This is a specification section (Section 10 75 16) for ground-set flagpoles required for the Montezuma National Wildlife Refuge & New York Ecological Services New Multipurpose Facility project (Beardsley No. 23052).
The specification requires cone-tapered aluminum flagpoles fabricated from seamless extruded tubing complying with ASTM B 241/B 241M, Alloy 6063, with a minimum wall thickness of 3/16 inch and an exposed height of 30 feet. Acceptable manufacturers include American Flagpole (a Kearney National Inc. Company), Concord Industries Inc., Ewing Flagpoles, or an approved equal. Flagpoles must be obtained as complete units from a single manufacturer and include all fittings, accessories, bases, and anchorage devices. The flagpoles must withstand wind loads determined according to NAAMM FP 1001 with a basic wind speed of 90 mph. Flagpoles should be constructed in one piece if possible; if multiple pieces are necessary, they must use flush hairline joints with self-aligning internal sleeves without fasteners or screw collars. The specification includes requirements for a metal foundation tube with corrugated steel construction, fiberglass or PVC pipe foundation sleeves, finial balls with gold anodic finish, and an internal halyard winch system with manually operated controls and stainless-steel cable. Installation requirements specify preparation of foundations through cast-in-place concrete work, placement of the flagpole in the foundation tube with steel centering wedges, compaction with sand, and sealing with elastomeric joint sealant and flashing collar. Submittals must include product data, shop drawings with construction details and foundation system plans, and operation and maintenance documentation. Flagpoles must be spiral-wrapped with heavy paper and enclosed in protective containers for delivery.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Montezuma NWR & NY Ecological Services Beardsley No. 23052 New Multipurpose Facility
GROUND-SET FLAGPOLES 10 75 16 - 1
SECTION 10 75 16
GROUND-SET FLAGPOLES
PART 1 - GENERAL
1.1 SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and profiles, operating characteristics, fittings, accessories, and finishes for flagpoles.
B. Shop Drawings: For flagpoles.
1. Include plans, elevations, and attachment details. Show general arrangement, jointing, fittings, accessories, grounding, anchoring, and support.
2. Include section, and details of foundation system.
1.2 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For flagpoles to include in operation and maintenance manuals.
1.3 DELIVERY, STORAGE, AND HANDLING
A. Spiral wrap flagpoles with heavy paper and enclose in a hard fiber tube or other protective container.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain flagpoles as complete units, including fittings, accessories, bases, and anchorage devices, from single source from single manufacturer.
2.2 PERFORMANCE REQUIREMENTS
A. Structural Performance: Flagpole assemblies, including anchorages and supports, shall withstand design loads indicated within limits and under conditions indicated.
1. Wind Loads: Determine according to NAAMM FP 1001. Basic wind speed for Project location is 90 mph.
GROUND-SET FLAGPOLES 10 75 16 - 2
2.3 ALUMINUM FLAGPOLES
A. Aluminum Flagpoles: Cone-tapered flagpoles fabricated from seamless extruded tubing complying with ASTM B 241/B 241M, Alloy 6063, with a minimum wall thickness of 3/16 inch.
1. Products: Subject to compliance with requirements, provide one of the following:
a. American Flagpole; a Kearney National Inc. Company.
b. Concord Industries, Inc;.
c. Ewing Flagpoles.
d. Approved equal.
B. Exposed Height: 30 feet.
C. Construct flagpoles in one piece if possible. If more than one piece is necessary, comply with the following:
1. Fabricate shop and field joints without using fasteners, screw collars, or lead calking.
2. Provide flush hairline joints using self-aligning, snug-fitting, internal sleeves.
D. Metal Foundation Tube: Manufacturer's standard corrugated-steel foundation tube, 0.060-inch wall thickness with 3/16-inch steel bottom plate and support plate; 3/4-inch-diameter, steel ground spike; and steel centering wedges welded together. Galvanize foundation tube after assembly. Furnish loose hardwood wedges at top of foundation tube for plumbing pole.
1. Flashing Collar: Same material and finish as flagpole.
E. Sleeve for Aluminum Flagpole: Fiberglass or PVC pipe foundation sleeve, made to fit flagpole, for casting into concrete foundation.
1. Flashing Collar: Same material and finish as flagpole.
2.4 FITTINGS
A. Finial Ball: Flush-seam ball, sized as indicated or, if not indicated, to match flagpole-butt diameter.
1. 0.063-inch spun aluminum, finished to match flagpole with gold anodic finish.
B. Internal Halyard, Winch System: Manually operated winch with control stop device and removable handle, stainless-steel cable halyard, and concealed revolving truck assembly with plastic-coated counterweight and sling. Furnish flush access door secured with cylinder lock.
Finish truck assembly to match flagpole.
1. Halyard Flag Snaps: Bronze swivel snap hooks with neoprene or vinyl covers. Furnish two per halyard.
2.5 MISCELLANEOUS MATERIALS
A. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107/C 1107M.
http://www.specagent.com/Lookup?ulid=9054 http://www.specagent.com/Lookup?uid=123456894326 http://www.specagent.com/Lookup?uid=123456894328
GROUND-SET FLAGPOLES 10 75 16 - 3
B. Drainage Material: Crushed stone, or crushed or uncrushed gravel; coarse aggregate.
C. Sand: ASTM C 33/C 33M, fine aggregate.
D. Elastomeric Joint Sealant: Single-component neutral-curing silicone joint sealant.
E. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.
2.6 ALUMINUM FINISHES
A. Natural Satin Finish: AA-M32, fine, directional, medium satin polish; buff complying with AA- M20; seal aluminum surfaces with clear, hard-coat wax.
PART 3 - EXECUTION
3.1 PREPARATION
A. Prepare uncoated metal flagpoles that are set in foundation tubes by painting below-grade portions with a heavy coat of bituminous paint.
B. Foundation Excavation: Excavate to neat clean lines in undisturbed soil. Remove loose soil and foreign matter from excavation and moisten earth before placing concrete. Place and compact drainage material at excavation bottom.
C. Provide forms where required due to unstable soil conditions and for perimeter of flagpole base at grade. Secure and brace forms to prevent displacement during concreting.
D. Foundation Tube: Place foundation tube, center, and brace to prevent displacement during concreting. Place concrete. Plumb and level foundation tube and allow concrete to cure.
E. Sleeves: Locate and secure sleeves in forms by bracing to reinforcement and forms.
F. Anchor Bolts: Locate and secure anchor bolts in forms with templates and by tying to reinforcement.
G. Place concrete, as specified in Section 03 30 00 "Cast-in-Place Concrete." Compact concrete in place by using vibrators. Moist-cure exposed concrete for no fewer than seven days or use nonstaining curing compound.
H. Trowel exposed concrete surfaces to a smooth, dense finish, free of trowel marks, and uniform in texture and appearance. Provide positive slope for water runoff to perimeter of concrete base.
3.2 FLAGPOLE INSTALLATION
A. General: Install flagpoles where indicated and according to Shop Drawings and manufacturer's written instructions.
GROUND-SET FLAGPOLES 10 75 16 - 4
B. Foundation Tube: Place flagpole in tube, seated on bottom plate between steel centering wedges, and install hardwood wedges to secure flagpole in place. Place and compact sand in foundation tube and remove hardwood wedges. Seal top of foundation tube with a 2-inch layer of elastomeric joint sealant and cover with flashing collar.
END OF SECTION