B09_Statement_of_Work_revision_Section_E_0002.pdf
PDF 74 KB Posted
- Attached to
- Replace Water System Components, Mojave National P Federal contract opportunity
- Solicitation number
- 140P8121R0007
About this file
This statement of work revision details tasks for replacing water system components at Mojave National Preserve. The contractor will replace three 6-inch gate valves and two each of 2-inch and 1-inch ball valves in the 30,000 gallon storage tank valve vault. The contractor will also install 30 concrete bollards spaced five to five and a half feet apart around the tank and vault perimeter to prevent vehicle access. Relatedly, solicitation 140P8121R0007 from the National Park Service Pacific West Region seeks to replace water system components at Mojave National Preserve.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8121R0007_Amd_0004.pdf | ||
| B09_Daylight_Drain_Detail_amendment_04_0004.pdf | ||
| B09_Contract_Price_Schedule_revision_02_June_14_2021_0003.pdf | ||
| B09_Statement_of_Work_Amendment_03_0003.pdf | ||
| Sol_140P8121R0007_Amd_0003.pdf | ||
| B09_Contract_Price_Schedule_revised_0002.pdf | ||
| Sol_140P8121R0007_Amd_0002.pdf | ||
| B09_Concrete_Collar_Detail_0001.pdf | ||
| 52_204-8_Annual_Representations_and_Certifications_0001.docx | DOCX document | |
| B09_Concrete_Collar_with_Curb_0001.pdf | ||
| B09_Questions_and_Answers_0001.pdf | ||
| B11_Site_Visit_0001.pdf | ||
| Sol_140P8121R0007_Amd_0001.pdf | ||
| B08 Release of Claims.pdf | ||
| B03 General Decision.pdf | ||
| Sol_140P8121R0007.pdf | ||
| B08 Transmittal.pdf | ||
| B08 MOJA Map.pdf | ||
| B08 Invoice Payment Request.docx | DOCX document | |
| B08 Contract Price Schedule.pdf | ||
| A04 Statement of Work.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6. Tasks (revised 6-4-2021)
E. 30,000 Gallon Storage Tank Valving, Water Meters, & Bollards (revised 04 June 2021)
1. Replace tank valves in tank valve vault:
a. Three (3) 6-inch gate valves (revised 04 June 2021),
b. Two (2) 2-inch ball valves,
c. and two (2) 1-inch ball valves.
d. Remove existing valves and salvage for NPS.
2. (Requirement removed 04 June 2021)
3. At ground surface, demarcate tank and tank valve vault perimeter with concrete bollards
(count: 30 bollards) at a spacing of five (5) to five and a half (5.5) feet intervals to prevent vehicle encroachment onto the ground surface above the tank and tank valve vault.