This invitation for bid solicits construction services for a new Sequoia National Forest Supervisors Office building and associated site improvements. Key details include:

  • The contractor shall provide all labor, materials, equipment, project management and transportation to construct a new approximately 10,816 square foot administrative office building, along with site work and utilities.

  • The base bid includes site improvements and an 8,671 square foot office building. Add alternatives include additional building space, a communications tower, generator system, parking lot, decks and landscaping.

  • The pre-bid conference will be held on August 25, 2020 at the project location. Bids are due on September 10, 2020.

  • The procurement is set aside exclusively for small businesses. The contract type will be firm fixed price. The project value is between $5-10 million. The performance period is 325 days for the base bid, with extensions for add alternatives.

View the file

Other files for this federal contract opportunity

Other files attached to 129JGP20B0001 - Sequoia NF SO Construction, newest first.
File Type Posted
Davis-Bacon Act WD - Building - CA20200016.pdf PDF
129JGP20B0001 - A00008 - Wage Determination.pdf PDF
129JGP20B0001 -A00007 - RFIs - Round 5.pdf PDF
129JGP20B0001 - A00006 - RFIs - Round 4.pdf PDF
129JGP20B0001 - A00005 - Structural - Electrical.pdf PDF
129JGP20B0001 - Addendum 4.pdf PDF
A00004 - Specifications.zip ZIP file
A00004 - New Drawings - Part 1.zip ZIP file
A00004 - New Drawings - Part 2.zip ZIP file
129JGP20B0001 - RFI Official Responses - RFIs 8-26-9-1 - Round 2.pdf PDF
129JGP20B0001 - A00004 - RFIs_Drawings_Specs.pdf PDF
129JGP20B0001 - RFI Official Responses - RFIs 9-1 - Round 3.pdf PDF
A00003 - Time Extension - Window Revision.pdf PDF
129JGP20B0001 - A00002 - RFI Official Responses.pdf PDF
Amendment A00001 - FAR 52.236-1.pdf PDF
7. Fire Plan.docx DOCX document
8. RFI Form.docx DOCX document
1. Construction Documents Compiled Drawings - Part 2 - Final.pdf PDF
4. Davis-Bacon Act WD # CA20200021 07_24_2020.pdf PDF
6. Divisional Breakdown.doc DOC document
5. Schedule Of Items.doc DOC document
3. Geotechnical Report - 5_26_2020.pdf PDF
1. Construction Documents Compiled Drawings - Part 1 - Final.pdf PDF
9. Safety and Environmental Questionnaire.pdf PDF
2. Construction Documents Specifications - Final.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

129JGP20B0001

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 of 50 129JGP20B0001 X

08-05-2019

1008930

USDA FOREST SERVICE

R5 CENT-CAL ACQ SERV AREA CCASA

631 COYOTE STREET

NEVADA CITY CA 95959

ONLY EMAIL OFFERS ACCEPTED AT

GREGORY.CUNNINGHAM@USDA.GOV

AND

ROBERT.BRINEY@USDA.GOV

GREGORY CUNNINGHAM (530) 478-6162 or (530) 575-7569

Project: Sequoia National Forest (NF) Supervisors Office (SO) Construction NAICS Code: 236220, Commercial and Institutional Building Construction Small Business Size Standard: $36.5 million IAW FAR 36.204 - Disclosure of the magnitude of construction projects is between $5,000,000 and $10,000,000

Project Description: The Contractor shall furnish all labor, materials, equipment, project management, supervision, and transportation for construction of a new Sequoia National Forest Supervisor’s office, including but not limited to general construction, site work, site improvements, site utilities, concrete foundations, wood frame, with exterior finishes including aluminum windows, manufactured stone, plaster, fiber cement siding, single ply and composition shingle roofing, civil, mechanical, plumbing, electrical, fire protection, and telecommunication work as shown on the drawings and specifications. All work is to be completed in accordance with the Statement of Work, drawings, specifications and attachments.

