This document contains questions and answers regarding Solicitation Number 140P2027R0170 for rehabilitation work at Yellowstone National Park buildings. The solicitation involves masonry and structural repairs, window and door replacements, roof repairs, and hazardous material abatement for various park buildings. Questions addressed clarification around safety roles, past performance periods, hazardous materials handling, permitting responsibilities, work hours and noise levels, staging areas, and construction methods. The National Park Service will provide archaeological and cultural monitors, and occupants are expected to remain in the buildings during construction.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question: Answer: Amendment No.:
Can Site Superintendent function as the safety specialist? No 1
If possible to open the past performance period to at least 10 years Yes 1
Could you quantify the masonry repair scope in the crawl space / storm cellars for buildings 9 and 10?
Could we receive clarification regarding the paint preparation on the chimneys prior to repainting? Will they be fully abated and stripped to bare masonry prior to painting, or will they be prepared and encapsulated with new paint?
Are we to assume that all existing chimney bracing will be removed and replaced with new stainless steel bracing, and with a quantity of two braces per chimney?
Are we correct to assume that there will be no bracing on the chimneys for stone buildings 2 and 3?
Solicitation p. 66 of 85: Factor 2 Project Experience requests prime contractor experience where the general contractor self-performed at least 60% of the cost of the contract, excluding materials. As 60% is an unusually high percentage of self-performance for a general contractor, we ask NPS to strike this phrase.
The solicitation requirement for this factor will be reduced to 30% of the cost of the contract, excluding materials for projects that were self-performed. 1
Specifications: There are no specifications for hazardous materials. Under spec 01-31-00-9, para 1.9C, it states
“Hazardous Waste Removal, Transportation, and
Disposal- To be determined.” Please confirm if there are any hazardous materials on this project, i.e., lead paint, asbestos, etc.
The specifications are being provided as part of
Amendment 1. Please see attachment 1
Given the magnitude and complexity of this solicitation, we kindly request a minimum 2-week extension of the current due date. Contractors will need adequate time after the schedule site visit on 7/13 to put together a responsible bid.
An extension in the proposal due date will not be granted. 1
Spec 01 35 91, para 1.4 mentions that there will be a
Historic Preservation Treatment Specialist. It also states that this person’s qualifications will meet 36 CFR Part 61.
However, there are no qualifications listed in 36 CFR Part
61. This CFR references “Procedures of State, Tribal, and
Local Government Historic Preservation Programs.”
Page 24 of 26 of the attached "standards".pdf lists the Professional Qualification Standards used by the NPS. Additional context can be found at The
Secretary of the Interior Professional Qualifications
Standards: https://www.doi.gov/pam/asset-management/historic-preservation/pqs 1
Please provide the specific requirements for the HPT
Specialist.
Page 24 of 26 of the attached "standards".pdf lists the Professional Qualification Standards used by the NPS. Additional context can be found at The 1
Please define the role and responsibilities for the HPT
Specialist. Please see Q5 above. 1
Will the HPT Specialist need to be on site for any specific scope of work? Please see Q5 above. 1
Spec 01 35 23, para 1.4 B calls for a Site Safety
Supervisor. Can this role also be filled by the same person as the Site Superintendent? No - these must be separate positions. 1
Can one person serve as the SSHO, CQC and
Superintendent? If not, please clarify which roles can be combined so that the total number of field managers on site can be determined.
No, these must be separate positions as stated in the solicitation. 1
All around each house, there were numerous borrows seen for chipmunks and other animals. Please clarify who will be responsible for their removal. Once captured, did NPS want them released or handled by an exterminator?
The contractor is not responsible for capturing and disposing of rodents that are encountered during the performance of the site work. 1
01 57 23- Temp SWPP. Please clarify who is responsible for the NPDES permit fees.
The contractor is responsible for the NPDES permit fees. 1
What type of historic mortar analysis is required? E.g., Petrographic, X-Ray Diffraction, X-Ray Fluorescence, Scanning Electron Microscopy.
