This document is an amendment to a statement of work for a federal contract opportunity to replace water system components at Mojave National Preserve. The amendment revises tasks to replace 6-inch gate valves at the supply to the Visitor Center and Fire Center, as well as at a daylight drain. It also revises the material requirements section to include furnishing all materials, equipment, and labor to install 6-inch gate valves with valve cans as well as 6-inch gate valves within the tank vault, including excavation, backfill, compaction, valves, valve cans, concrete collars and all other work to complete installation. The related federal contract opportunity is solicitation number 140P8121R0007 from the Department of the Interior National Park Service Pacific West Region to replace water system components at Mojave National Preserve.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Daylight_Drain_Detail_amendment_04_0004.pdf | ||
| Sol_140P8121R0007_Amd_0004.pdf | ||
| B09_Contract_Price_Schedule_revision_02_June_14_2021_0003.pdf | ||
| Sol_140P8121R0007_Amd_0003.pdf | ||
| B09_Contract_Price_Schedule_revised_0002.pdf | ||
| B09_Statement_of_Work_revision_Section_E_0002.pdf | ||
| Sol_140P8121R0007_Amd_0002.pdf | ||
| B09_Concrete_Collar_with_Curb_0001.pdf | ||
| B09_Questions_and_Answers_0001.pdf | ||
| B09_Concrete_Collar_Detail_0001.pdf | ||
| 52_204-8_Annual_Representations_and_Certifications_0001.docx | DOCX document | |
| B11_Site_Visit_0001.pdf | ||
| Sol_140P8121R0007_Amd_0001.pdf | ||
| Sol_140P8121R0007.pdf | ||
| B08 MOJA Map.pdf | ||
| B08 Invoice Payment Request.docx | DOCX document | |
| B08 Contract Price Schedule.pdf | ||
| A04 Statement of Work.pdf | ||
| B08 Release of Claims.pdf | ||
| B03 General Decision.pdf | ||
| B08 Transmittal.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6. Tasks, B. Visitor Center, subpart 1 (revised 14 June 2021)
Replace 6-inch gate valves (Mueller Resilient Wedge or equal) at supply to Visitor Center (V_17), at supply to Fire Center (V_18), and at daylight drain (V_19).
6. Tasks, C. Fire Center, subpart 1 (revised 14 June 2021)
Replace existing fire hydrant and 6-inch gate valve with new fire hydrant (Mueller Modern Centurion or equal) and 6-inch gate valve (Mueller Resilient Wedge or equal).
Part 12. Material Requirements, subpart 12.E is now two sections, 12.E.1 and a 12.E.2 (revised 14 June 2021)
12.E.1 6-inch Gate Valves with Valve Can – This item includes furnishing all materials, equipment, and labor for installation of gate valves as specified. The work includes, but is not limited to excavation, backfill, compaction, valve, valve can, concrete collar, and all other work necessary to complete the installation.
12.E.2 6-inch Gate Valves in Tank Vault – This item includes furnishing all materials, equipment, and labor for installation of gate valves as specified. The work includes, but is not limited to working within the tank’s valve vault, disassembly and re-assembly with required reconfigurations of existing piping & appurtenances along with new valves and appurtenances, and all other work necessary to complete the installation.