Place of Performance: 480 North Henrahan Street, Porterville, CA 93527

Note #1 to bidders: A pre-bid conference and site-visit shall be held on August 25, 2020 at 10:00AM PDT in large empty Field on the south side of work center located at 480 North Henrahan Street, Porterville, CA 93527. ***See FAR 52.236-7

Note #2 to bidders: This Procurement is a 100% Total Small Business Set-Aside. Offerors must have current SAM registration PRIOR to bid due date / time.

Note #3 to bidders: IAW FAR 14, Sealed Bids. Award will be base on price and price related factors.

Note #4 to bidders: All Request for Information (RFI's) shall be submitted ONLY to the Contracting Officer at Gregory.Cunningham@usda.gov, in writing using attached RFI form, by September 1st, 2020 @ 3:00 PM PDT.

Note #5 to bidders: Bid Bonds, Payment Bonds and Performance Bonds shall be required under this solicitation and any resultant contract.

Note #6 to bidders: The current Wage Rate Requirement Decision is attached as "Davis-Bacon Act WD # CA20200016”

10 325 (+)

X X 52.211-10

X 10

1 10:00 AM PDT

09-10-2020

X mailto:Gregory.Cunningham@usda.gov

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

E-mail:__________________________________

DUNS:____________________________________

9JGP

USDA FOREST SERVICE

VA R5 CENT-CAL ACQ SERV AREA CCASA

631 COYOTE STREET

NEVADA CITY CA 95959

Invoice Processing Platform (IPP), www.ipp.gov

GREGORY CUNNINGHAM

CONTRACTING OFFICER

Page | 3

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID INSTRUCTIONS

2.2 STATEMENT OF WORK

2.3 BID SCHEDULE

2.4 DIVISIONAL PRICING BREAKDOWN

2.5 52.216-1 TYPE OF CONTRACT (APR 1984)

2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

2.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

2.8 52.228-1 BID GUARANTEE (SEP 1996)

2.9 52.233-2 SERVICE OF PROTEST (SEP 2006)

2.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB

1995)

2.11 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) ..24

3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

3.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—

CERTIFICATION (JUN 2018)

GENERAL CONDITIONS

4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,

AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER

COVERED ENTITIES (JUL 2018)

4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING

RESPONSIBILITY MATTERS (OCT 2018)

4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984) ALTERNATE I (APR 1984)

4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(JUL 2013)

4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)

Page | 4

4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL

LABOR RELATIONS ACT (DEC 2010)

4.8 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY

2014)

4.9 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT

FOR EPS-DESIGNATED ITEMS (MAY 2008)

4.10 52.223-20 AEROSOLS (JUN 2016)

4.11 52.223-21 FOAMS (JUN 2016)

4.12 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE

AGREEMENTS (OCT 2016) ALTERNATE I (MAY 2014)

4.13 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE II (JUN 2009)

4.14 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.15 52.236-4 PHYSICAL DATA (APR 1984)

4.16 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

ADDITIONAL ATTACHMENTS

Page | 5

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 BID INSTRUCTIONS

SUBMISSION REQUIREMENTS OF BIDS:

All the following documents shall be emailed only to Gregory.Cunningham@usda.gov & Robert.Briney@usda.gov in response to this Invitation for Bid (IFB). Sending your bid to any other individuals may deem the firm ineligible for award. Incomplete bid packages may be determined nonresponsive.

(a) One (1) fully completed and signed Standard Form 1442 with blocks 14 – 20 completed, acknowledgment of all amendments either via entering data in block 19 of the SF1442 OR by completing blocks 15 a, b, and c of the Amendment(s) (SF30’s) and returning with bid.

(b) Five (5) fully completed Pricing Breakdown Sheet (1 each for base, alt 1, alt 2, alt 3, & alt 4.)

(c) One (1) fully completed Price Schedule (provided with the Solicitation)

(d) One (1) scanned original completed/signed SF24 Bid Bond with Raised Seals, and Power of Attorney as required.

