This document contains questions and answers pertaining to solicitation number 140P2022R0100 for a project to replace the transcanyon waterline and improve potable water systems at Grand Canyon National Park. The National Park Service seeks to improve the potable water supply through replacing the existing transcanyon pipeline and upgrading pumping stations at Roaring Springs and Indian Gardens. While comprehensive as-built drawings of the existing system do not exist, the solicitation documents provide the most current information available. Material substitutions must be approved by the eventual contract awardee after award and submitted to the National Park Service. A pre-solicitation attendees list issued on June 21st includes contractors who expressed interest in the project.

View the file

Other files

File Type Posted
Amendment_8_40_91_10_Primary_Meters_and_Transmitters_(IG_Phase_3)_08.pdf PDF
Amendment_8_Questions_and_Answers_9-8-22_08.docx DOCX document
Amendment_8_SF_30_9-8-22_08.pdf PDF
Sol_140P2022R0100_Amd_08.pdf PDF
Amendment_7_Questions_and_Answers_9-2-22_07.docx DOCX document
Sol_140P2022R0100_Amd_07.pdf PDF
Amendment_7_SF_30_9-2-22_07.pdf PDF
Amendment_6_Wage_Determination_AZ20220007_Heavy_06.pdf PDF
Sol_140P2022R0100_Amd_06.pdf PDF
Amendment_6_Questions_and_Answers_8-26-22_06.docx DOCX document
Amendment_6_06_82_00_-_FIBERGLASS_REIN_PLASTIC_FABS_Rev_2022-08-25_06.pdf PDF
Amendment_6_Wage_Determination_AZ20220016_Heavy_06.pdf PDF
Amendment_6_43_23_04_Horizontal_Multistage_Pumps_GRCA_261633_Pump_3_06.pdf PDF
Amendment_6_Wage_Determination_AZ20220030_Building_06.pdf PDF
Amendment_6_SF_30_8-26-22_06.pdf PDF
Amendment_5_Questions_and_Answers_8-19-22_05.docx DOCX document
Sol_140P2022R0100_Amd_05.pdf PDF
Amendment_5_SF_30_8-19-22_05.pdf PDF
Amendment_4_SF_30_8-12-22_04.pdf PDF
Sol_140P2022R0100_Amd_04.pdf PDF
Amendment_4_Att12b_CSF_Drawings_Rev_8-12-22_04.pdf PDF
Amendment_4_Questions_and_Answers_8-12-22_04.docx DOCX document
Amendment_3_03-E504_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-C405_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-E503_REV1_2022-08-02_03.pdf PDF
Sol_140P2022R0100_Amd_03.pdf PDF
Amendment_3_SF_30_8-5-22_03.pdf PDF
Amendment_3_Questions_and_Answers_8-5-22_03.docx DOCX document
Amendment_3_03-C137_REV1_2022-08-02_03.pdf PDF
Amendment_3_03-C131_REV1_2022-08-22_03.pdf PDF
Amendment_2_Questions_and_Answers_7-29-22_02.docx DOCX document
Sol_140P2022R0100_Amd_02.pdf PDF
Amendment_2_SF_30_7-29-22_02.pdf PDF
Sol_140P2022R0100_Amd_01.pdf PDF
Amendment_1_01-E601_REV_1_7-22-22_01.pdf PDF
Amendment_1_01-E104_REV_1_7-22-22_01.pdf PDF
Amendment_1_SF_30_7-22-22_01.pdf PDF
Amendment_1_01-E100_REV1_7-22-22_01.pdf PDF
Amendment_1_01-E631_REV_1_7-22-22_01.pdf PDF
Att4b_GRCA 190083 Basis of Design Report_Appendices only.pdf PDF
Att1f_GRCA 190083 Vol 04_Drawings_Pg 497to698_4-22-22.pdf PDF
Att7d_TransCanyon Waterline Drone Footage - End Plateau.mp4 MP4 file
Att6f_Innercanyon_Single-Phase_Transformer_Short_Circuit.pdf PDF
Att7e_Phantom_Rnch_Headworks_Excav_Photos.pdf PDF
Att1i_Revised_Drawings_1_7-5-22.pdf PDF
Att6i_GRCA_190083_Geotech_Field_Work_Photo_Album_4-17-18.pdf PDF
Att7b_TransCanyon_Waterline_Drone_Footage.mp4 MP4 file
Att2a_GRCA_190083_Final_CD_Specifications_Vol_1_Division_1.pdf PDF
Att6c_Suez_Proposal_for_GRCA_190083_MF-UF_Equip_9-2-20.pdf PDF
Att5b_Addendum_to_the_Geotechnical_Investigation_Report_12-23-20.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRCA 190083

Replace Transcanyon Waterline and Improve Potable Water Systems Grand Canyon National Park

Solicitation 140P2022R0100 – Questions and Answers

Amendment 1, issued 7/22/22:

1. Question: Can you post the as‐built drawings for the existing transcanyon pipeline and pumping stations at roaring springs and Indian Gardens?

Answer: No set of comprehensive as-builts exist. The solicitation documents are the most current basis of existing system information available.

2. Question: Is AIR-SHIELD LMP an acceptable approved equal material?

Answer: The prime contractor will make all material submittals to the NPS for approval after award. Any substitution requests should be submitted to the eventual awardee of this contract.

3. Question: Do you have a list of contractors who are looking at this project?

Answer: The Presolicitation Attendees list was issued with a Special Notice on sam.gov under this solicitation number on June 21, 2022.