This document contains an amendment to a federal solicitation for repair and restoration work at Cape Hatteras Lighthouse. Key details include:
-
The solicitation number is 140P2023R0132 issued by the National Park Service for work including stair repair, fence and ramp construction, landscape restoration, and repair of the historic Fresnel lens.
-
The amendment provides revised drawings and specifications adding details for interior stair repair, clarifying allowances for common stair components, and requiring replacement of certain stair treads and clips.
-
It updates cost line items (CLINs) in the drawings and price schedule, revises the landscape and temporary fencing scope, and includes miscellaneous clarifications and additions to drawings and specifications.
-
Questions and answers are provided addressing topics such as scaffolding and shoring requirements, missing specification sections, clarification of CLINs, and requests for documents like geotechnical reports, hazardous materials surveys, and OSHA logs.
-
Evaluation criteria for the solicitation are outlined relating to scheduling, safety, and small business participation plans.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2023R0132 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
08/01/20230003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/03/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
CAHA 213068 / Repair Cape Hatteras Lighthouse, CAHA 319350 Restore or Reconstruct Historic
First Order Fresnel Lens, and CAHA 319351 Improve or Restore Historic Landscape
The purpose of this amendment 0003 is to incorporate the following:
1. Summary of changes to the drawings and specifications for Amendment 003.
2. Post Questions and Answers.
3. Attached CAHA Geotechnical Investigation Sept-1998 to support Amendment 002, question
#71.
4. Attached Revised Specifications, CAHA 2130680 319351_SPECS Amend 003.
5. Attached Revised Drawings, CAHA 213068 319351_DWGS Amend 003.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Bai Perney
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
140P2023R0132 Amendment 003
The following is a summary of changes to the drawings and specifications for Amendment 003.
ITEM NO. 1 – STAIR REPAIR SCOPE:
1.1 Additional drawings provided to more clearly describe scope of stair repair previously described on sheet S135. (sheet S135 voided; sheets S300, S301, S302, S303, S310, S311, S320 added)
1.2 Repair details for interior stair handrail have been added. (S303)
1.3 Allowances for repair and replacement of common stair components has been clarified. (S310)
1.4 Stair treads that are not stamped with a 2002 or 2008 date are called out to be replaced. (S310, S311)
1.5 Design load parameters have been updated for the stair loads. (S002)
1.6 A sample of original drawings has been added for reference only. All dimensions are to be verified in field. (S320)
1.7 Notes to refer to structural for recently added stair scope have been added. (A100, A101, A102, S100, S101, S121)
1.8 Painting of stair elements has been clarified to include both existing and new elements. (A100, A101, A102)
1.9 Revised Section 05 03 74 to include requirements for replicated interior stairway treads.
ITEM NO. 2 – UPDATED CLINS
2.1 CLIN notations in drawings have been updated to reflect Contract Price Schedule. (C1.1, C4.5, A101, A300, A301, all structural drawings)
ITEM NO. 3 – LANDSCAPE UPDATES
3.1 Timber matting area updated. (C1.2, C2.0)
3.2 Revisions to temporary wood stakes. (C4.2, C4.3, C4.4, C4.5, C4.8, C5.3, C5.4, C5.5, C5.8, C8.9)
ITEM NO. 4 – MISCELLANEOUS UPDATES
4.1 Table of Contents updated. (G001)
4.2 Floor elevation information added. (A112)
4.3 Dimension added clarifying handrail detail at ramp. (A301)
4.4 Oil House door thickness added to door schedule. (A201)
4.5 Dimension information added to louver above front entry door. (A120)
4.6 Dimension information added to metal bearing plate. Refence to “bench cap” changed to “bearing plate.” (A100, A140)
140P2023R0132 Amendment 003
4.7 Window hood may be cast in sections and welded together – removed note that this must be cast as one piece. (A129)
4.8 Erroneous references and paragraphs edited or removed from specifications. (01 27 00; 05 03 74;
07 61 00, 09 96 00)
4.9 Submittal List updated (01 33 23)
4.10 Aluminum Alloy 6061-T6 added as an acceptable option for aluminum castings. (05 03 74)
SHEETS (ADDED):
S300 S301 S302 S303 S310 S311 S320
SHEETS (MODIFIED):
G001 G005 C1.1 C1.2 C2.0 C4.2 C4.3 C4.4 C4.5 C4.8 C5.3 C5.4 C5.5 C5.8 C8.9 A100 A101 A112 A120 A129 A140 A201 A300 A301 S002 S100 S101 S102 S110 S120 S121 S122 S123
S124 S125 S126 S127 S128 S129 S130 S131 S132 S133 S20
SHEETS (REMOVED):
S135
SPECIFICATIONS (ADDED):
None
SPECIFICATIONS (MODIFIED):
01 27 00 01 33 23 05 03 74 07 61 00 09 96 00 32 31 15
Questions and Answers August 1, 2023
Question Number
Question Answer/Response
We will need to stabilize our interior and exterior scaffold/shoring/hoisting systems. I see the note in the drawings saying contractors are not to remove, alter or disfigure the existing surfaces. Would NPS be willing to consider scaffold tie back options that involve anchors being set in the existing masonry joists/walls?
