This document outlines requirements for a federal construction contract opportunity with the U.S. Fish and Wildlife Service. The contract involves construction of Phase 1 of a new fish sucker fish hatchery located in Klamath Falls, Oregon, with a project magnitude between $4-6 million. Key requirements include excavation and construction of an influent retention pond, up to ten earthen aquaculture ponds, over 2,000 feet of access roads, a 2,990 foot geothermal supply pipeline, and a 1,035 foot pond drain pipeline. There are also options to construct a pre-engineered metal building, additional aquaculture ponds, and catch basin structures. The solicitation number is 140F0322B0001 and responses are due in mid-February 2022 on SAM.gov. The contract type is firm-fixed-price and the NAICS code is 236210. The opportunity is set aside for small businesses with a size standard of $39.5 million or less annually averaged over three years.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 01 57 13 – EROSION AND SEDIMENTATION CONTROL
Klamath Falls N.F.H. 01 57 13 - 1 New National Fish Hatchery
PART 1 - GENERAL
1.01 WORK DESCRIPTION
A. The Work shall consist of planning, installing, inspecting, maintaining and removing Temporary Erosion and Sediment Control (TESC) Best Management Practices (BMPs) to prevent pollution of air and water; and to control, respond to, and dispose of eroded sediment and turbid water during the term of the Contract.
B. These TESC requirements shall apply to all areas associated with the Work, including but not limited to the following:
1. Work areas
2. Adjacent Wetlands
3. Equipment and material storage areas
4. Staging areas
5. Stockpiles
6. Discharge points within or adjacent to the work areas that are impacted by stormwater runoff from the site.
C. Acceptance of TESC plans does not constitute an approval of permanent Work or drainage design (e.g., size and location of roads, pipes, restrictors, channels, retention facilities, utilities, etc.).
D. Contractor shall read and conform to all requirements set forth in Oregon Department of Environmental Quality (DEQ) 1200-C NPDES Stormwater Discharge Permit.
1.02 REFERENCES
A. The rules, requirements, and regulations that apply to this Work include, but are not necessarily limited to the following:
1. Central Oregon Intergovernmental Council Central Oregon Stormwater Manual, 2010.
2. Oregon DEQ NPDES 1200-C Permit.
3. Oregon Department of Transportation 2018 Standard Specification for Construction, Section 00290 Environmental Protection and 03020 Erosion Materials
1.03 SUBMITTALS
A. An Erosion and Sediment Control plan (ESCP), as required by NPDES permit.
Klamath Falls N.F.H. 01 57 13 - 2
1. Contractor shall be responsible for preparing and submitting an ESCP to proper authority for approval prior to mobilizing to the site.
2. Contractor shall be responsible for updating the project ESCP during construction to reflect the required changes to BMPs, as needed, to comply with the 1200-C permit at no additional cost to the Owner.
B. Safety Data Sheet (SDS) for any dust palliative product.
C. A copy of all Contractor visual monitoring records.
D. Water Management Plan/Temporary Dewatering Plan.
1.04 AUTHORITY OF ENGINEER
A. The Engineer has the authority to limit the surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations, as determined by analysis of project conditions; and to direct the Contractor to provide immediate permanent or temporary pollution control measures to minimize impacts to adjacent streams or other watercourses, wetlands, lakes, ponds, and other areas of water impoundment.
B. In the event that areas adjacent to the work area are suffering degradation due to erosion, sediment deposit, water flows, or other causes, the Engineer may stop construction activities until the Contractor rectifies the situation.
PART 2 - PRODUCTS
2.01 DUST CONTROL
A. Dust palliative for dust control proposed by the Contractor and approved by the Engineer.
PART 3 - EXECUTION
3.01 GENERAL
A. The Owner has obtained the Klamath County Commercial-Industrial Site Plan Review and Approval which covers stormwater compliance requirements. The permit shall be transferred to the Contractor prior to ground disturbing activities.
The Contractor shall be the responsible Operator/Permittee for the duration of the project.
B. In the event of conflict between these requirements and pollution control laws, rules, or regulations of other federal, state, or local agencies, the more restrictive laws, rules, or regulations shall apply as determined by the Engineer.
