Amendment 3 Attachment 1 Maximum Workweek Update.pdf
PDF 148 KB Posted
- Solicitation number
- 12805B24R0012
About this file
This document is an amendment to a solicitation for a construction project to upgrade the insulation, piping, and HVAC systems at the CNRC facility in Houston, TX. The project has an estimated value between $1-5 million and is set aside for small businesses under NAICS code 236220.
The key details include: 1) Limits on work hours and days, with insulation and piping work required to be performed at night and on weekends; 2) Government holiday schedule; 3) Contractor submission requirements for construction schedules and work hours; 4) Detailed requirements for controlling erosion, sedimentation, and pollution during construction; and 5) Technical proposal instructions and evaluation factors, including past performance, schedule, experience modification rate, and technical approach.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12805B24R0012
Page | 14
H.4 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (AGAR 452.236-74) (NOV 1996)
(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.)
(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, and impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.
(End of Clause)
H.5 MAXIMUM WORKWEEK - CONSTRUCTION SCHEDULE (AGAR 452.236-75) (NOV 1996)
Within 10 (ten) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
A schedule as required by FAR clause 52.236-15, "Schedules for Construction Contracts" and
The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
Limit work in the existing building to normal business working hours of 7 a.m. to 4 p.m., Monday through Friday, unless otherwise indicated. Insulation repairs indicated on architectural drawings and storm drain piping replacement indicated on plumbing drawings must be completed Sunday night through Friday morning - 6 PM to 7 AM local time.
MAXIMUM WORKWEEK - CONSTRUCTION SCHEDULE (SUPPLEMENT)
The following applies to all work performed on Government-owned property:
(a) Listed below are official Government holidays:
New Year’s Day January 1* Birthday of Martin Luther King Third Monday in January Washington’s Birthday Third Monday in February Memorial Day Last Monday in May Juneteenth June 19* Independence Day July 4* Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11* Thanksgiving Day Fourth Thursday in November Christmas Day December 25* Inauguration Day January 20* (for Washington D.C. Metropolitan Area (WDCMA))
*In accordance with Federal regulations, if these holidays fall on a Saturday, the holiday will be observed on Friday, if Sunday, holiday will be observed on Monday.
Brian.Dean Cross-Out
| SECTION B- SUPPLIES AND SERVICES AND PRICE/COST |
| B.2 SCHEDULE OF ITEMS |
| B.3 Period of Performance |
| SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT |
| C.1 Description of Work |
| C.2 PERMITS AND LICENSES |
| C.3 DIRECTIVES, INSTRUCTIONS AND REFERENCES |
| C.4 WORK MANAGEMENT |
| C.5 MATERIALS AND EQUIPMENT |
| C.6 SERVICE INTERRUPTIONS/UTILITY OUTAGES |
| C.7 EMPLOYEE REQUIREMENTS |
| C.8 OSHA |
| C.9 KEY PERSONNEL |
| C.10 EMPLOYEE REQUIREMENTS |
| C.11 EMPLOYEE CONDUCT/REMOVAL OF EMPLOYEES |
| C.12 STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-72) (FEB 1988) |