See specification section 01 50 00 2.4C for delegated design requirements for scaffolding and shoring. Independently supported scaffolding and shoring systems are preferred.
Additional loading on the existing lighthouse masonry or existing metal framing shall be minimized to the extent possible. At the interior, scaffold posts that rest on existing framing shall be re-shored down to foundations. The Contractor’s shoring engineer shall provide any loads imparted on the existing structure including shop drawing details for review and approval by the Contracting Officer. Additional loads imparted on the structure may require engineering analysis to ensure no adverse impact. Per 2.4.C.4 if there is anchorage or temporary load applied to the existing structure, contractor’s engineer shall submit full analysis of the lighthouse for the loads. For any proposed attachment points (lateral bracing, masonry bearing, etc.) Contractor shall also provide workplan for removal of anchorage, repair, and restoration to the desired final appearance at the end of construction.
Contracting Officer will need to review and approve attachment locations, attachment details, and loads imparted before the construction of the scaffold beings. For attachment to the masonry, anchorage into mortar joints is preferred over anchorage into masonry units.
Section 01 22 00 – UNIT PRICES and Section 01 23 01 – OPTIONS is referenced in Section 01 27 00 Def of Contract Line Items, but they are both missing from the specbook. Please provide these missing Specification Sections.
Sections 01 22 00 and 01 23 01 are not part of the project. Disregard the reference in Section 01 27 00.
Drawing A300 (Sheet 92) is titled as CLIN 2:
Fence Details, but has a note just above the Title Block that says “Scope on this sheet is in CLIN 6 unless otherwise noted”. Please clarify which CLIN the work on dwg A300 should be part of Scope on sheet A300 is in CLIN 6
Disregard the “CLIN 2” in the title block.
Drawing A301 (Sheet 93) is titled as CLIN 5:
RAMP, but has a note just above the Title Block that says “Scope on this sheet is in CLIN 7 unless otherwise noted”. Please clarify which CLIN the Scope on sheet A301 is in CLIN 7
Disregard the “CLIN 5” in the title block.
076100-2.2.B notes that the copper should be “88oz / 1/8”thick”. Industry standard/maximum thickness for a roof panel is 20oz that is to be mechanically seamed as shown in Detail 8/A125.
a. Copper roof material should be 24-oz./sq. ft.
Disregard 88-oz
2. 076100-2.5.A.2- please clarify location and function of this item- they don’t appear to be referenced on the drawings
Disregard section 076100-2.5.A.2. Copper roof should be attached to roof deck, as detailed.
5. Detail 3/A125 references a “Tin Coated Copper Roof Liner”. Is this an item that you would want the Roofing Contactor to handle?
Is there additional photo/drawing detail of these panels in regards to profile and how they attach.
“Tin-Coated” Copper is no longer manufactured, “Zinc-Coated” Cooper is produced by Revere- the same manufacturer referenced for the copper roofing. There is also reference to “Ice & Water Shield Over Exterior Surface & Paint Both Surfaces”- clarity/intent is requested for this note
Zinc-coated copper is acceptable. Attachment is to be suspended from rafters. QE to issue details clarifying profile and attachment, as well as ice & water shield.
The specified fabricator for the fresnel has indicated that the fabrication time will be 18-24 months after approval. Would the NPS consider a delayed NTP.