(e) One (1) fully completed Safety and Environmental Questionnaire

(f) Documentation of Safety & Environmental Record

(g) Documentation of Experience Modification Rate (EMR)

IMPORTANT SUBMISSION NOTES:

• Email all of the above items in one concise .pdf with the following email subject line;

o Company Name - Sequoia NF SO Construction – IFB: 129JGP20B0001

• Bidders are responsible for insuring and verifying their bid and all required bid documents are received at the public bid opening address stated below by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment).

• Bidders are cautioned to carefully review System for Award Management in regards to Representations and Certifications. See FAR 52.204-7, 52.204-8, 52.209-7 & 52.209-9 for specific instruction as needed.

• Emailed offer of bid packages to Gregory.Cunningham@usda.gov & Robert.Briney@usda.gov are the only acceptable submission method.

o Email submission should not exceed 8MB total as it could potentially be rejected by the FS network.

• Bids received after bid opening date and time will be rejected.

mailto:Robert.Briney@usda.gov mailto:Robert.Briney@usda.gov

Page | 6

• Any exception to the terms and conditions of the IFB will result in a nonresponsive bid.

CONTRACT TYPE:

• The awarded contract will be a firm fixed price (FFP) contract.

• This solicitation is a Total Small Business Set-Aside per FAR 19.507(c)

PROSPECTIVE CONTRACTORS’ RESPONSIBILITY:

• Purchases shall be made from, and contracts shall be awarded to, responsible prospective contactors only. The presumed winning bidder must be determined as “Responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications. To aid in making this determination, bidders shall provide, at bid-opening all documents as required under “Submission Requirements of Bids” above.

• Submitted documents will be reviewed promptly after bid-opening. This information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines below or submit this information may result in a determination of Non-Responsibility and make the bid ineligible for award. The Contracting Officer will obtain additional information as needed and specified in FAR 9.105-1 to make the Determination of Responsibility, to include, but not limited to the Federal Awardee Performance and Integrity Information System (FAPIIS), Excluded Parties List System (EPLS), and Past Performance Information Retrieval System (PPIRS).

SAFETY & ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE (EMR):

• To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.

• All Bidders shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their bid, on provided certification form.

1. SAFETY & ENVIRONMENTAL RECORD: A self-certification that the bidder has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

2. EMR: All bidders shall submit information regarding their current EMR. This information shall be obtained from the bidder’s insurance carrier and be furnished on the insurance carrier’s letterhead. Bidder will also enter the information on provided form.

BID OPENING:

• Bids are due Thursday, September 10th, 2020 at 10:00 am PDT at the address specified in Block 8 of SF1442.

• Due to the current COVID-19 pandemic, we currently DO NOT accept hand-delivered bids. Follow email only submission instructions on page 6.

• Due to the current COVID-19 pandemic, the Public Bid Opening will not be held in person.

Participants who wish to attend the Bid Opening may do so via telephone. The bid opening will begin promptly on Thursday, September 10th, 2020 at 11:00 am PDT.

o Bid opening call-in number: 888-844-9904

Page | 7 o Bid opening Access Code: 8318480 o Offerors are advised that all participants in the call will be muted except for FS employees and no questions will be allowed during the bid opening. If questions / concerns do arise they should be emailed to the Contracting Officer at Gregory.Cunningham@usda.gov.

• At the time of Bid Opening, an apparent low, responsive, responsible bidder will be selected;

however, actual low bidder chosen for award shall be subject to verification and confirmation of required, submitted bid documents.

PRE-BID SITE VISIT:

• Bidders are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing construction services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

• See Provision 52.236-27 for specific information regarding the project pre-bid site visit.

• This pre-bid site visit will be the only opportunity for potential bidders to visit the site.

• All potential bidders, subcontractors, and suppliers are strongly encouraged to attend this pre-bid site visit.

REQUEST FOR INFORMATION (RFI):

• To obtain clarifications and/or additional information concerning the contract requirements, drawings, or specifications, submit a written RFI utilizing the RFI Form included in this IFB, which is to be sent via email ONLY to Gregory.Cunningham@usda.gov. See RFI Form for specifics.

• RFI’s will be responded to as necessary in amendment format which will be posted on beta.SAM.gov. Deadline for submission of RFIs for this IFB is September 1st, 2020 at 3:00PM PDT. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone / verbal request for information, to include during the site visit will not be accepted, returned, or deemed as valid.

