Sol_140P2024R0069_Amd_0009.pdf
PDF 169 KB Posted
- Attached to
- KALA 248432 construct a fuel farm and dispensing
- Solicitation number
- 140P2024R0069
About this file
This is Amendment 0009 to solicitation 140P2024R0069, issued by the National Park Service DSC Contracting Services Division in Denver, CO, with an effective date of December 5, 2024.
The amendment makes three key changes to the solicitation: 1) Replaces bollards shown on drawing M1 with Jersey Barriers that must meet 2024 IFC, NFPA 30A, Maui County Fire code, AASHTO, Hawaii DOT, and Federal Highway Administration standards for protecting fuel tanks; 2) Adds CLIN 1A for fuel commissioning that includes minimum fuel required to commission both Mogas and Diesel fuel tanks; and 3) Updates the wage determination to the version dated November 15, 2024. The contract includes a base requirement for above-ground fuel storage tanks and dispensing system (CLIN 1), fuel commissioning (CLIN 1A), and an option for concrete access driveway (CLIN 2).
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0069 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
12/05/20240009
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/23/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to change the technical specifications in regard to
Bollards, create a new CLIN for fuel commissioning, and update the wage determination.
Please see continuation page for further details.
CO: Mark Barber
CS: Amy Solomon
PM: David Futch, COR
PS: Elisabeth Jackson, COR
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Mark Barber
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
CONTINUATION PAGE Page 2 of 2
The purpose of this amendment is to change the technical specifications in regard to Bollards, create a new CLIN for fuel commissioning, and update the wage determination. The following changes are hereby made:
1. The Bollards shown on drawing M1 are hereby replaced with Jersey Barriers adhering to the codes below. The Jersey Barriers should protect all around the tank not to exceed code and not around the empty field. Provide the correct number of Barriers to properly protect the fuel tanks per codes below.
Must meet 2024 IFC 5703.6.4 Protection from vehicles Section 312 Vehicle Impact Protection 312.1 and 312.2 for spacing from each other and from the tanks. Reference section
312.3 for other barriers in which the Jersey Barrier falls under.
Must also meet NFPA 30A and Maui County Fire code.
When determining specs for the jersey barriers please refer and adhere to AASHTO Roadside Design Guide, Hawaii DOT standards, and the Federal Highway Administration standards.
2. CLIN 1A is hereby added to the Section B Contract Price Schedule. This CLIN should include the minimum amount of fuel required to commission both the Mogas and Diesel fuel tanks. A revised Schedule B is as follows:
CONTRACT LINE
ITEM NUMBER (CLIN) CONTRACT LINE ITEM (CLI) TITLE UNIT OF
MEASURE TOTAL PRICE
1 Above Ground Fuel Storage Tanks and Dispensing System.
LS
1A Fuel Commissioning for Mogas and Diesel Fuel Tanks LS
TOTAL BASE PRICE (Contract Line Item Number 1 and 1A)
2 (Option A) Concrete Access Driveway
LS
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 2) TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 2) All measurement and payment information is included in the project specifications, Section 012700.
3. The wage determination included in the solicitation is hereby deleted and replaced with the updated version dated 11.15.2024.
4. All other terms and conditions remain unchanged.
File details come from the government source that posted it. Updated .