No, NPS would not consider a delayed notice to proceed (NTP) for the Fresnel lens. Discussions for extention of period of performance upon request. Would consider upon request an NTP at award for submittal, review, and fabrication of the Fresnel lens.
The drawing below from sheet C4.5 is referencing CLIN numbers (there is possibly one or two other sheets that do the same).
Revised documents included
In the last round of comments, the Park requested some changes to the look of the temporary fencing, which would require a small change to one of VHB’s details and the spec
Revised documents included
S135 Treads with 20% section loss replace.
How many treads need to be inspected? What is the replacement assumption?
Sheet S135 replaced with Sheets S300, S301, S302, S303, S310, S311, S320
S135 Replace missing Tread clips, clips with 20% section loss replace. How many clips need to be inspected? What is the replacement assumption?
Sheet S135 replaced with Sheets S300, S301, S302, S303, S310, S311, S320
S135 Stringer splices with 20% section loss replace. How many stringers need to be inspected? What is the replacement assumption?
Sheet S135 replaced with Sheets S300, S301, S302, S303, S310, S311, S320
S135 Mock-up required for removal and replacement of Stair Nut, Outer Stinger Nuts, Stair Stringers at connections. Is Mock-up
IN_SITU?
Sheet S135 replaced with Sheets S300, S301, S302, S303, S310, S311, S320
75 L1.0 Can Common Bermuda Grass be used in lieu of Yukon Bermuda Grass
No substitution, use Yukon Bermuda Grass.
76 7/C8.2 Will alternative matting me allowed in lieu of Timber Matting?
No substitution, use timber matting.
C8.11 What is the existing granite finish that needs to be matched?
This will need to be determined by Contractor after award and confirmed by CMR, A/E and Park via a submittal or construction RFI.
Is NPS responsible for all costs associated with the Archeological Monitor? Or is the contractor responsible for all costs associated with the Archeological Monitor?
NPS will handle the Archeological monitoring using either Park staff or Southeast Archeological Center (SEAC).
What reasonability is required of the prime contractor or GC for site security from vandalism and theft if repeated theft and/or vandalism of the site or construction work area(s) occurs? Is the contractor required to provide 24 hour security guards for site security?
The contractor will be responsible for site security during construction including fencing and night watchmen, if required.
Will NPS Police provide security patrols to protect and guards to protect the site during non-working hours?
No, the contractor will be responsible for site security during construction including fencing and night watchmen, if required.
Section 076100 – Warranty is for five years. Is this required to be a bonded warranty? The most surety companies will bond warranties is typically 2 years.
The intent is for the installer/contractor to guarantee their work above and beyond the standard one-year warranty. The expectation is that this will be custom formed roofing due to the shape and the size of the roof area, and thus the installer shall guarantee their work.
Roof details 2&5/A125 are not possible with 88 oz copper per spec section 076100. The double lock would be 5/8" to ¾" thick. Also max possible weight of ASTM B370 copper is 32 oz, not 88 oz. .125"x36"x96" sheet copper is available in ASTM B152. There are also large minimum orders on the ASTM B152 copper if that is required. Please advise.
Refer to RFI 16.
Section 085116 – Warranty is for 10 years. Is this required to be a bonded warranty for the installer? The most surety companies will bond warranties is typically 2 years.
The intent is for the installer/contractor to guarantee their work above and beyond the standard one-year warranty. The expectation is that this will be a custom bronze window, and thus the installer shall guarantee their work.
107 What CLIN is the stone tile work on Level 1-8? CLIN 3
Due to highly specialized nature of work, please organize a second site visit to allow additional specialty contractors to view the project. This will ultimately result in more subcontractor competition and result in more value to the NPS
No more official site visits will be organized.
Please provide an extension that provides at least 2 weeks after response of all technical Q&As. This will provide the specialty subcontractors to account for all clarifying information in their proposals and reduce contingencies.
See RFI #21
Please extend the Q&A period 2-Weeks to allow specialty subcontractors who have just begun reviewing the documents additional time to submit technical questions as they review the RFP Documents.
See RFI #21
Please confirm the "Environmental Report Located in the Specifications" as noted on G002 General note 18 is referring to Attachment _4_Cape_Hatteras_Lead_Based_Paint_Report_- _R. Specifications do not include anything labeled "Environmental Report" Please confirm this is what this is referring to.