| C.13 PERIOD OF PERFORMANCE (AGAR 452.211-74) (FEB 1988) |
| E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988) |
| E.3 FINAL INSPECTION |
| E.4 FINAL ACCEPTANCE |
| SECTION F - DELIVERIES OR PERFORMANCE |
| F.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) (APR 1984) |
| SECTION G - CONTRACT ADMINISTRATION DATA |
| G.2 CONTRACT CLOSEOUT |
| G.3 AS-BUILT DRAWINGS |
| G.4 RELEASE FROM CLAIMS |
| G.5 SUPPLEMENT TO CHANGES CLAUSE |
| G.6 SUMMARY SHEET FORMAT |
| G.7 INVOICE PREPARATION AND SUBMISSION |
| G.8 Contractor Performance Information and Contractor Performance Assessment Reporting System (CPARS) (FAR 42.1502) |
| SECTION H - SPECIAL CONTRACT REQUIREMENTS |
| H.2 USE OF PREMISES (AGAR 452.236-72) (NOV 1996) |
| H.3 ARCHAEOLOGICAL OR HISTORIC SITES (AGAR 452.236-73) (FEB 1988) |
| H.4 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (AGAR 452.236-74) (NOV 1996) |
| H.5 MAXIMUM WORKWEEK - CONSTRUCTION SCHEDULE (AGAR 452.236-75) (NOV 1996) |
| H.6 SAMPLES AND CERTIFICATES (AGAR 452.236-76) (FEB 1988) |
| H.7 KEY PERSONNEL (AGAR 452.237-74) (FEB 1988) |
| H.8 SUBMITTALS AND SHOP DRAWINGS |
| H.9 CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE |
| H.10 INVOICES |
| H.11 AS-BUILT DRAWINGS AND OPERATIONS AND MAINTENANCE MANUALS |
| H.12 LIST OF MATERIALS |
| H.13 COOPERATION WITH OTHER CONTRACTORS |
| H.14 PROPERTY DAMAGE LIABILITY INSURANCE |
| H.15 SUBCONTRACTORS, OUTSIDE ASSOCIATES AND CONSULTANTS |
| H.16 Energy Efficiency |
| H.17 PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT (AGAR 452.236-71) (NOV 1996) |
| H.18 BIOBASED PRODUCTS REQUIREMENTS |
| I.2 BUY AMERICAN - CONSTRUCTION MATERIALS (FAR 52.225-9) (NOV 2021) |
| I.3 POSTAWARD CONFERENCE (AGAR 452.215-73) (NOV 1996) |
| I.4 SIZE STANDARD AND NAICS CODE INFORMATION (AGAR 452.219-70) (SEP 2001) |
| I.5 REIMBURSEMENT FOR BOND PREMIUMS--FIXED-PRICE CONSTRUCTION CONTRACTS AGAR 452.232-70) (NOV 1996) |
| K.2 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FAR 52.204-8) (DEC 2022) |
| K.3 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (FAR 52.225-10) (MAY 2014) |
| K.4 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (FAR 52.225-12) (MAY 2014) |
| K.5 BIOBASED PRODUCT CERTIFICATION (52.223-1) (May 2012) |
| K.6 REPS AND CERTS |
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICE TO OFFERORS |
| L.2 TYPE OF CONTRACT (FAR 52.216-1) (APR 1984) |
| L.3 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY (FAR 52.222-23) (FEB 1999) |
| L.4 BID GUARANTEE (FAR 52.228-1) (SEP 1986) |
| L.5 SERVICE OF PROTEST (FAR 52.233-2) (SEP 2006) |
| SITE VISIT ATTENDANCE IS MANDATORY TO PROVIDE A QUOTE ON THIS SOLICITATION |
| L.7 ALTERNATIVE FORMS OF SECURITY (AGAR 452.228-70) (NOV1996) |
| L.8 INQUIRIES (AGAR 452.204-70) (FEB 1988) |
| L.9 INSTRUCTIONS FOR THE PREPARATION OF OFFERS |
| OFFER SUBMISSION DOCUMENTS: |
| TECHNICAL SUBFACTORS: |
| PAST PERFORMANCE SUBFACTORS: |
| NOTICE TO OFFERORS: |
| SECTION M - EVALUATION FACTORS FOR AWARD |
| FACTOR 1 – Technical |
| Subfactor 2: Submit a completed Exhibit A, Bid Schedule |
| Subfactor 3: Submit a properly executed SF 24, Bid Bond |
| Subfactor 4: Experience Modification Rate |
| Subfactor 5: Technical Narrative |
| FACTOR 2 – Past Performance Subfactor 1: Documented Experience |
| Subfactor 2: CPARS |
| FACTOR 3 – Price |