Mortar analysis was completed for each building in
August 2021. "Custom Mortar Matching Reports" by U.S. Heritage Group are included in Appendix C of the Project Specifications. Mortar mix designs 1
How many mortar test samples are required per building? Please identify which parts of building the tests should be taken from? E.g., Chimney, foundation, etc.
Mortar Aanalysi was completed for each building in
August 2021. Custom Mortar Matching Reports by
U.S. Heritage Group are included in Appendix C of the Project Specifications. Mortar mix designs listed in 04 03 00 of the Project Specifications are 1
21 Will we receive the HAZMAT specs? The Hazmat Specifications were released with 1
22 Will housing be provided or will it be on our own? The contractor must supply their own housing. It 1
23 Which lanes do we use to enter the park? If entering the Park through the Gardiner entrance 1
24 What are the work hours for this project? Normal work hours are 7:00 a.m. to 6:30 p.m. 1
25 What is the max decibel for noise? The max decibel for noise levels can be found in 1
Summary of Work, Para 1.3B states that the buildings will be occupied during construction. This will present significant safety concerns on the project. Will occupants be required to wear full PPE, including but not limited to hard hats, steel toe shoes, long pants, short sleeve shirts, safety goggles, during construction? (that is a requirement of our insuance carrier and our safety plan). As you know there will also be work done overhead in the attic. It is unsafe to have occupants underneath the overhead work during construction. Can residents be moved out at least during work hours M-F?
The Park will not unilaterally require that occupants wear PPE. The sequencing plan in
SUMMARY OF WORK (01 11 00), 1.3(c)(4) requires that the contractor describe methods for limiting disturbance to building occupants while also providing safe access directly into buildings. The
CO will evaluate the contractor's plan and ensure that whatever roof construction method is employed will sufficient limit disturbance to the building occupants. The expectation is that the contractor will use every reasonable construction method available to minimize disruption to the occupants. Occupants will remain in their homes during the entirety of the construction operations. 1
27 Will archaeological and Cultural monitors be provided?
The Park will be providing the archeological and cultural resources monitors. 1
28 What is the NTP date for planning purposes? The anticipated Notice to Proceed date is October 1
29 Who is responsible for snow removal in staging areas
The contractor is responsible for snow removal within the staging areas. 1
30 Can the paint removal be done onsite? Paint removal can be performed on site as long as 1
Please clarify if the 808 calendar days PoP pertains to the “base bid only” or “base and all options”? We have contractors concerned with expected weather impacts to perform work that has cold weather constraints which will prevent tasks for extended periods/months.
The period of performance is 808 calendar days and pertains to all CLIN's including the optional CLIN's. 1
Temporary facilities - What size storage container can we place on the site? How many storge containers can we bring on site?
Storage container size limited by extents of staging area. 1
Can we have a storage container on Officer’s Row if we have it blocked visually with temp fencing and screens?
Not prohibited by the contract, but YELL should be consulted. The Park requires at least one lane be provided for vehicle traffic to pass through the area. 1
Where can we place our work trailer? Can one be placed at Officer’s Row? Work trailer = job office?
Work trailer can be placed in area designated as staging location behind the Officer Row housing.
See Sheet ( G-005 ) 1
Are we permitted to use the public toilets in lieu of bringing in temp toilets?
No - the contractor must provide their own temporary toilet facilities, please reference
Construction Specification 01 50 00 (Section 3.2(e). 1
Spec 06 03 12-6, para 3.3 E.1&2 states to remove landscape covering at the end of each work day. Can we use a breathable cover and pull it off only on the weekends. No 1
½” plywood added. Will now be created a 1/2” gap between the window and the trim. (see below sketch) How do we fill the void? We assume that
NPS wants to salvage and reuse the existing trim and jamb. Hence, we will need to put in a filler piece. Will that be acceptable
The existing trim and jamb must be salvaged and reused to the greatest extent possible. However, existing sheathing (assumed to be true 1x) will be removed and replaced with 1/2" plywood sheathing and 1/4" furring strips. There is no net gain in sheathing thickness. 1
Spec 07-31-16-2 , para-1.6 mock ups , states to construct an 8’x8’ roofing mockup, on the ground. Can that be 4’x4’ on the ground.
