Amendment_6_06_82_00_-_FIBERGLASS_REIN_PLASTIC_FABS_Rev_2022-08-25_06.pdf

PDF 141 KB Posted

Attached to
GRCA 190083 - Improve Potable Water Supply to Inne
Solicitation number
140P2022R0100
Issued by

About this file

This document is a technical specification for fiberglass reinforced plastic fabrications required for a federal construction project to replace a transcanyon waterline and improve potable water systems at Grand Canyon National Park. Key details include specifications for fiberglass reinforced plastic grating, structural members, baffle walls, and supporting structure to be designed by a registered structural engineer. Materials must be fiberglass reinforced vinyl ester resin with fire retardant properties and manufacturer-applied abrasive grit surfacing. Submittals require shop drawings, product data, samples, design calculations and manufacturer certifications. Installation must follow manufacturer instructions and meet tolerances for location, alignment, plumb and level.

View the file

Other files

File Type Posted
Amendment_8_40_91_10_Primary_Meters_and_Transmitters_(IG_Phase_3)_08.pdf PDF
Amendment_8_Questions_and_Answers_9-8-22_08.docx DOCX document
Amendment_8_SF_30_9-8-22_08.pdf PDF
Sol_140P2022R0100_Amd_08.pdf PDF
Amendment_7_Questions_and_Answers_9-2-22_07.docx DOCX document
Sol_140P2022R0100_Amd_07.pdf PDF
Amendment_7_SF_30_9-2-22_07.pdf PDF
Amendment_6_Wage_Determination_AZ20220007_Heavy_06.pdf PDF
Sol_140P2022R0100_Amd_06.pdf PDF
Amendment_6_Questions_and_Answers_8-26-22_06.docx DOCX document
Amendment_6_Wage_Determination_AZ20220016_Heavy_06.pdf PDF
Amendment_6_43_23_04_Horizontal_Multistage_Pumps_GRCA_261633_Pump_3_06.pdf PDF
Amendment_6_Wage_Determination_AZ20220030_Building_06.pdf PDF
Amendment_6_SF_30_8-26-22_06.pdf PDF
Amendment_5_Questions_and_Answers_8-19-22_05.docx DOCX document
Sol_140P2022R0100_Amd_05.pdf PDF
Amendment_5_SF_30_8-19-22_05.pdf PDF
Amendment_4_SF_30_8-12-22_04.pdf PDF
Sol_140P2022R0100_Amd_04.pdf PDF
Amendment_4_Att12b_CSF_Drawings_Rev_8-12-22_04.pdf PDF
Amendment_4_Questions_and_Answers_8-12-22_04.docx DOCX document
Amendment_3_03-E504_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-C405_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-E503_REV1_2022-08-02_03.pdf PDF
Sol_140P2022R0100_Amd_03.pdf PDF
Amendment_3_SF_30_8-5-22_03.pdf PDF
Amendment_3_Questions_and_Answers_8-5-22_03.docx DOCX document
Amendment_3_03-C137_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-C131_REV1_2022-08-22_03.pdf PDF
Amendment_2_Questions_and_Answers_7-29-22_02.docx DOCX document
Sol_140P2022R0100_Amd_02.pdf PDF
Amendment_2_SF_30_7-29-22_02.pdf PDF
Sol_140P2022R0100_Amd_01.pdf PDF
Amendment_1_01-E601_REV_1_7-22-22_01.pdf PDF
Amendment_1_01-E104_REV_1_7-22-22_01.pdf PDF
Amendment_1_Questions_and_Answers_7-22-22_01.docx DOCX document
Amendment_1_SF_30_7-22-22_01.pdf PDF
Amendment_1_01-E100_REV1_7-22-22_01.pdf PDF
Amendment_1_01-E631_REV_1_7-22-22_01.pdf PDF
Att4b_GRCA 190083 Basis of Design Report_Appendices only.pdf PDF
Att1f_GRCA 190083 Vol 04_Drawings_Pg 497to698_4-22-22.pdf PDF
Att7d_TransCanyon Waterline Drone Footage - End Plateau.mp4 MP4 file
Att6f_Innercanyon_Single-Phase_Transformer_Short_Circuit.pdf PDF
Att7e_Phantom_Rnch_Headworks_Excav_Photos.pdf PDF
Att1i_Revised_Drawings_1_7-5-22.pdf PDF
Att6i_GRCA_190083_Geotech_Field_Work_Photo_Album_4-17-18.pdf PDF
Att7b_TransCanyon_Waterline_Drone_Footage.mp4 MP4 file
Att2a_GRCA_190083_Final_CD_Specifications_Vol_1_Division_1.pdf PDF
Att6c_Suez_Proposal_for_GRCA_190083_MF-UF_Equip_9-2-20.pdf PDF
Att5b_Addendum_to_the_Geotechnical_Investigation_Report_12-23-20.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10301936 National Park Service GRCA 190083 - TCWL Replacement Package B&C - 100% Final CDs