PLANS/SPECIFICATIONS/DRAWINGS:

• Drawings and specifications are attached in electronic format to this solicitation. Bidders are responsible for downloading and printing their own bid sets. The USFS will not provide hard copies of the drawings and specifications to any bidder. Contractors are responsible for ensuring that any construction document package used for bidding or construction is complete and up-to-date.

TRAINING:

• All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s Competent Person/Superintendent shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge (if deemed required) will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

mailto:Gregory.Cunningham@usdagov

Page | 8

PREPARATION OF BIDS:

• The Federal Government WILL NOT pay for any costs incurred in preparation and submission of bids.

SYSTEM FOR AWARD MANAGEMENT (SAM):

• Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Bids shall be deemed non-responsive and rejected if the contractor is not registered and current in SAM prior to bid submission. Bidders are strongly encouraged to ensure they have an active DUNS number and are registered in SAM prior to submitting their bid.

JOINT VENTURES: See 13 C.F.R. § 121.103

(e) Affiliation based on joint ventures: A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.

This means that a specific joint venture entity generally may not be awarded more than three contracts over a two year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.

As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to a finding of general affiliation between and among them.

For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (e)(4) of this section.

NOTICE TO PROCEED (NTP):

• A notice to proceed shall be issued after award at an estimated date of October 1st, 2020 which will begin the 325 calendar day period of performance. The NTP date and time “to be determined” after award to a successful bidder. Primary factor in determination to issue NTP shall be the Prime Contractor’s submission of, and the Government’s review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.

http://www.sam.gov/

Page | 9

SOLICITATION AUTHORITY:

• This Invitation For Bid (IFB) is conducted under FAR Part 14 - Sealed Bidding, where firms are bidders and shall submit bids. References to RFP and Bidder’s, in technical specification sections and technical drawings are strictly coincidental and strictly for purposes of administrative convenience and efficiency. The Contracting Officer exercises final authority over all aspects of this IFB and any resultant contract.

SOLICITATION CLAUSES AND PROVISIONS:

• Please note that this IFB, and any resultant contract, and all clauses and provisions located there, supersede and contain final authority. Those clauses and provisions that may be referenced in IFB technical specification sections and technical drawings are strictly coincidental and for purposes of administrative convenience and efficiency.

SOLICITATION DEFINITIONS:

• Throughout this IFB, and any resultant contract, the terms Contracting Officer's Representative (COR), Project Engineer (PE), Resident Engineer (RE), and Project Manager (PM), all denote the same engineering official and may be used equally and interchangeably as described by the Contracting Officer (CO).

BRAND NAME OR EQUAL:

• The IFB may include the salient characteristics of the “or equal” aspect for determination of what is equal to any cited brand name. See FAR 52.211-6 for “brand name or equal” information. This is an extremely long, detailed, and comprehensive IFB, including all specifications and drawings. Please note that, wherever a brand name is cited, contractor shall ensure, in any resultant contract, that any equal has the salient characteristics of the brand name.

• Lack of confirmation shall be grounds for Government inspection at any time and Government direction for replacement of materials or equipment by the Contractor at no increase in contract price or time.

WORK DAYS AND HOURS

• Normal work days and hours for this project range from 07:00 AM – 5:00 PM Monday - Friday.

Access to the work site may be restricted to these hours and days. Work during other than normal work days and hours may be required, but days and hours must still be coordinated in advance with the Contracting Officer through the COR.

FEDERAL HOLIDAYS ARE:

New Year's Day Labor Day Martin Luther King Day Columbus Day

Presidents' Day Veterans' Day Memorial Day Thanksgiving

Independence Day Christmas

Page | 10

2.2 STATEMENT OF WORK

United States Forest Service (USFS)

Sequoia National Forest

Project: Sequoia NF SO Construction

1.2 DESCRPTION OF WORK

Furnish all labor, equipment and material to accomplish the Work under this contract, which consists of the construction of a new, approximately 10,816 sf administrative and interagency dispatch office and associated site and off-site improvements on a 2.08 acre site. The building is single story, wood frame, with exterior finishes including aluminum windows, manufactured stone, plaster, fiber cement siding, and composition shingle roofing. Interior finishes include carpet, tile, casework, suspended acoustic and wood panel ceilings, Site improvements include concrete walks, hardwood patios, asphalt paving, landscape planting and irrigation, trash enclosure and fencing.