No - mockup must be as denoted in the specification. 1
Spec 07 31-16-3 Field conditions 1.8A states not to install metal shingles when windchill
<45degrees? This is unnecessarily restrictive and will limit the ability to have the work done. Can this be change to above 35 degrees ambient. I don’t understand the relevance of wind chill, either, unless the concern is that the workers will be too cold to do a good job.
Refer to basis of design product literature for required ambient air and windchill requirements. 1
Please clarify for the areas where we are to apply to paint to existing materials, are we to scrape down to a sound surface, or will we have to remove the existing paint 100% to the bare material.
Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate. 1
If there is a combination of scraping and full removal, please clarify which areas those would apply.
Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate. 1
Please clarify that this a lead in construction project, not a lead abatement project.
Lead abatement is the responsibility of the contractor. Refer to 02 83 00 – Lead-Based Paint
Stabilization, Component Removal, and Soil
Removal. Refer to Appendix B: Hazardous Materials
Inspection Report, Tetra Tech, Inc., August 2021. 1
There are no depths indicated for the existing utilities.
Can we assume that all the utilities will be deep enough so as not to impact the new sprinkler systems?
Proper notification will need to be made to 811 to identify marked utilities as well as notifying the
Park relative to any owned Park utilities so they can marked appropriately. 1
Should any of the options be taken, we would like to request the ability to include additional time to the overall contract duration (if needed). Since there is no definition as to which option will be taken, we request the ability to add days to the overall contract duration based on the number of options taken by NPS. Ie.
If 1 option is taken, add ____ calendar days
If 2 option are taken, add ____ calendar days
If 3 option are taken, add ____ calendar days
Etc.
The total period of performance for the base CLIN's and all option CLIN's is 808 calendar days. 1
Sheet 02-A901, why does only 4 openings show ‘exterior trim’ with level 1 repair? Why are the other windows shown as N/A? On the elevations, there does not seem to be any difference in these windows.
The exterior trim repair level for 2.N1.04, 2.N1.05, 2.N1.06, and 2.N3.01 should be “N/A.” The reason
“N/A” is noted for all exterior trim, is because these windows are set into a stone masonry wall and do not have exterior trim. 1
Given the magnitude and complexity of this solicitation, we kindly request a minimum 2-week extension of the current due date. Contractors will need adequate time after the schedule site visit on 07/13/2023 to put together a responsible bid.
An extension in the proposal due date will not be granted. 1
Solicitation P. 66 of 85: Factor 2 Project Experience requests prime contractor experience where the general contractor self-performed at least 60% of the cost of the contract, excluding materials. As 60% is an unusually high percentage of self-performance for a general contractor, we ask NPS to strike this phrase.
The solicitation requirement for this factor will be reduced to 30% of the cost of the contract, excluding materials for projects that were self-performed. 1
Specifications: There are no specifications for hazardous materials., Under Spec 01-31-00-9, para 1.9c, it states
"Hazardous Waste Removal, Transportation and Disposal
- To Be Determined". Please confirm if there are any hazardous materials on this project i.e. lead paint, asbestos, etc.
These are being provided as part of Amendment 1.
Please see relative attachments. 1
The siding on the dormers on Buildings 2 and 3 consists of shingles. Is there any scope associated with these shingles?
The siding on the dormers on Buildings 30-33 consists of shingles. Is there any scope associated with these shingles?
Will electrical service be available at any of the staging areas shown on Sheet G-005?
There is an electric service available at the staging area located due east of Buildings 7 and 8, and northeast of Building 12. Contractor will be responsible for coordination with electrical utility, costs associated with the setup of temporary power infrastructure (i.e., meter, temp service, etc.) and the costs of the electricity. 1
What is the scope of work at Building 83?