The file is a Price Schedule Excel spreadsheet for a National Park Service (NPS) contract to preserve historic structures at Hampton National Historic Site in Towson, Maryland. The solicitation (140P2025R0043) is set aside for a Competitive 8(a) business concern and involves design-bid-build construction with 13 contract line items (CLINs), including base work and optional rehabilitation tasks. Base work includes Farm Side Rehabilitation, Garden Service Cluster Area Rehab, and Hampton Mansion & Area Exterior Improvements, while optional tasks cover specific building and infrastructure rehabilitation projects such as the Ice House, Caretaker's Cottage, Mule Barn, and various other site structures.
The contract offers both base and optional pricing, with options valid for 12 months from the award date. The pricing schedule includes detailed cost breakdown categories ranging from foundations and construction to site improvements, with space for itemizing material, labor, equipment, and other direct costs. The project requires comprehensive rehabilitation of multiple historic structures and infrastructure elements at the Hampton National Historic Site, focusing on preservation and improvement of the site's historic buildings and surrounding areas.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price CLINs
| Contract Price Schedule | ||||
| National Park Service (NPS) - Denver Service Center (DSC) | ||||
| Solicitation Number: | 140P2025R0043 | |||
| PARK - PMIS: | HAMP 32607 | |||
| Developed Area: | Hampton National Historic Site, Towson, MD | |||
| Project Title: | Preserve Historic Structures | |||
| CLIN | Contract Line Item (CLIN) Title | Quantity | Unit of Measure | Total Price |
| 0001 | Farm Side Rehabilitation - Base | 1 | Job | |
| 0002 | Garden Service Cluster Area Rehab- Base | 1 | Job | |
| 0003 | Hampton Mansion & Area Exterior Improvements - Base | 1 | Job | |
| 0004* | Ice House Rehabilitation - Option A | 1 | Job | |
| 0005* | Hampton Mansion Interior Improvements - Option B | 1 | Job | |
| 0006* | Caretaker's Cottage Rehabilitation (Except Fire Alarm & Intrusion Detection) - Option C | 1 | Job | |
| 0007* | Mule Barn Rehabilitation / Long House Granary Rehabilitation - Option D | 1 | Job | |
| 0008* | Road Maintenance (Except Repairs for Waterline and other utility-required repairs, no Garden Service Road - Option E | 1 | Job | |
| 0009* | Green Metal Building Rehab (No Fire Alarm & Intrusion Detection) - Option F | 1 | Job | |
| 0010* | Green House #1 Rehabilitation (No Site Work) - Option G | 1 | Job | |
| 0011* | Dairy Rehabilitation - Option H | 1 | Job | |
| 0012* | Pump House Rehabilitation - Option I | 1 | Job | |
| 0013* | Provide Separate CMR Office Space | 1 | Job | |
| TOTAL Base Price - ALL CLINs (0001 through 0003) --------------------------------------------------------------------- | ||||
| TOTAL option Price - ALL CLINs (0004 through 0013) -------------------------------------------------------------------- | ||||
| TOTAL PROPOSED PRICE - ALL CLINs (0001 through 0013) ------------------------------------------------------ | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. | ||||
| *Otpion prices are valid 12 months from award date. |
Cost Breakdown
| Item No. | Description | Material Cost/Unit | Total Material Cost | Labor Cost/Unit | Total Labor Cost | Equipment Cost/Unit | Total | Direct Cost/Unit | Total Direct Costs |
| Equipment Cost | |||||||||
| 1 | Foundations | ||||||||
| 2 | Basement Construction | ||||||||
| 3 | Superstructure | ||||||||
| 4 | Exterior Enclosure | ||||||||
| 5 | Roofing | ||||||||
| 6 | Interior Construction | ||||||||
| 7 | Staircases | ||||||||
| 8 | Interior Finishes | ||||||||
| 9 | Conveying Systems | ||||||||
| 10 | Plumbing Systems | ||||||||
| 11 | HVAC | ||||||||
| 12 | Fire Protection | ||||||||
| 13 | Electrical | ||||||||
| 14 | Equipment | ||||||||
| 15 | Furnishings | ||||||||
| 16 | Special Construction | ||||||||
| 17 | Selective Building Demolition | ||||||||
| 18 | Site Preparation | ||||||||
| 19 | Site Improvements | ||||||||
| 20 | Site Mechanical Utilities | ||||||||
| 21 | Site Electrical Utilities | ||||||||
| 22 | Other Site Construction | ||||||||
| 23 | Standard General Conditions | ||||||||
| Subtotal Direct Construction Costs | |||||||||
| 24 | Design Contingency | ||||||||
| 25 | Total Subcontracting | ||||||||
| 26 | Overhead | ||||||||
| 27 | Profit | ||||||||
| 28 | Bonds | ||||||||
| 29 | Insurance | ||||||||
| 30 | Permits | ||||||||
| Total Construction Cost |
Labor Rates example
| Prime Labor Category | Rates | Hour | Total Labor Cost | |
| Project Executive | ||||
| Project Manager | ||||
| Superintendent | ||||
| Quality Control Manager | ||||
| Safety Manger | ||||
| Admin Support | ||||
| Subcontractor Labor Category | ||||
| Foremen | ||||
| Laborer | ||||
| L |
Design-Bid-Build (DBB) Sample
| Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Old Faithful | ||||
| Project Title: | Johnstonian Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | Lineal Feet | - 0 | |
| 3 | Sanitary Sewer Line | 200 | Lineal Feet | - 0 | |
| 4 | Rock Excavation | 150 | Cubic Yards | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) --------------------------------------------------------------------------------- | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | - 0 | |
| 6 | OPTION B, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) ------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Build (DB) Sample
| Contract Price Schedule - Design-Build (DB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Yosemite Valley | ||||
| Project Title: | Design and Build a New Structure | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 and 2) --------------------------------------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ---------------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ---------------------------- | $0.00 | ||||