S01 12FPC323R0001 AM04.pdf
PDF 187 KB Posted
- Attached to
- PO-75 LaBranch Marsh Creation, Louisiana Federal contract opportunity
- Solicitation number
- 12FPC323R0001
About this file
This document describes a federal contract solicitation for a marsh creation project in Louisiana. The solicitation was issued by the Department of Agriculture Under Secretary for Farm Production and Conservation to restore 1,200 acres of marsh and create 6,540 linear feet of tidal creeks in St. Charles Parish, Louisiana near Norco. The project goals are to increase wildlife and fisheries habitat, acreage and diversity, and improve water quality, while also providing storm protection to Interstate 10. A firm fixed price construction contract will be awarded for a performance period of 524 calendar days following issuance of the notice to proceed.
View the file
Other files for this federal contract opportunity
Show all 38
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
� �� ���������������������������������� ��!"��#��#�$�������������������������������������������������$��%����������$������������$����"����$��$��"���$���������%���������!��������"%������$���$��������������"�������������������������%���$�&��'()*+,-�.'�/.+,�(012.3*-45-6-27�7.��-�,-0-)8-4�(7�79-�:*(0-�4-;)52(7-4�'.,�79-�,-0-):7�.'�.''-,;�:,).,�7.�79-�9.+,�(24�4(7-�;:-0)')-4�6(/�,-;+*7�)2�,-<-07).2�.'�/.+,�.''-,&��)�����=�$�%����������������������%�����$���������#���������$��"$������%�������>��%�������#�����������������"����$��$��"���$���������%��������>��$�=����������"����$��$��"���$���������%����������� ���$���$��������������"����������������������������>��������$����=����$��$��������������#���%$�������������������&�
| � | ? |
| @AB@? | C@DE�FGH�IFGHJ�DE�KL��M@�N |
NM
��IO��PQR��SHOT�UVRQWRXY����FGH�IFGHJ��PWPGZQ�
PXHPG� ?
�U[S� \D�@?
B[]S]D]̂\�C]_@DE� ?
@AB@���
�I?SA]\̀ D̂\�C
�M �N
�]\Ca a\Ca\ a�?_a�SIT��b�Lc �@S� ?
�U[S� \D�@?
B�C]_@̂ S�U�?\ A@Sa �d��d�
N ��� efg�hijk�jhlm�nopq�rsspjlk�hn�mntjujvrhjno�nu�vnohwrvhkxnwtlwkg��jh�mntjujlk�hil�vnohwrvhxnwtlw�ong�rk�tlkvwjylt�jo�jhlm�ezg{|&�(00.+27)25�(24�(::,.:,)(7).2�4(7(�}~����������� ���������������&�����������>�)�����������{�>�����$��%$���#.���$���%����� ��!"��#��$��������������������������$��$����������%$�����������������������������"�����������$�����������>�����������������""�!��#���������������������"����#7������=���%���$�����"������������������������������$������)����{�&��7�����%$����������������������$�$����������.���$�eeg�hijk�jhlm�nopq�rsspjlk�hn�rmlotmlohk�nu�knpjvjhrhjnok'(0)*)7/�0.4-�0.4-� {��&�4(7-4�}����~�������{�(&�6.4)')0(7).2�.'�0.27,(07�.,4-,�2.&��&�4(7-4�}����~��������(&�(6-246-27�.'�;.*)0)7(7).2�2.&
0.4-� �&�2(6-�(24�(44,-;;�.'�0.27,(07.,�}��������������������������������~�� ����
