This file is a Price Schedule for Solicitation 140L0625R0007, a design-build project for the Cahuilla Ranger Station Replacement issued by the Department of the Interior Bureau of Land Management National Office. The comprehensive price schedule outlines 16 base construction categories including mobilization, earthwork, utilities, concrete, masonry, metals, finishes, and electrical, with each line item currently showing zero dollar values. The schedule also includes two optional line items: Residential Living Quarters (Modular) and Decorative Landscaping, along with corresponding design and architectural/engineering (A&E) services for both the base and optional components.
The price schedule is structured to capture the full scope of the ranger station replacement project, with line items broken down into distinct construction and design phases. While no specific pricing is currently populated in the document, the detailed breakdown suggests a comprehensive approach to project costing that allows for granular tracking of expenses across multiple project elements. The solicitation appears to be seeking a design-build contractor capable of handling a complete ranger station facility replacement, with flexibility for additional living quarters and landscaping options.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| PRICE SCHEDULE | |||||
| 140L0625R0007 | CA, D-B GAOA Cahuilla Ranger Station Replacement | |||||
| Item | Description | Unit | Quantity | Unit Price | Total |
| 1 | Mobilization | LS | $ - 0 | ||
| 2 | Existing Conditions | LS | $ - 0 | ||
| 3 | Earthwork | LS | $ - 0 | ||
| 4 | Utilities | LS | $ - 0 | ||
| 5 | Concrete | LS | $ - 0 | ||
| 6 | Masonry | LS | $ - 0 | ||
| 7 | Metals | LS | $ - 0 | ||
| 8 | Paint, Cabinets and Countertops | LS | $ - 0 | ||
| 9 | Thermal and Moisture Control | LS | $ - 0 | ||
| 10 | Doors and Windows | LS | $ - 0 | ||
| 11 | Finishes | LS | $ - 0 | ||
| 12 | Fire Supression | LS | $ - 0 | ||
| 13 | Plumbing | LS | $ - 0 | ||
| 14 | HVAC | LS | $ - 0 | ||
| 15 | Electrical | LS | $ - 0 | ||
| 16 | Bonds, Overhead, Profit | LS | $ - 0 | ||
| Construction Base Total: | $ - 0 |
| 17 | Option 1 - Residential Living Quarters (Modular) | LS | |
| 18 | Option 2 - Decorative Landscaping | LS | |
| Construction Option Total: | $ - 0 |
| 19 | Design/A&E Services (Base) | LS | |
| A&E Base Total: | $ - 0 |
| 20 | Design/A&E Services (Option 1) | LS | |
| 21 | Design/A&E Services (Option 2) | LS | |
| A&E Option Total: | $ - 0 |
TOTAL $ - 0