Project is divided into a base bid and bid alternatives, as described below:

• Base Bid: Construct approximately 2.1 acres of site improvements (earthwork, street improvements, utilities, paving, landscaping) and construct an 8,671 SF single story wood framed office building.

• Add Alternative 1: Construct an additional 1,308 SF of office space on the west end of the office building; furnish and install a 50' radio antenna tower.

• Add Alternative 2: Construct an additional 850 SF of office space on the east end of the office building.

• Add Alternative 3: Furnish and Install an emergency generator system to support portions of the new building, construct a gravel parking lot in the northeast portion of the site, construct two wood decks, and install additional landscape boulders.

• Add Alternative 4A, 4B, 4C: Furnish and install work station furniture and other fixed in place furniture for each separate portion of the new office building (Base bid, Alt 1, and Alt 2).

The Contractor should refer to the SCHEDULE OF ITEMS and project plans and specifications when making estimates of quantities or work.

C.2 PROJECT LOCATIONS

• The Porterville Work Center is located at 480 N. Henrahan, Porterville, California.

C.3 CONTRACT TIME

• Estimated start work date is October 1, 2020. The contract time will be 325 days for the base bid plus 25 days additional for each Add Alternative awarded (Alts 1, 2, and 3 only); up to 400 days total. Contract time includes delays for weather; locating and transporting supplies and materials; and final site cleanup.

Page | 11

C.4 PROJECT SITE CLEAN UP

• Project site cleanup includes the removal and proper disposal of all construction trash, debris, residue, and asphalt and concrete slag off of National Forest Land. Items such as miscellaneous construction materials are considered the property of the Contractor and shall be removed from the project site.

• All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed according to all Local, State, and Federal rules, regulations, and laws governing such disposal.

• During the Work the Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent. The Contractor shall not place materials of any kind into private or Government trash bins or dumpsters.

C.5 PRICE RANGE

• The price range of this project is between $5,000,000 and $10,000,000.

C.6 SPECIAL CONDITIONS AFFECTING THE WORK

a. Physical Conditions. The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys performed by the Government, and do not guarantee site surface and subsurface conditions. The Contractor is responsible for making his own evaluation of site conditions and shall complete the work through any and all sub-surface conditions, with appropriate construction methods.

b. Weather. Low temperatures at the project site range from temperatures of less than 20 ºF in December and January to lows of 65 ºF in July and August. High temperatures range from 45 ºF in December and January to over 100 ºF in July and August. The annual precipitation at the project site is less than 12 inches per year.

c. Work Hours. Project is within the city limits of Porterville adjacent to residential housing areas.

Work hours are from 7:00 am to 5:00 pm Monday through Friday. Weekend equipment work is not allowed at any time during the Work. Dogs and pets are not allowed on the project site at any time.

d. Safety, Emergency Communications and Evacuation. Contractor is responsible for the safety of the Contractor’s employees including Subcontractors employees, Government employees associated with the project, and any visitors to the site both Government and private.

The Contractor shall submit a project safety plan to the Contracting Officer for review prior to commencement of Work. The project safety plan shall comply with the appropriate California OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.

e. Traffic Safety. Contractor is responsible for complying with the State of California regulations for working in the right-of-way. This includes but is not limited to furnishing traffic control signs and flag persons.

f. Temporary Site Utilities. Contractor may install temporary site utilities to support work on the project. The installation of temporary utilities is the responsibility of the Contractor and shall be paid for by the Contractor. The Contractor shall provide the Contracting Officer with written

Page | 12 certification that all temporary site utilities have been properly disconnected and the final utility bills are paid in full.

