This is a price schedule (Attachment 9) for a federal contract to implement a Towpath Hazardous Tree Management Plan for FY26. The contract involves tree removal, pruning, and stump grinding services across multiple work packages and geographic locations.
The base task consists of two work packages: Work Package 1 requires removal of 131 trees, pruning of 39 trees, and grinding of 2 stumps; Work Package 2 requires removal of 117 trees, pruning of 22 trees, and grinding of 3 stumps. Both base tasks are priced as firm fixed price line items. The contract includes eight optional inspection tasks covering various geographic segments along a canal or towpath system, measured in miles and mileposts: Point of Rocks to Little Catoctin (4.31 miles, 50 estimated hours); Weverton to Lock 34 (3.47 miles, 40 hours); Cohill to Lockhouse 56 (5.51 miles, 30 hours); Lockhouse 56 to Lock 59 (10.38 miles, 96 hours); Lock 59 to Paw Paw (9.60 miles, 88 hours); Spring Gap to Evitts Creek (5.63 miles, 56 hours); Trails Parkwide inspection of 25 designated trails (120 hours); and Two-Year Cyclic Maintenance Areas inspection of 23 areas (110 hours). All inspection work requires ISA Certified Arborist labor at vendor-provided wage rates, with material/equipment costs not to exceed $500 per option task. The schedule requires vendors to provide wage rates for multiple labor CLINs within each task, and all pricing fields remain blank pending vendor submission. A grand total line for base and all option CLINs is included at the bottom of the schedule.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY26
QUANTITY UNIT AMOUNT
1 EA
1 EA
Labor
CLIN
Wage Rate (Vendor Provides)
14.1
14.2
14.3
14.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 1
Labor
CLIN
Wage Rate (Vendor Provides)
16.1
16.2
16.3
16.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 2
Labor
CLIN
Wage Rate (Vendor Provides)
18.1 18.2
18.3
18.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 3
Labor
CLIN
Wage Rate (Vendor Provides)
20.1
20.2
20.3
20.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 4 -$
Labor Category Estimated Hours (NPS provides) Total Labor NTE
ISA Certified Arborist 96 $ -
OPTION TASK 4 / Inspection: Inspect Lockhouse 56 - Lock 59, Mileposts 136.21 - 146.59
a. Total 10.38 Miles
Material/Equipment (NTE)
Labor Category
Labor Category
Material/Equipment (NTE)
OPTION TASK 2 / Inspection: Inspect Weverton – Lock 34, Mileposts 58.1 - 61.57
a. Total 3.47 Miles
Estimated Hours (NPS provides) Total Labor NTE
ISA Certified Arborist 56 $ -
Material/Equipment (NTE)
Estimated Hours (NPS provides)
OPTION TASK 3 / Inspection: Inspect Cohill – Lockhouse 56, Mileposts 130.7 - 136.21
a. Total 5.51 Miles
ISA Certified Arborist
Total Labor NTE
OPTION TASK 1 / Inspection: Inspect Point of Rocks – Little Catoctin, Mileposts 48.2 - 52.51
a. Total 4.31 Miles
Labor Category
ISA Certified Arborist
Material/Equipment (NTE)
Total Price for all locations:
Total Labor NTE
Estimated Hours (NPS provides)
The below Optional Tasks are for Hazard Tree Inspections throughout the designated areas.
Attachment 9 - Price schedule
LINE ITEM DESCRIPTION RATE
10 Firm fixed Price
Base Task 1: Work Package 1
a. Removal: Remove 131 tree(s) identified in Enclosure 1.
b. Pruning: Prune 39 tree(s) identified in Enclosure 1.
c. Grinding: Grind 2 existing stump(s) identified in Enclosure 1.
Firm fixed Price
Work Item: Implement Towpath Hazardous Tree Management Plan - 2026
Base Task 2: Work Package 2
a. Removal: Remove 117 tree(s) identified in Enclosure 1.
b. Pruning: Prune 22 tree(s) identified in Enclosure 1.
c. Grinding: Grind 3 existing stump(s) identified in Enclosure 1.
Labor
CLIN
Wage Rate (Vendor Provides)
22.1
22.2
22.3
22.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 5
Labor
CLIN
Wage Rate (Vendor Provides)
24.1
24.2
24.3
24.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 6
Labor
CLIN
Wage Rate (Vendor Provides)
24.1 24.2 24.3
24.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 7
Labor
CLIN
Wage Rate (Vendor Provides)
24.1 24.2 24.3
24.4 (Maximum allowable cost $500)
Total Lump Sum For Option Task 8
Total Price for all Options
Total Labor NTE
Material/Equipment (NTE)
Labor Category Estimated Hours (NPS provides) Total Labor NTE
Material/Equipment (NTE)
Grand Total with base CLINs and All Option CLINs:
ISA Certified Arborist 80 $ -
ISA Certified Arborist 120 $ -
OPTION TASK 8 / Inspection: Inspect Two-Year Cyclic Maintenance Areas
a. Inspect 23 Cyclic Maintenance Areas (Areas provided in SOW)
Labor Category Estimated Hours (NPS provides)
Labor Category Estimated Hours (NPS provides) Total Labor NTE
ISA Certified Arborist 56 $ -
OPTION TASK 6 / Inspection: Inspect Spring Gap - Evitts Creek, Mileposts 173.37 - 179
a. Total 5.63 Miles
OPTION TASK 7 / Inspection: Inspect Trails Parkwide
a. Inspect 25 Trails Parkwide (Areas provided in SOW)
Material/Equipment (NTE)
ISA Certified Arborist 88 $ -
70 & 80
OPTION TASK 5A and 5B / Inspection: Inspect Lock 59 – Paw Paw, Mileposts 146.5 – 156.1
a. Total 9.60 Miles
Material/Equipment (NTE)
Labor Category Estimated Hours (NPS provides) Total Labor NTE