FIBERGLASS REINFORCED PLASTIC FABRICATIONS

06 82 00 - 1

SECTION 06 82 00 1

FIBERGLASS REINFORCED PLASTIC FABRICATIONS 2

PART 1 - GENERAL 3

1.1 SUMMARY 4

A. Section Includes: 5

1. Fiberglass reinforced plastic (FRP) fabrications including but not limited to: 6

a. Grating. 7

b. Structural members. 8

c. Supporting structure design. 9 c.d. Baffle walls and components. 10

1.2 QUALITY ASSURANCE 11

A. Referenced Standards: 12

1. ASTM International (ASTM): 13

a. E84, Standard Test Method for Surface Burning Characteristics of Building Materials. 14

2. Occupational Safety and Health Administration (OSHA): 15

a. 29 CFR 1910, Occupational Safety and Health Standards, referred to herein as OSHA 16 Standards. 17

B. Qualifications: 18 a.1. All fiberglass reinforced plastic support systems shall be designed and sealed by a registered 19 professional structural engineer licensed in the State of Arizona. 20

1.3 DEFINITIONS 21

A. Skid-resistant: 22

1. Manufacturer's standard applied abrasive grit coating. 23

2. Abrasive coated tape is not acceptable. 24

B. FRP: Fiberglass Reinforced Plastic. 25

1.4 SUBMITTALS 26

A. Shop Drawings: 27

1. Product technical data including: 28

a. Acknowledgement that products submitted meet requirements of standards referenced. 29

b. Manufacturer's installation instructions. 30

c. Manufacturer's recommendations on reinforcing field cut openings. 31

2. Fabrication and/or layout drawings. 32

a. Plan showing profile, location, section and details of each item including anchorage or 33 support system(s). 34

b. Locations and type of expansion joints. 35

c. Materials of construction including shop applied coatings. 36

d. Listing of all accessory items being provided indicating material, finish, etc. 37

3. Certifications: 38

a. Certification of Structural Engineer's qualifications. 39

b. Certification that all components and systems have been designed and fabricated to 40 meet the loading requirements specified. 41

4. Manufacturer's full line of colors available for each component. 42

B. Informational Submittals: 43

1. Complete design calculations of all supporting structure and fastening conditions. Design 44 calculations shall be sealed by a Professional Engineer licensed in the State of Arizona. 45

a. Design calculations to be for information only. 46

b. Contracting Officer will not review or take any action on submittal. 47

FIBERGLASS REINFORCED PLASTIC FABRICATIONS

06 82 00 - 2

1.5 DELIVERY, STORAGE, AND HANDLING 1

A. Deliver and handle each item to preclude damage. 2

B. Store all items on skids above ground. 3

1. Keep free of dirt and other foreign matter which will damage items or finish and protect 4 from corrosion and UV exposure. 5

