This document appears to be Amendment 3 Attachment 8 containing drawings related to a solicitation for CNRC Critical Upgrades to Insulation, Piping & HVAC in Houston, TX. The drawings indicate that the scope of work involves the removal and replacement of existing insulation with 4" of new spray polyurethane foam (SPF) and a thermal barrier in specified areas. The drawings provide clarification on the areas requiring this work, which include plastered ceilings, walls above curtain walls, and other outlined sections. The solicitation is a 100% small business set-aside with a project value between $1-5 million under NAICS code 236220 - Commercial and Institutional Building Construction.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please confirm the outlined area in black and gray have existing insulation removed and replaced with 4” of new SPF and thermal barrier ?
ALL QUESTIONS ARE
CONFIRMED, AND
ADDITIONAL EXPLANATION
IS PROVIDED IN BLUE
WHERE REQUIRED. SEE
REVISED DRAWINGS FOR
GREATER CLARITY
REGARDING INTENDED
SCOPE OF WORK BASED
ON THE HATCH PATTERNS
PROVIDED IN THE
LEGENDS VERSUS THOSE
SEEN ON THE REFLECTED
CEILING PLANS.
Please confirm the outlined area in black and gray have existing insulation removed and replaced with 4” of new SPF and thermal barrier ?
Please confirm the outlined area in black and gray have existing insulation removed and replaced with 4” of new SPF and thermal barrier?
Please confirm this area is a plastered ceiling that will require demo and 4” new SPF and thermal barrier, also can you confirm the ceiling height?
CONFIRMED. THE CEILING HEIGHT VARIES
DUE TO THE TIERED SEATING, BUT IT IS
22'-10" AT ITS HIGHEST CONDITION.
Please confirm the outlined area in black have existing insulation removed and replaced with 4” of new SPF and thermal barrier?
If curtain wall is replaced will it be done before the new foam is installed, also please confirm the foam is only above curtain wall ?
CONFIRMED. INSULATION IS TO BE
INSTALLED AT THE EXTERIOR WALL
ABOVE THE CURTAIN WALL.
Please confirm the outlined area in black have existing insulation removed and replaced with 4” of new SPF and thermal barrier?
Please confirm if the little areas in gray are part of the SPF scope of work? THESE SHADED AREAS ARE NOT
INTENDED TO INDICATE SCOPE OF
WORK. THESE HAVE BEEN REMOVED
IN THE REVISED DRAWINGS.
Please confirm the outlined area in black have existing insulation removed and replaced with 4” of new SPF and thermal barrier?
Please confirm if the little areas in gray are part of the SPF scope of work? THESE SHADED AREAS ARE NOT
INTENDED TO INDICATE SCOPE OF
WORK. THESE HAVE BEEN REMOVED
IN THE REVISED DRAWINGS.
Please confirm the outlined area in black have existing insulation removed and replaced with 4” of new SPF and thermal barrier?
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
File details come from the government source that posted it. Updated .