This document is a submittal schedule template for a federal contract opportunity. It outlines the schedule for submitting various technical documents, drawings, reports, and test results related to the construction project. The key details include:
The project is for repairing sewer manholes and addressing infiltration and inflow (I&I). It requires submittals such as design documents, demolition and asbestos plans, civil drawings, architectural submittals, structural calculations, mechanical/HVAC system details, plumbing, and electrical components. Each submittal item has a required submission date referenced from the Notice to Proceed (NTP). The contract also requires closeout documentation such as O&M manuals, test results, and as-built drawings. This submittal schedule template appears to be a standard form used for this type of construction project to ensure the contractor provides the necessary technical documentation throughout the project lifecycle.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| WT11790270 | Repair Sewer Manholes, (Address I&I). | TBD | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | ||||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 3 | ||||||||||||||||||||
| Construction Schedule | X | NTP + 7 | ||||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | NTP + 7 | |||||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | NTP + 7 | |||||||||||||||||||||
| Contractor's QA/QC Plan | NTP + 7 | |||||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | Design | |||||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Design Documents to include: | NTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%) | |||||||||||||||||||||
| Roof Drain Storm Sewer Tie In | NTP+45 | |||||||||||||||||||||
| Wind Loading Diagrams for Roof | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Shear Walls | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Framing | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Blast Resistant Doors & Windows | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| HVAC Calculations | NTP+45 | |||||||||||||||||||||
| Sprinkler Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Fire Alarm Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Communications Layout | NTP+45 | |||||||||||||||||||||
| Technical Specifications | X | NTP+7 | ||||||||||||||||||||
| DEMOLITION/ASBESTOS | ||||||||||||||||||||||
| Demolition Plan | X | NTP+45 | ||||||||||||||||||||
| Asbestoes Plan | NTP+45 | |||||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| Soil Gradations for each type of soil used | Install -7 | |||||||||||||||||||||
| Moisture-Density curve for each type of soil used | Install -7 | |||||||||||||||||||||
| Nuclear Densometer Calibration | Install -7 | |||||||||||||||||||||
| Soil Compaction Test Results for Utilities, Facilities & Pavement | Install+7 | |||||||||||||||||||||
| Storm Pipe | Design+14 | |||||||||||||||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| Blast Resistant Doors and Frames | NTP+45 | |||||||||||||||||||||
| Door Hardware | NTP+45 | Hardware Schedule | ||||||||||||||||||||
| Gypsum Board-Type X | NTP+45 | |||||||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | NTP+45 | |||||||||||||||||||||
| Wood Paneling | NTP+45 | |||||||||||||||||||||
| Wood Chair Rails | NTP+45 | |||||||||||||||||||||
| Wood Ceiling Cloud | NTP+45 | |||||||||||||||||||||
| Sheet Vinyl Flooring | NTP+45 | |||||||||||||||||||||
| Rubber Base | NTP+45 | |||||||||||||||||||||
| Ceiling Tiles | NTP+45 | |||||||||||||||||||||
| Blast Resistant Window | NTP+45 | |||||||||||||||||||||
| Glazing | NTP+45 | |||||||||||||||||||||
| Solid Surface Countertops | NTP+45 | |||||||||||||||||||||
| Kitchen Cabinets | NTP+45 | |||||||||||||||||||||
| Garbage Disposal | NTP+45 | |||||||||||||||||||||