PART 2 - PRODUCTS 6

2.1 MANUFACTURERS 7

A. Subject to compliance with the Contract Documents, the following manufacturers are 8 acceptable: 9

1. Grating and solid plate: 10

a. American Grating. 11

b. Enduro Composites. 12

c. Fibergrate Composite Structures, Inc. 13

d. Harsco Industrial IKG. 14

e. International Grating Inc. 15

f. Mona Composites. 16

g. Seasafe, Inc. 17

h. Strongwell Corporation. 18

i. Or Approved Equal. 19

2. Baffle Walls: 20

a. Enduro composite Systems. 21

b. Fibergrate Composite Structures, Inc. 22 i.c. Strongwell. 23

2.2 MATERIALS 24

A. Fiberglass Reinforced Plastic (FRP): 25

1. Vinyl ester with fiberglass reinforcing. 26

a. Type V. 27

2. Fire retardant. 28

a. Flame spread: ASTM E84, 25 or less. 29

3. Color: To be selected by Contracting Officer when more than one color is available for any 30 one component. 31

B. Fasteners, Clips, Saddles, and Miscellaneous Components: 32

1. Fiberglass where possible. 33

2. Stainless steel may be used if fiberglass component is not available. 34

C. Skid-resistant Surfacing: Manufacturer-applied abrasive grit coating. 35

D. Baffle walls: 36

1. Design criteria: 37

a. Water differential: 8 IN uniform over entire wall 38

b. Minimum lateral load on wall: 5 PSF, nonconcurrent with water differential. 39

c. Maximum lateral deflection of 1/180 of span under lateral loads. 40

d. Maximum vertical deflection of 1/360 of span under gravity loads. 41

e. Design for the most severe loading condition noted above. 42

2. Panels weakened by penetrations, cuts, etc. shall be stiffened or reinforced as necessary to 43 withstand the specified loading and deflection limits. 44

3. Exposed surfaces shall be smooth and free of burs and jagged edges. 45 C.4. Provide accessory items including angles, bolts, and anchorage necessary for installation of 46 the baffle walls per manufacturer’s recommendations. 47

FIBERGLASS REINFORCED PLASTIC FABRICATIONS

06 82 00 - 3

2.3 FABRICATION 1

A. General: 2

1. Verify field conditions and dimensions prior to fabrication. 3

2. Preassemble items in shop to greatest extent possible. 4

3. All components shall be treated with UV inhibitor. 5

4. Drill or punch holes with smooth edges. 6

B. Grating and Solid Plate Material: 7

1. See Drawings for locations where FRP grating is required. 8

2. Design live load: 9

a. 100 PSF uniform live load. 10

b. 300 LBS concentrated load. 11

c. Maximum deflection of l/300 of span under a superimposed live load. 12

d. Design for the most severe loading condition noted above. 13

3. Minimum grating depth: 1-1/2 IN. 14

4. Bar span: Maximum of 1-1/2 IN center to center. 15

5. Walking surface: Manufacturer's standard applied abrasive grit coating. 16

C. Embedded Grating Supports: 17

1. Fiberglass. 18

2. Size to suit depth of grating. 19

3. Provide leg or strap for embedding and anchoring into concrete. 20

4. Similar to Strongwell "Duradek Fiberglass Curb Angle." 21

PART 3 - EXECUTION 22

3.1 INSTALLATION 23

A. Install products in accordance with manufacturer's instructions. 24

B. Set work accurately in location, alignment and elevation, plumb, level, and true. 25

1. Measure from established lines and levels. 26

2. Provide temporary bracing or anchors in formwork for items which are to be built into 27 concrete, masonry or similar construction. 28

3. Tolerances: 29

a. Maximum variation from plumb in vertical line: 1/8 IN in 3 FT. 30

b. Maximum variation from level of horizontal line: 1/4 IN in 20 FT. 31

c. Maximum variation from plan location: 1/4 IN in 20 FT. 32

C. Coat all exposed surfaces of stainless steel fasteners with minimum 15 MIL gel coating to match 33 component being anchored. 34

D. Attach grating to each end and intermediate support clip or saddle with bolts, nuts and washers. 35

1. Maximum spacing: 2 FT OC with minimum of two per side. 36

2. Attach clips or saddles to bearing bars only. 37

3. Reinforce all field cut openings in accordance with manufacturer's recommendations. 38

E. Seal cut ends of all items with catalyzed resin as recommended by manufacturer. 39

1. Provide same resin used in fabrication of item as a minimum. 40

END OF SECTION 42