C. No project discharge of water shall be allowed that exceeds the regulated pollutant levels within the Oregon DEQ 1200-C Permit Approval.
Klamath Falls N.F.H. 01 57 13 - 3
D. Contractor shall be solely responsible for all BMP modifications and upgrades to comply with the 1200-C permit and the requirements of this Section, at no additional cost to the Owner.
E. Contractor shall be solely responsible for any damages and fines incurred because of Contractor, subcontractor, or supplier actions in implementing the requirements of this Section.
F. The Contractor shall be solely responsible for schedule impacts incurred because of Contractor, subcontractor, or supplier actions in implementing the requirements of this Section.
3.02 TEMPORARY EROSION AND SEDIMENT CONTROL DEVELOPMENT
A. The Contractor shall prepare a project SWPPP that complies with the County requirements.
1. The SWPPP shall describe construction activities and sequencing, and the proposed Temporary and Permanent Erosion and Sediment Control measures.
2. The SWPPP shall consist of planning, installing, inspecting, maintaining, and removing TESC BMPs per Central Oregon Stormwater Manual (2010) or equivalent. The BMPs shown in the Drawings are the minimum required to prevent pollution of air and water, to control peak volumetric flow rates and velocity of stormwater, and to control, respond to, and dispose of eroded sediment and turbid water during the term of the Contract.
B. Contractor shall develop project-specific TESC BMPs and incorporate them into the SWPPP. Contractor shall address the following issues as part of developing and implementing the BMPs.
1. TESC BMPs must meet the requirements in Central Oregon Stormwater Manual (2010) or equivalent.
2. TESC notes and details shown in the Drawings and the information in this Section form a basis of the minimum requirements for a TESC Plan.
Contractor shall develop a TESC Plan specific to the construction schedule and proposed means and methods prior to commencing construction activities for the duration of the Project.
3.03 TEMPORARY EROSION AND SEDIMENT CONTROL IMPLEMENTATION
A. Contractor is responsible for implementing and updating the ESCP including BMPs.
1. Contractor shall inspect and assess the BMPs daily and maintain these measures to ensure continued proper functioning for the duration of the Project.
Klamath Falls N.F.H. 01 57 13 - 4
2. Contractor will be responsible for documenting visual inspection of BMPs and maintaining records of the inspections on site.
3. During the construction period the Contractor shall, at no additional cost to the Owner, upgrade, supplement and/or maintain BMPs as needed, based on Contractor means and methods, work sequencing, and changing site conditions (e.g., changes to impervious surface coverage, proximity of work to storm conveyance systems, storm events, etc.).
Contractor shall modify these measures for changing site conditions and update the ESCP to document all modifications made.
B. Catch basins shall be cleaned when the depth of debris reaches 30% of the sump depth or the debris surface is six (6) inches below the outlet pipe.
Contractor shall clean all catch basins, manholes, and conveyance lines, if present, prior to Work completion. The cleaning process shall not flush sediment-laden water into a downstream system or wetland.
C. Contractor shall ensure that water, or a dust palliative and a dispensing subcontractor, if needed, is available for project use. It is the responsibility of the Contractor to develop and adhere to appropriate safety measures pertaining to the palliative use. This also includes ensuring the dispensing subcontractor develops and adheres to the appropriate safety measures, if a dispensing subcontractor is used. Water used for dust suppression shall not be applied at such a rate or in a location that it will generate runoff from the site.
D. BMPs in an inactive area shall be inspected and maintained by the Contractor until the area is permanently stabilized.
E. In the event that additional temporary erosion and pollution control measures are required due to the Contractor's negligence, carelessness, or failure to install permanent controls as a part of the Work as scheduled or as ordered by the Engineer, such work shall be performed by the Contractor at its own expense.
F. Contractor shall remove all TESC facilities, install permanent site surfacing improvements and permanent BMPs with minimal disturbance, and shall clean stormwater facilities prior to Work completion.
G. Contractor shall terminate the 1200-C permit upon final stabilization of the site.
END OF SECTION