| Interior Paint | NTP+45 | |||||||||||||||||||||
| Exterior Paint | NTP+45 | |||||||||||||||||||||
| Roofing System | NTP+45 | |||||||||||||||||||||
| Roofing Insulation | NTP+45 | |||||||||||||||||||||
| Roof Drains | NTP+45 | |||||||||||||||||||||
| Scuppers | NTP+45 | |||||||||||||||||||||
| Coping | NTP+45 | |||||||||||||||||||||
| Flashing | NTP+45 | |||||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| Reinforcing Steel Drawings | NTP+45 | |||||||||||||||||||||
| Concrete Mix Design | NTP+45 | |||||||||||||||||||||
| Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Concrete Field Test Results | X | NTP+45 | ||||||||||||||||||||
| Reinforcing Steel Mill Certifications | NTP+45 | |||||||||||||||||||||
| Slump Test results & Concrete Truck Tickets (per truck) | Test + 3 | |||||||||||||||||||||
| 7-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| 28-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| Blast Resistant Window Attachment | Design + 14 | |||||||||||||||||||||
| MECHANICAL | ||||||||||||||||||||||
| HVAC Balancing | Design+14 | |||||||||||||||||||||
| Registers | Design+14 | |||||||||||||||||||||
| Dampers | Design+14 | |||||||||||||||||||||
| Ductwork | Design+14 | |||||||||||||||||||||
| Sprinkler Heads | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops Before Removal | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops After Installation | NTP+14 | |||||||||||||||||||||
| Ductwork | NTP+14 | |||||||||||||||||||||
| Controls | Design+14 | |||||||||||||||||||||
| Piping | Design+14 | |||||||||||||||||||||
| Heaters | Design+14 | |||||||||||||||||||||
| Valves | Design+14 | |||||||||||||||||||||
| Pumps | Design+14 | |||||||||||||||||||||
| Thermal Insulation | Design+14 | |||||||||||||||||||||
| Instrumentation | Design+14 | |||||||||||||||||||||
| PLUMBING | ||||||||||||||||||||||
| Plumbing Fixtures | NTP+45 | |||||||||||||||||||||
| Piping for Water | NTP+45 | |||||||||||||||||||||
| Garbage Disposal | X | NTP+45 | ||||||||||||||||||||
| Waste and Vent | X | NTP+45 | ||||||||||||||||||||
| INTERIOR ELECTRICAL | ||||||||||||||||||||||
| Cables(electrical,comm,fire alarm) | NTP+45 | |||||||||||||||||||||
| Switches | NTP+45 | |||||||||||||||||||||
| Receptacles | NTP+45 | |||||||||||||||||||||
| Panels | NTP+45 | |||||||||||||||||||||
| Breakers | NTP+45 | |||||||||||||||||||||
| Conduits | NTP+45 | |||||||||||||||||||||
| Lighting Fixtures | NTP+45 | |||||||||||||||||||||
| Lighting UPS units (if req'd) | NTP+45 | |||||||||||||||||||||
| Communication System Outlets(incl jacks) | NTP+45 | |||||||||||||||||||||
| Communications patch panels | NTP+45 | |||||||||||||||||||||
| PA Speakers | NTP+45 | |||||||||||||||||||||
| Fire Alarm Devices (All) | NTP+45 | |||||||||||||||||||||
| Occupancy Sensors | NTP+45 | |||||||||||||||||||||
| Power Packs | NTP+45 | |||||||||||||||||||||
| EXTERIOR ELECTRICAL | ||||||||||||||||||||||
| Conduits | NTP+14 | |||||||||||||||||||||
| Transformer | NTP+14 | |||||||||||||||||||||
| Meter | NTP+14 | |||||||||||||||||||||
| Cables(med & low voltage) | NTP+14 | |||||||||||||||||||||
| Switches | NTP+14 | |||||||||||||||||||||
| Contactors | NTP+14 | |||||||||||||||||||||
| Panels | NTP+14 | |||||||||||||||||||||
| Breakers | NTP+14 | |||||||||||||||||||||
| Controller | NTP+14 | |||||||||||||||||||||
| Junction Cabinet | NTP+14 | |||||||||||||||||||||
| Heating Mat | NTP+14 | |||||||||||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| O&M maint data and maint manuals & Manufacturer's Warranty for Communications Equipment | Install + 4 | |||||||||||||||||||||
| Factory and Field Test Certificates, Logs and Test Results | X | Before Acceptance | ||||||||||||||||||||
| Inspection Logbook | X | Before Acceptance | ||||||||||||||||||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | Final + 7 |