. Submit a safety plan to the contracting officer’s representative (COR) prior to work commencement.

C. Tree Pruning

1. Pruning of all trees shall be accomplished under the direction and guidance of an ISA (International Society of Arboriculture) Certified Arborist provided by the Contractor. All pruning will be performed according to the ‘Tree Pruning Guidelines’ developed by the ISA and the ‘Tree Maintenance and Safety Standards’, developed by the American National Standards Institute (ANSI A300). These standards are the accepted standards of the tree care industry.

2. Pruning will consist of crown cleaning /deadwood pruning which includes the removal of all dead, dying, diseased or broken branches 2 inches in diameter or larger throughout the tree. Pruning will also include the removal of crossing / rubbing, weak branches that may compromise the structural integrity of the tree.

3. All portions of the trunk and any tree limbs or branches over 8 inches in diameter must be lowered to the ground by crane or ropes and may not be dropped. The Contractor will be responsible for any damage to the turf, roads or structures caused by dropping parts of the tree.

4. All wood chip particles and debris from the tree removal shall be cleaned up thoroughly and removed daily. The Contractor shall take every precaution to prevent any falling branches or trees from damaging any buildings or fences, adjacent plant material or information panels.

5. The Contractor shall be responsible for repair and or replacement to any damaged turf, fences or other property.

6. The Contractor is responsible to ensure that all pruning cuts shall be made just outside the collar or shoulder ring (branch bark ridge/swollen trunk collar) close to parent stem so that healing can readily start under normal conditions.

7. The Contractor shall retain the natural shape of the tree by removing the entire lateral branches back to their point of origin when reducing the tree’s height and spread.

8. The Contractor is responsible to ensure that all limbs 4 inch in diameter or over must be undercut to prevent tearing of the bark. All branches 8 inch diameter or larger shall be lowered to the ground using proper lowering devices such as ropes.

9. The Contractor is responsible to ensure that all trees shall be pruned to retain the tree’s natural crown characteristics and growth patterns.

10. The Contractor is responsible to ensure that all trees shall have branches removed to permit the sufficient penetration of sunlight and circulation of air through the canopy in conjunction to the aesthetic appearance, natural crown characteristics and growth patterns of the tree. This process is also known as thinning.

11. The Contractor is responsible for ensuring care when removing living and/or dead crossing or rubbing branches, where practicable, so the removal will not leave large holes in the canopy of the tree natural crown characteristics and growth patterns of the tree.

12. The Contractor is responsible for ensuring that, when pruning trees known to be diseased or susceptible to diseases, tools are disinfected with alcohol after each cut and between trees, where there is known to be danger of transmitting the disease on the tools.

13. The Contractor is responsible for reporting to the COR all the following conditions: when old scars are not healing properly; where callus growth is not already established; visible girdling roots, and when there are any structural weaknesses; decayed trunk or branches; and split crotches, or branch exists.

14. The following methods of pruning are NOT acceptable therefore, the contractor is responsible to ensure that these methods are never performed: topping, stubbing, de-horning, and pollarding. Equipment that may damage the tree bark or cambium layer should not be used on or in the tree. The Contractor is not permitted to use climbing spikes or spurs to climb any live tree scheduled for pruning.

15. The Contractor is responsible to ensure that in lifting the bottom branches of the trees for under clearance, care shall be given to symmetrical appearance, aesthetic appearance, natural crown characteristics and growth patterns of the trees.

16. In general, the Contractor shall ensure when reducing the size of a tree and with respect to retaining the tree’s natural crown characteristics and patterns, not more than 1/4 of the total area shall be reduced at a single operation.

17. Palm pruning shall follow ISA Best Management Practices for Palms and shall include removal of dead fronds and fruit stalks while preserving healthy green fronds.

D. Tree Felling

1. Tree felling shall include the complete removal of designated dead, dying, hazardous, structurally compromised, and/or COR-identified trees.

