Attachment_6_Statement_of_Structural_Tests_and_Special_Inspections.pdf
PDF 549 KB Posted
- Attached to
- Replace Primary Potable Water Pumps 1&2 Which Provides Water to the South Rim - Indian Garden
- Solicitation number
- 140P2018R0105
About this file
Attachment 6_Statement of Structural Tests and Special Inspections
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GRCA 182403 Statement of Structural Tests and Special Inspections Page 1 of 5
Statement of Structural Tests and Special Inspections Denver Service Center National Park Service
Park: Grand Canyon National Park
PMIS: 182403
Project Name: Indian Gardens Pump Station
Structural Engineering Firm: HDR, Inc.
This Statement of Structural Tests and Special Inspections (STSI) is being submitted as required by Chapter 17 of the 2015 International Building Code (IBC-15). It includes the following:
1. Qualification requirements for Inspectors and Testing Technicians
2. Listing of Required Structural Tests and Special Inspections
The Construction Contractor’s Quality Control Supervisor will provide copies of all special inspection reports and associated documentation to the Contracting Officer. The Construction Contractor will be required to correct all deficiencies discovered in the Special Inspection and Structural Testing program.
Prepared by:
Tom Hamlin, PE, SE______________________________ (Type or print name)
Signature Date PE or SE Stamp
GRCA 182403 Statement of Structural Tests and Special Inspections Page 2 of 4
Qualification Requirements for Inspectors and Testing Technicians
PE/SE Structural Engineer – licensed PE or SE specializing in the design of buildings and structures
PE/GE Geotechnical Engineer – licensed PE specializing in soil mechanics and foundations
EIT Engineer-In-Training – graduate engineer who has passed the Fundamentals of engineering examination
OtherAppr A person deemed qualified and approved in advance of the inspection by both the
Owner and Engineer.
American Concrete Institute (ACI) Certification
ACI-CCSI Concrete Construction Special Inspector
ACI-LTT Concrete Laboratory Testing Technician Level 1 or 2
ACI-STT Concrete Strength Testing Technician
ACI-FTT Concrete Field Testing Technician – Grade I
International Code Council (ICC) Certification
ICC-RCSI Reinforced Concrete Special Inspector
ICC-SSI Soils Special Inspector
ICC-SMSI Structural Masonry Special Inspector
ICC-SSBSI Structural Steel and Bolting Special Inspector
ICC-SWSI Structural Welding Special Inspector
National Institute for Certification in Engineering Technologies (NICET) Certification
NICET-CT Concrete Technician – Levels I, II, III and IV
NICET-GET Geotechnical Engineering Technician - Levels I, II, III and IV
NICET-ST Soils Technician - Levels I, II, III and IV
Note: where multiple qualifications are listed for an inspection, the person inspecting need only meet one of the qualifications listed.
GRCA 182403 Statement of Structural Tests and Special Inspections Page 3 of 4
Listing of Required Structural Tests and Special Inspections
R eq u ir ed
Structural Test or Special Inspection
Required
Qualifications
(at least one where multiple listed)
C o n ti n u o u s
P er io d ic
F re q u en cy o f
P er io
T es t o r
In sp ec ti n
Concrete Construction (ref: IBC-15 Table 1705.3) X 1. Inspection of reinforcing steel. Acceptable methods include onsite inspection or photographs provided to
Inspector/Testing Technicians, PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Prior to each concrete placement
X 2. Inspection of bolts to be installed in concrete prior to and during placement of concrete.
PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Prior to each concrete placement
X 3. Inspection of anchors installed in hardened concrete for conformance to manufacturer’s requirements.
PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Inspect 25% of anchors installed in hardened concrete
R eq u ir ed
Structural Test or Special Inspection
Required
Qualifications
(at least one where multiple listed)
C o n ti n u o u s
P er io
F re q u en cy f
P er io
T es t o r
In sp ec ti n
X 4. Verify use of approved prepackaged concrete materials. PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Prior to concrete placement
X 5. Verify that prepackaged concrete products have been mixed and placed according to manufacturer’s instructions and requirements of Contract Documents.
PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
GRCA 182403 Statement of Structural Tests and Special Inspections Page 4 of 4
X 6. At the time fresh concrete is sampled to fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete.
PE/SE
ACI-FTT
ICC-RCSI
NICET-CT
OtherAppr
X
Minimum once per placement, or once per each 40
CY placed
X 7. Inspection formwork for shape, location and dimensions of the concrete member being formed.
PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Prior to each placement
X 8. Inspection for maintenance of specified curing temperature and techniques.
PE/SE
ACI-CCSI
ICC-RCSI
NICET-CT
OtherAppr
X
Once after concrete is placed
Soils (ref: IBC-15 Table 1705.6)
X 1. Prior to placement of controlled fill, observe subgrade and verify that site has been prepared properly.
PE/GE
NICET-ST
OtherAppr
X
Prior to placement of slabs over subgrade
File details come from the government source that posted it.