¡&�(46)2);7-,-4��/�}~����¢����¢���~��£�¤�0.4-�¥&�);;+-4��/ :(5-���.'��:(5-;�&�,-¦+);)7).2�:+,09(;-�,-¦&�2.&§&�-''-07)8-�4(7-|&�(6-246-27�6.4)')0(7).2��2.&� �&�:,.<-07�2.&�}~���̈ ©̈���ª©��{&��0.27,(07�)4�0.4-rmlotmloh�nu�knpjvjhrhjnoxmntjujvrhjno�nu�vnohwrvh
�d Nd�
09-01�.2- (&�79);�09(25-�.,4-,�);�);;+-4�:+,;+(27�7.��}�̈���������¢��������79-�09(25-;�;-7�'.,79�)2�)7-6�{��(,-�6(4-�)2�79-�0.27,(07�&�79-�(�.8-�2+6�-,-4�0.27,(07�.,4-,�);�6.4)')-4�7.�,-'*-07�79-�(46)2);7,(7)8-�09(25-;�}���¢�����¢��«������̈����«���������0&�79);�;+::*-6-27(*�(5,--6-27�);�-27-,-4�)27.�:+,;+(27�7.�(+79.,)7/�.'�4&�.79-,�}�̈��������̈�����£�������������������¢��������̈ �̈�̈���������������������;-7�'.,79�)2�)7-6�{�>�:+,;+(27�7.�79-�(+79.,)7/�.'�'(,��§&{�§���& lg�jmsnwhroh¬ 0���$����$� ������� ���$�%�$��������#����������%���������$��%$�����������������������������������������%��#�������&�.,4-,�2.&�)2�)7-6�{�(& {�&�4-;0,):7).2�.'�(6-246-27�6.4)')0(7).2�}®�«���̄���ª��° ±���������¢�����«������©����«���©���������²�����������ª³����£������́¢���������ª©��� ̂@KM�µZUGZX¶J�bZG·J� GPZHRFXDJR·�Z̧PXW̧PXH�GP̧F¹P·�ºEEEº�VXWPG�VXRH�»GR¶P�FX�HJP�¼RW�·¶JPWVQP�QRXP�RHP̧�
MODJP�¶QF·P�WZHP�ZXW�HŖP�F½�HJR·�·FQR¶RHZHRFX�GP̧ZRX·�VX¶JZXYPW�F½��GRWZ¾T��P¼GVZG¾��KT� ��T��¿
� b�
PXHGZQ�DŖPO
{¥(&�2(6-��(24�7)7*-�.'�0.27,(07)25�.'')0-,�}��̈�����̈�����{�(&�2(6-�(24�7)7*-�.'�;)52-,�}��̈�����̈����� {�0&�4(7-�;)52-4 {¥�&�+2)7-4�;7(7-;�.'�(6-,)0(�{��&�0.27,(07.,�.''-,., {¥0&�4(7-�;)52-4}��«����������̈���������¢���̄��������«�� }��«���������� ���������«�®�������µ?[�aa\�bO�a] ;7(24(,4�'.,6�§���,-8&�{{�|�{¥�:$���$��������5;(�'(,�����0',���§&|�§:$�=��%����������%�%���"�
Solicitation No. 12FPC323R0001 AMENDMENT 004-2/16/2023
PART I – THE SCHEDULE
PO-75 LaBranch Marsh Creation, Louisiana
B - SUPPLIES OR SERVICES AND PRICES
This solicitation requires bidding on all line items, failure to do so will disqualify the proposal.
Item No. Supplies/Services Spec.
No.
Quantity Unit Unit Price
Amount
1 Mobilization/Demobilization 8 1 LS XXX
2 Construction Surveys 7 1 LS XXX
3 Excavation, Marsh Creation Fill 423 6,153,026* CY
4 Identification Markers or Plaques, Staff Gauges
93 49* EA
5<AM03> Excavation, Tidal Creeks 21 6,848* LF <AM04>
XXX
<AM04>
5AA<AM0
3>
Excavation, Tidal Ponds 21 39* EA
6 Earthfill, Containment Dikes 421 54,618.060*
LF
7 Geotextile 95 695* SY
8 Field Office (Optional) 96 1 LS XXX
TOTAL : $
SUBMITTED BY: Unique Entity ID
52.211-18 Variation in Estimated Quantity. (Apr 1984) If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above fifteen (15) percent or below eighty five (85) percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within ten (10) days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
(End of clause)
Quantities marked with an * above are estimated quantities and the clause FAR 52.211-18, 52.211-18 Variation in Estimated Quantity, applies.
ONE AWARD FOR THE AGGREGATE OF ALL ITEMS WILL BE MADE AS A RESULT OF THIS
SOLICITATION