g. Toilets. No toilet or shower facilities are available on site. Contractor shall provide toilet facilities for its employees.

h. Camping. There is no onsite camping at this location.

i. Security. Contractor is responsible for the Contractor’s equipment and building materials supplied to the site. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools, ladders and other equipment shall be secured at the end of each working day. On Fridays all construction debris, trash, and refuse shall be properly stored in dumpsters or trash bins or removed from the site.

j. Burning Permits. Contractor is subject to all rules and regulations governing the on site burning of slash and other debris. Contractor shall obtain a burning permit from the jurisdiction having control over burning. The Contractor shall comply with Fire Plan for Construction and Service Contracts included in the Contract.

k. Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site to remove weeds, mud, grease and oil buildup from the tires, wheels, tracks, engines and engine compartments, and other surfaces. Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with all applicable rules, regulations and laws. Contractor shall submit a project spill response plan at the pre-work meeting for review by the Contracting Officer.

C.7 PRE-BID CONFERENCE OR TOURS

• A Pre-Bid Tour will be conducted on August 25th, 2020 at 10 a.m. at the Porterville Work Center, 480 North Henrahan Street in Porterville, CA. Meet at the large unimproved dirt lot on the south end of the Porterville WC, adjacent to the intersection of East Morton Ave and North Henrahan St. Contractors shall notify the Contracting Officer of their intent to attend the pre-bid tour.

• See FAR 52.236-27 for further details.

Page | 13

2.3 BID SCHEDULE

Pay Item No.

Item Description

Method of Measurement

Estimated Pay Unit

Unit Price

Amount Quantity

Base Bid Work Items (8,658 SF Building & Sitework):

019000-1

Mobilization, General Conditions & Requirements

L.S.Q.

L.S.

024119-1

Selective Demolition of Existing Items Designated for Removal; Includes Clearing & Grubbing; Legal Debris Disposal

033000-1

Cast-In-Place Concrete, Type A, Including Minor Concrete Structures, Walkways, Curbs & Gutters, Waterways, Inlets & Outlets, Catch Basins & Decorative Concrete

033000-2

Cast-In-Place Concrete, Type B, Including Rigid Pavement Concrete Structures, Access Roads/Driveways & Pads

033000-3

Cast-In-Place Concrete, Type C, Including Structural Slabs On Grade & Foundations

042200-1

Concrete Unit Masonry Walls & Masonry Stone Veneer

060000-1

Rough Carpentry & Wood Framing Work, Includes Structural Steel For Framing Work

060000-2

Interior Architectural Woodwork, Wood Casework & Fiber Reinforced Panels

070000-1

Thermal & Moisture Protection Work, Insulation, Air Barrier System, Roofing System & Siding

080000-1

Building Openings Work, Doors, Windows, Louvers & Vents

090000-1

Exterior & Interior Walls Finishes Work, Cement Plaster, Gypsum Board, Tile & Painting

090000-2

Acoustical & Linear Wood Ceiling Finishes, Flooring & Carpeting Tiles With Base Work

100000-1

Miscellaneous Specialties Equipment Work, Includes Electrical Kitchen & Projection Equipment, and Roll-Down Blinds

210000-1 Fire Suppression Systems Work L.S.Q. 1 L.S.

220000-1 Building Plumbing Systems Work L.S.Q. 1 L.S.

230000-1 Building HVAC & Mechanical Systems Work L.S.Q. 1 L.S.

260000-1

Building Interior & Exterior Electrical, Communications, Electronic Safety & Security Work

310000-1

Site Earthwork, Excavation & Embankment, Save Suitable Excavation, Dispose of Unsuitable Excavation & Waste Offsite, Imported Commercial Source Embankment, Engineered Fill To all Structural Pads, Finish Grading to Design Elevations, Compaction as Specified per ASTM D1557

320000-1

Exterior Improvements Work, Landscaping, Irrigation System, Ornamental Metal Fencing, Gates & Controls, Selected Site Outdoor Furnishings

321123-1

3/4-Inch Minus Crushed Aggregate Base Course From A Commercial Source

Page | 14

Measurement

321217-1

Hot Mix Bituminous Pavement From A Commercial Source

331100-1

Site New Water Distribution System, Complete

333000-1 Site New Sanitary Sewer System, Complete L.S.Q. 1 L.S.