This is referring to the "Hazardous Materials Survey Report - Final" by Terracon dated March 16, 2020
Please provide any geotechnical reports and/or structural foundation as-builts to identify footing requirements and potential conflicts with the existing structure that would need to be coordinated and incorporated into the design of the scaffolding system.
For Geotechnical Report see RFI #71
Reference Drawing G005 - Project Scope Site Plan. Please confirm the full sidewalk surrounding the lighthouse is not part of the base bid. There is a section of sidewalk to the west of the lighthouse that appears to be part of
CLIN 6.
The sidewalk around the lighthouse is part of CLIN 6. The landscape scope in CLIN 1 only includes repair, reseeding, and post-construction site restoration, as defined in spec section 01 27 00.
Dimensioned Floor elevations are provided on A110-A111, but the dimensions are missing above the Lantern Match line on A112. Please provide dimensioned elevations of levels 9,10,11, tower - roof cornice, and the top of the copper ventilator & pinnacle.
Sheet A112 updated. See amended drawings.
Specification 02 82 13 states there are asbestos containing light fixture stored in the oil house.
Please clarify removing these fixtures are in the scope of work of this project, or if they will be removed by others outside of this solicitation.
Yes, this is within the scope of work of this project.
Please confirm that other than the light fixtures stores in the oil house, no other asbestos containing material has been identified.
The light fixtures in the Oil House are the only known asbestos-containing material within the Oil House and Lighthouse.
Sheet D101 General note 9 states that removal of existing primer prior to application of new coatings. Please confirm whether newly painted surfaces require complete removal of existing paints & primer prior to application of coatings
Some interior metal surfaces have been stripped of paint and re-primed. The primer that has been applied is not compatible with the proposed high-performance coating system so it must be completely removed prior to application of new coatings.
Please provide any hazardous materials reports that have been completed to determine levels of contaminants
Refer to "Hazardous Materials Survey Report - Final" by Terracon dated March 16, 2020
Section L, Factor 1b: Please provide a Notice to Proceed date for use in development of preliminary proposals.
See RFI #109
Section L, Factor 1b: Please confirm development of preliminary Gantt Chart schedule using Primavera P6 is allowable.
Yes.
136 Section L, Factor 1b: Please state the page limit for the Schedule narrative.
The scheduling narrative shall be limited to 3 pages in addition to the Gantt Chart
Section L, Factor 1b: Please confirm that the Gantt Chart schedule does not count against the page limit for the 1b Schedule narrative.
Gantt chart does not count against page limit.
Section L, Factor 3a: Please provide the referenced “Key Trades form required to be submitted with the proposal”.
Key Trades is in SPECIAL REQUIREMENT 2:
KEY PERSONNEL on page 14 of 62
139 Section L, Factor 4b: Please state the page limit for the Safety narrative.
The page limit for the Safety narrative is three pages.
Section L, Factor 4b: The Section M evaluation criteria states “Fewer documented OSHA 300A incidents and lower EMR rates will be more favorably rated” but the Section L instructions do not state to provide OSHA 300A logs or EMR rates. Please clarify if the NPS intends to review OSHA 300A logs for the previous three calendar years along with a statement from our insurance company showing our current EMR rate.
Section L, Factor 4b is revised to: Submit an overview of your company’s Construction Safety Program and an assessment of the safety risks associated with this construction project.
Include OSHA 300A logs and EMR rates.
Section L, Factor 4b: Please confirm that, if required, the OSHA 300A logs and EMR rate statement from insurance company do not count against the page limit for the Safety narrative.
OSHA 300A logs and EMR rate statement from insurance company do not count against the page limit.
Section L, Volume II Business and Price Proposal: The NPS typically requires submission of a SB Participation Plan in Volume I Technical and a SB Subcontracting Plan in Volume II Business and Price Proposal.
Please confirm the NPS only requires submission a SB Subcontracting Plan for Cape Hatteras.
Section L, Volume II Business and Price Proposal: NPS only requires submission a Small Business Subcontracting Plan for this solicitation.
Section L, Volume I Technical Proposal: The NPS has not included a SB Participation Plan template with the solicitation documents, please provide if required in the technical volume.
SB Participation Plan template is Attachment 10 Small Business Subcontracting Plan posted with the solicitation.