140P4225R0007_-_Amendment_0003_-_Questions_and_Answers_0003.pdf
PDF 110 KB Posted
- Attached to
- Shenandoah National Park (SHEN) Access Routes
- Solicitation number
- 140P4225R0007
About this file
This document is a Questions and Answers (Q&A) amendment for Solicitation 140P4225R0007, a competitive HUBZone set-aside contract for repairing access routes at Shenandoah National Park. The project involves pavement repair, overlay, crack sealing, and related infrastructure work in the Big Meadows Campground area, with an estimated value between $1-5 million and a 75-day performance period.
Key details include a Notice to Proceed (NTP) date of 8/18/25, with work potentially beginning 9/21/25, though administrative blackout dates from September through November may impact the timeline. The contract requires compaction testing, utility adjustments, and pavement markings, with approximately 12,769 square feet of walkways to be paved. Contractors must field verify quantities, comply with park restrictions, and submit documentation like the Past Performance Questionnaire by 4 PM on the specified due date. Work hours are limited to 9-4 during weekdays, with no weekend construction activities permitted in the campground area.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4.10 states to provide as-built draw are to scale in order to provide wha
Please clarify where the starting poi yellow on sheet 4 appears arbitrary
For estimating purposes please prov
SOW 4.5 Compaction Testing. It is u pavement itself, please clarify. Due exceed 30-40 locations. Should we need to carry for?
For the full depth pavement repair a not shown on the typical details
Due to the award date being in Aug mid November, please confirm this
Is this a tax exempt project?
For the bid option of 2" overlay ove widths of the walkways. If the walk ones to be paved and the average w
SOW states to adjustment of utilitie areas of where utilities the need adj proposals to cover these adjustmen
For estimating purposes, please pro
With a NTP of 8/18/25 and Factor 2 take place beginning 9/21/25 and e after April 1st.
Moving materials to and from the S Dump Trucks. It was stated that a w Could you please provide the actual waiver and what weight limit would
Park Entrance: Is there another ent accessed without going through a tu
Different Treatment Locations: Wil locations for the applied surfaces, b
Attachment 7 (Past Performance Q Wednesday, 2 July. Given the organ decision, contacting prior customer performance questionnaire (PPQ) d moving the due date closer to the c
Please confirm the form "Report on for submission with our proposal.
Working Hours: Would the Nationa Monday thru Thursday so they are o There would not be any constructio
Reference Drawings
Drawings
SOW
Solicitation
Contract T&C
SOW
SOW
SOW
SOW
Drawings
SOW
ings. Confirm the contractor will be provided CAD or PDF drawings that at is required.
int of the 2" overlay on the main road coming in. The location shown in vide the lineal footage for the crack repair.
understood compaction testing is for granular base / fill areas and not the e to the areas where possible compaction test need to occur, could include 30-40 compaction test? Are there any other types of testing we areas, what is the thickness of the existing pavement? This dimension is ust, and the no work in the park being last week of September through work will not happen until the spring of 2026.
er the walkways, please provide a map showing these walkways and the kways to be paved are the trails shown on the drawing, please clarify the width.
es to match final pavement elevations, (if applicable) Are there any know justment? If not, what allowance should all contractors carry within their nts?
ovide the quantity for the pavement markings
140P4225R0007 Questions & Answers D
Shenandoah National Park – Repair Big Me Contractor Question
2, Note 1 in the Solicitation states the park will not allow paving work to nding on 4/1/26. Please confirm the milling and paving will not start until
Attachments 4
3.2 On Site Hours
1.2 Work Covered by the
Contractors Documents
1.2 Work Covered by the
Contractors Documents
1.2 Work Covered by the
Contractors Documents
Attachment 7 (Past Performance Questionnaire)
Due Date
Site: It was discussed that within the park there are weight restrictions on waiver could be applied for to allow heavier loads to move within the park.
l weight restrictions and height restrictions currently in place without a d be allowed with an approved waiver?
rance to the park near Harrisonburg, the plant location, that can be unnel or other height restrictions such as with the Main Entrance?
l the National Park Service provide maps prior to the bid indicating the being overlay, mill and pave, seal coat and fog coat?
Questionnaire) has to be completed and delivered no later than 0900 on nized site visit on 25 June was a determining factor for bid/no-bid
(s), obtaining permission(s), completing, and submitting the past uring a holiday week will be difficult. Is the government amenable to urrent solicitation due date of 14 July?
n Limitations on Subcontracting" is to filled out during the project and not l Park Service consider allowing the Contractor to work 10-hour days, out of the way for Visitors that arrive Friday to stay for the weekend?
on activities on Friday, Saturday or Sunday.
Either CAD or PDF acceptable
Will be marked by COR prior to sta
Crack sealing is estimated to be ap
Correct, compaction test will be fo width of access road. Based on pro compaction tests. However, the co
Dependent on date of award, it is functions and submittals. The park
Tax exemption form will be provid
Average width of trail is 2.5 - 3 fee within each loop of the campgroun
SOW and Drawings note field verif
SOW Background: Asphalt estimat
Approximately 65 directional arrow field verify.
Document - Amendm adows Campground A
Dependent on date of award, it is functions and submittals. The park 2026 work/paving season is at the
The contractor may submit a waive attached Superintendents Compen
Contractors can enter through Swi
Drawings/maps were provided wit
The Past Performance Questionna
4PM.
Per "Instructions for the Submissio offerors shall complete and submit amounts paid; however, for solicit anticipated subcontractors. Refer t
The form will be evaluated as part with the subcontracting requireme Due to the quiet hours within the c weekend work will be approved.
art of work - location will be directly adjacent to Campground Fee booth.
pproximately 500 LF, however, it is the contractors responsibility to field verify.
Government Response or aggregate base. One compaction test per each location where full depth repairs span the full ovided mapping and known field conditions, it is estimated to be 20 locations that are subject to ontractor will need to field verify.
not likely that work will occur due to the blackout dates of Sept through Nov due to administrative k may be willing to discuss options in the event that work can begin outside of the blackout period.
ed upon request from the awarded contractor.
et wide. Total square feet of walkways to be paved is 12,769. All paved walkways are located
nd. The trails on the exterior of the loops are campsite access trails and are not paved.
fication is responsibility of Contractors ed depths vary between 2-8 inches ws and approximately 1,300 LF of striping. These are estimates and contractors are responsible to ment 0003
Access Routes not likely that work will occur due to the blackout dates of Sept through Nov due to administrative k may be willing to discuss options in the event that work can begin outside of the blackout period.
discretion of the contractor as long as the schedule has been approved by the Government.
er request; however, approvals are not guaranteed and are reviewed on a case-by-case basis. See ndium listing weight restrictions provided under amendment 2 ift Run Entrance accessed off Route 33 to avoid the tunnel.
th the solicitation package ire is due 7 days prior to proposal due date. The current proposal due date/time is July 28, 2025 at on of Offers and Other Information – Competitive Source Selection" page 42 of the solicitation t attachment 4 "Report on Limitation on Subcontracting" form. The form itself requests input of ation purposes, input projected amounts based on your proposed pricing and that of your to Clauses FAR 52.219-14 for associated information.
of the offeror’s responsiveness. The report will be reviewed and evaluated to ensure compliance ents.
campground, the construction activities would have to remain between 9-4 during weekdays. No
Sheet1
File details come from the government source that posted it. Updated .