2. All tree removal operations shall be performed under direct supervision of the ISA Certified Arborist.

3. All removal work shall comply with:

i. ANSI Z133 – Arboricultural Safety

ii. ANSI A300 Standards

iii. OSHA 29 CFR 1926

iv. NFPA 241

v. Lake Mead NRA resource protection requirements

4. Tree Removal Requirements

i. The Contractor is responsible to ensure that all trees designated for removal are field verified with the COR prior to cutting.

ii. The Contractor is responsible to ensure that no non-designated tree is removed.

iii. Free-fall felling is NOT permitted in developed campground, housing, picnic, or harbor areas unless approved by the COR.

iv. The Contractor is responsible for ensuring that all limbs and trunk sections over 8 inches in diameter are lowered to the ground using ropes, rigging devices, cranes, or aerial lift equipment.

v. The Contractor shall not drop tree sections in a manner that damages:

1. Asphalt pavement

2. Concrete curbing

3. Irrigation systems

4. Adjacent vegetation

5. Park structures

vi. The Contractor shall be responsible for repair and/or replacement of any damaged property at no additional expense to the Government.

vii. The Contractor is not permitted to use climbing spikes or spurs to climb any tree.

viii. Dead standing trees shall be evaluated prior to removal. Trees will be removed with aerial lifts, cranes, or other mechanical means. Climbing is not an acceptable removal technique.

ix. Palm tree removal shall include removal of fronds prior to trunk sectioning.

x. All debris shall be chipped and hauled off-site daily unless otherwise directed.

xi. Spark arrestors and fire extinguishers are required per crew.

xii. Wildlife protection protocols shall be followed. Work shall stop if nesting birds, desert tortoise, or cultural resources are encountered.

E. Stump Removal (Grinding)

1. All removed trees shall have stumps ground unless otherwise directed.

2. The Contractor is responsible to ensure that underground utilities and irrigation systems are located prior to grinding.

3. Stumps in turf areas shall be ground to a minimum depth of 12 inches below finished grade.

4. Stumps in desert landscape areas shall be ground to a minimum depth of 6 inches below surrounding soil.

5. Surface roots creating trip hazards shall be removed within 48 inches of stump perimeter.

6. Grindings shall be removed in turf areas and holes backfilled with native soil and compacted.

7. Irrigation heads displaced during operations shall be reset and tested.

8. Backfilled areas shall be flush and free of settlement.

9. Unacceptable practices include:

i. Leaving stumps above grade

ii. Backfilling with wood chips

iii. Damaging irrigation systems

iv. Creating depressions or trip hazards

F. Field Verification: The contractor will field verify existing conditions and government’s estimated quantities affecting the work in this contract. The scheduling of field verification site visit(s) will be coordinated with the COR.

G. Performance Period: 120 days after Award. (Approx: 7/9/26 – 11/6/26)

H. Appendix: The Appendix is provided in a separate document titled “A06_Appendix Compressed”, which includes satellite imagery of the area with a breakdown of the work areas. Example photos of trees are included for reference.

1.3 PUBLIC USE OF THE SITE

A. General: The project site will be open to the public during work. The contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Temporary closures may be permitted upon specific written approval of the contracting officer.

1.4 CONTRACTOR USE OF SITE

A. General: Limit use of the site during the work period to the project area limits as outlined on the site map in the appendix document. Do not disturb portions of the site beyond the project area limits.

B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

C. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until 5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer. REQUESTS MUST BE SUBMITTED NO LESS THAN FIVE BUSINESS DAYS IN ADVANCE.

1. January 1, New Year's Day

i. January 1 on Saturday, New Year's Day observed on Friday

ii. January 1 on Sunday, New Year's Day observed on Monday

2. 3rd Monday in January, Martin Luther King, Jr Birthday

3. 3rd Monday in February, Washington's Birthday (Presidents' Day)

4. 4th Monday in May, Memorial Day

5. June 19, Juneteenth National Independence Day

i. June 19 on Saturday, Independence Day observed on Friday

ii. June 19 on Sunday, Independence Day observed on Monday

6. July 4, Independence Day

i. July 4 on Saturday, Independence Day observed on Friday

ii. July 4 on Sunday, Independence Day observed on Monday

7. 1st Monday in September, Labor Day

8. 2nd Monday in October, Columbus Day

9. November 11, Veterans Day

i. November 11 on Saturday, Veterans Day observed on Friday

ii. November 11 on Sunday, Veterans Day observed on Monday

10. 4th Thursday in November, Thanksgiving Day

11. December 25, Christmas Day

i. December 25 on Saturday, Christmas observed on Friday

ii. December 25 on Sunday, Christmas observed on Monday

D. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

E. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified on the attached site map, in the appendix document or as established at the pre-work meeting.

F. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the pre-work meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.

G. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

H. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.

1.5 RESOURCE PROTECTION

A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the Contracting Officer’s Representative (COR) at least five (5) business days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.

2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact Park dispatch at 702-293-8998 immediately if animal is hit or injured or will not move off the road. All vendor personnel working in Lake Mead National Recreation Area must have up-to-date Lake Mead Desert Tortoise Awareness Training. Prior to starting work, contact the Contracting Officer’s Representative (COR) at least five (5) business days in advance to schedule the desert tortoise awareness training.

The following endangered species are found within the park and require certain considerations.

a. Desert Tortoise – Training Required

b. Razorback Sucker – Additional requirements for aquatic activities

c. Humpback Chub - Additional requirements for aquatic activities

3. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment. Archaeological resources are found above and below ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeological sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the pre-work meeting.

4. Nesting Birds: Bird Nesting season is between March 1 and August 31. All work performed in this time frame requires monitoring by park biologist. Working outside of this time frame does not require additional monitoring. If active bird nests are discovered, halt work on that tree and notify the COR immediately. All trees must be surveyed for bird nests prior to the beginning of work on each tree.

5. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.

END OF SECTION 01 11 00

SECTION 01 27 00

DEFINITION OF CONTRACT PRICE ITEMS

PART 1 – GENERAL

1.1 LIST OF CONTRACT LINE ITEMS

A. Contract Price Item No.10 and 20 – Remove Hazardous Trees.

1. These price items consist of all necessary material, labor, and equipment required to trim or remove hazardous trees at Boulder Beach. All removed/demolished equipment and materials shall be transported and legally disposed of off-site.

2. Monthly invoicing acceptable.

3. Quantities are approximate and shall be verified by the contractor. Government is not responsible for inaccurate bids based on the quantities provided.

1.3 SCHEDULE OF VALUES (PRICE SCHEDULE)

A. Submit a schedule of values/Price Schedule (This table is also listed in the solicitation)

Item No.
Schedule of Values

Remove Hazardous Trees at Boulder Beach

QTY
Unit
Total ($)
1
Trim trees at BB Housing
1
Lump Sum
$
2
Remove Trees at BB Housing
1
Lump Sum
$
3
Trim trees at VIP BB Campground
1
Lump Sum
$
4
Remove Trees at VIP BB Campground
1
Lump Sum
$
5
Trim trees at BB Picnic Area
1
Lump Sum
$
6
Remove Trees at BB Picnic Area
1
Lump Sum
$
7
Trim Palm Trees at BB Picnic Area
1
Lump Sum
$
8
Trim Palm Trees at Boulder Harbor
1
Lump Sum
$
9
Trim trees at BB Campground
1
Lump Sum
$
10
Remove Trees at BB Campground
1
Lump Sum
$
11
Trim Palm Trees at BB Campground
1
Lump Sum
$
12
Disposal Costs
1
Lump Sum
$
13
Mobilization/Demobilization
1
Lump Sum
$

Total CLINS 1-13 This is a firm fixed price requirement. All costs associated to perform the work in accordance with the Statement of Work shall be included. It is anticipated that award will be made as a lump sum. For price evaluation purposes, price reasonableness will be based on the total sum of CLIN 1-13.

END OF SECTION 01 27 0

BUREAU OF LAND MANAGEMENT (BLM) 05/22/06

Appendix

See “A06_Appendix_Compressed” attachment.

LAKE – PMIS #349175 2

image1.jpeg

File details come from the government source that posted it. Updated .