334000-1 Storm Drainage System, Complete L.S.Q. 1 L.S.

Total Base Bid:

Add Alternative 1 Bid Work Items (West End 1,310 SF Building Addition & Communications Tower):

033000-3A

042200-1A Masonry Stone Veneer L.S.Q. 1 L.S.

060000-1A

060000-2A

070000-1A

080000-1A

090000-1A

090000-2A

100000-1A

210000-1A Fire Suppression Systems Work L.S.Q. 1 L.S.

220000-1A Building Plumbing Systems Work L.S.Q. 1 L.S.

230000-1A Building HVAC & Mechanical Systems Work L.S.Q. 1 L.S.

260000-1A

338116-1A

Communications Tower, Complete With Foundation (Type D Concrete), Grounding, Lightning Protection, Antennas With Cabling, and Connection to Building Communications Room

Total Bid Add Alternative 1:

Sub Total - Base + Alternative 1:

Add Alternative 2 Bid Work Items (East End 850 SF Building Addition):

033000-3B

042200-1B Masonry Stone Veneer L.S.Q. 1 L.S.

060000-1B

060000-2B

070000-1B

080000-1B

Page | 15

Measurement

090000-1B

090000-2B

100000-1B

210000-1B Fire Suppression Systems Work L.S.Q. 1 L.S.

220000-1B Building Plumbing Systems Work L.S.Q. 1 L.S.

230000-1B Building HVAC & Mechanical Systems Work L.S.Q. 1 L.S.

260000-1B

Total Bid Add Alternative 2:

Sub Total - Base + Alternative 1 & 2:

Add Alternative 3 Bid Work Items (Emergency Generator System, Northeast Gravel Parking Lot, Wood Decks, Landscape Boulders):

263213-1C

Standby Emergency Power Supply System, Complete

310000-1C

Site Earthwork, Excavation & Embankment, Save Suitable Excavation, Dispose of Unsuitable Excavation & Waste Offsite, Imported Commercial Source Embankment, Engineered Fill To all Structural Pads, Finish Grading to Design Elevations, Compaction as Specified per ASTM D1557

321123-1C

3/4-Inch Minus Crushed Aggregate Base Course From A Commercial Source

320000-1C

Exterior Improvements Work, Wood Decks, Landscape Boulders

334000-1C Storm Drainage System Work L.S.Q. 1 L.S.

Total Bid Add Alternative 3:

Sub Total - Base + Alternative 1, 2, & 3:

Add Alternative 4A Bid Work Items (Fixed in Place Furniture for Base Bid Building:

125900-1D

Fixed in Place Systems Furniture for 8,658 SF Base Bid Office, Furnish & Install

Add Alternative 4B Bid Work Items (Fixed in Place Furniture for West End Building Addition):

125900-1E

Fixed in Place Systems Furniture for 1,310 SF West End Office Addition (Add Alternative 1) with Changes to Base Bid Furniture Layout, Furnish & Install

Add Alternative 4C Bid Work Items (Fixed in Place Furniture for East End Building Addition):

125900-1F

Fixed in Place Systems Furniture for 850 SF East End Office Addition (Add Alternative 2), Furnish & Install

Total Bid Add Alternative 4 A, B, & C:

Total Bid - Base + Alternative 1, 2, 3, & 4:

Page | 16

NOTICE OF ADDITIVE OR DEDUCTIVE ALTERNATES:

(a) The low offeror and the items to be awarded shall be determined as follows -

(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.

(2) The low offeror shall be the Offeror that -

(i) Is otherwise eligible for award; and

(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.

(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.

(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and

(ii) Add that next item if an award may be made that includes that item and is within the available funds.

(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if -

(1) It is in the best interest of the Government;

(2) Funds are available at the time of award; and

(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.

(c) Example. The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.

https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=c8c3a0e1352656420971c4be2ffb81f2&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=c8c3a0e1352656420971c4be2ffb81f2&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=180b662c286174212c790cce449b7af7&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=c8c3a0e1352656420971c4be2ffb81f2&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=180b662c286174212c790cce449b7af7&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9f1a663007e7a282a7257646796e6600&term_occur=999&term_src=Title:48:Chapter:2:Subchapter:H:Part:252:Subpart:252.2:252.236-7007

Page | 17

2.4 DIVISIONAL PRICING BREAKDOWN

REF DESCRIPTION TOTAL

DIV01 DIVISION 1 – GENERAL REQUIREMENTS $

DIV02 DIVISION 2 – EXISTING CONDITIONS $

DIV03 DIVISION 03 – CONCRETE $

DIV04 DIVISION 04 – MASONRY $

DIV05 DIVISION 05 - METALS $

DIV06 DIVISION 06 – WOODS AND PLASTIC $

DIV07 DIVISION 07 – THERMAL AND MOISTURE

PROTECTION

DIV08 DIVISION 08 – DOORS AND WINDOWS $

DIV09 DIVISION 09 - FINISHES $

DIV10 DIVISION 10 - SPECIALTIES $

DIV11 DIVISION 11 - EQUIPMENT $

DIV12 DIVISION 12 - FURNISHINGS $

DIV14 DIVISION 14 – CONVEYING EQUIPMENT $

DIV21 DIVISION 21 – FIRE SPRINKLER SYSTEM $

DIV22 DIVISION 22 – PLUMBING $

DIV23 DIVISION 23 – HEATING, VENTIALTING, & AIR

CONDITIONING

DIV26 DIVISON 26 – ELECTRICAL $

DIV27 DIVISION 27 – COMMUNICATIONS $

DIV28 DIVISION 28 – ELECTRONIC SAFETY AND SECURITY $

DIV31 DIVISION 31 - EARTHWORK (CIVIL) $

DIV32 DIVISION 32 – EXTERIOR IMPROVEMENTS (CIVIL) $

DIV33 DIVISION 33 – UTILITIES (CIVIL) $

DIV34 DIVISION 34 – TRANSPORTATION (CIVIL) $

SUB TOTAL: $

BONDS AND INSURANCE $

OVERHEAD $

Page | 18

PROFIT $

TOTAL BID FOR – BASE – ALT 1 – ALT 2 – ALT 3 – ALT 4 (CIRCLE ONE): $

NOTE* COMPLETE ABOVE PRICING BREAKDOWN FOR BASE, ALT 1, ALT 2, ALT 3 AND

ALT 4 FOR A TOTAL OF 5 SUBMITTED WITH BID.

*This document is to be used only for price analysis per FAR 14.408-2

Page | 19

CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL

Contractor Certification Regarding Project: 129JGP20B0001 - Sequoia NF SO Construction

2017 2018 2019 2020

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations. (Four serious, one repeat, or one willful disqualifies the contractor.)

Number of violations from EPA within the last 3 years.

Please attach explanation for any violations.

Company’s Current Insurance Experience Modification Rate (EMR) = _____________

(Note: Contractor must support the EMR with a signed letter from Insurance Carrier on their letterhead.)

Signature: ______________________________________________

Typed Name: ______________________________________________________

Title: ______________________________________________________

Page | 20

2.5 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO

ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION

(FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

16.1 % 6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2)

Page | 21 specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

USDA FOREST SERVICE

R5 CENT-CAL ACQ SERV AREA CCASA

631 COYOTE STREET

NEVADA CITY CA 95959

(End of Provision)

2.8 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

Page | 22

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or 3,000,0000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.9 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Gregory Cunningham

Hand-Carried Address:

R5 CENT-CAL ACQ SERV AREA CCASA

ATTN: GREG CUNNINGHAM

Mailing Address:

R5 CENT-CAL ACQ SERV AREA CCASA

ATTN: GREG CUNNINGHAM

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

Page | 23

2.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I

(FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

August 25th, 2020 @ 10:00AM PDT

(c) Participants will meet at—

480 North Henrahan Street in Porterville, CA.

Meet at the large unimproved…