This document provides specifications for a road and general construction multiple award IDIQ contract opportunity for the Chequamegon-Nicolet National Forest. The Forest Service intends to make multiple awards for a 5-year IDIQ with a maximum value of $7 million. Work will include road, bridge, structure and site construction and repair such as native surface roads, gravel or paved roads, motorized and non-motorized trails, road decommissioning, small non-residential buildings, bridges, culverts, aquatic passages, stream restoration, signs, guardrails, fences, and general excavation. Projects will primarily be located on the Chequamegon-Nicolet National Forest but may also be in Wisconsin, Minnesota and Michigan. Task orders will be competed amongst IDIQ holders for specific work identified throughout the life of the contract. The NAICS code is 237310 and the small business size standard is $39.5 million. Vendors must register in SAM to submit offers for this small business set-aside. A full solicitation will be available on February 26, 2020 on the listed website.

View the file

Other files

File Type Posted
Amendment 2_Questions and Answers 2.docx DOCX document
Amendment 2_C1_Jackson Price Schedule_revision 2.DOCX DOCX document
Amendment 2 SF30.pdf PDF
Questions and Answers 03182020.docx DOCX document
Amendment 1_ A1_Shawano Price Schedule_revision 1.docx DOCX document
Amendment 1_C1_Jackson Price Schedule_revision 1.DOCX DOCX document
Amendment 1 SF30.pdf PDF
C4_Jackson GP Coverage.pdf PDF
C1_Jackson Price Schedule.DOCX DOCX document
B1_Sawdust Price Schedule.docx DOCX document
C3_Jackson PlansDrawings.pdf PDF
Wage Determination.pdf PDF
RFP 1256A120R0003.pdf PDF
A3_Shawano PlansDrawings.pdf PDF
B2_Sawdust Supplemental Specifications.docx DOCX document
A1_Shawano Price Schedule.docx DOCX document
A2_Shawano Supplemental Specifications.docx DOCX document
B3_Sawdust PlansDrawings.pdf PDF
A4_Shawano Ck GP Coverage.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jackson – Forest Service Supplemental Specifications 2 Table of Contents

Preface3
101 - Terms¸ Format¸ and Definitions4
101.01 Meaning of Terms.4
101.03 Abbreviations.4
101.04 Definitions.5
102 - Bid¸ Award¸ and Execution of Contract9
Delete Section 102.9
103 - Scope of Work10
Delete Subsections 103.02, 103.03, 103.04, 103.05.10
104 - Control of Work11
Delete Subsections 104.01, 104.02, 104.04.11
104.06 Use of Roads by Contractor.11
106 - Acceptance of Work12
106.01 Conformity with Contract Requirements.12
106.02 Visual Inspection.14
107 - Legal Relations and Responsibility to the Public15
Delete Subsection 107.05.15
108 - Prosecution and Progress16
Delete Section 108.16
109 - Measurement and Payment17
Delete Subsections 109.06, 109.07, 109.08, 109.09.17
109.01 Measurement of Work.17
109.02 Measurement Terms and Definitions.18
153 - Contractor Quality Control19
153.02 Qualifications.19
153.07 Records and control charts.19
155 - Schedules for Construction Contracts20
Delete Section 155.20
156 - Public Traffic21
Section 156. – PUBLIC TRAFFIC21
157 - Soil Erosion and Sediment Control24
157.04 General.24
201 - Clearing and Grubbing25
201.04 Clearing.25
201.06 Disposal.25
203 - Removal of Structures and Obstructions26
203.05 Disposing of Material.26
209 - Structure Excavation and Backfill27
209.07 Dewatering.27
209.09 Backfill.27
209.10 Compacting.27
302 - Minor Crushed Aggregate31
302.04 Placing Crushed Aggregate.31
625 - Turf Establishment32
Section 625. — TURF ESTABLISHMENT32
703 - Aggregate36
703.05 Subbase, Base, Surface Course, and Screened Aggregate.36

Preface Preface_wo_09_09_2019

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016 Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016 Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations AFPA — American Forest and Paper Association FSAR — Forest Service Acquisition Regulations MSHA — Mine Safety and Health Administration NESC — National Electrical Safety Code WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP—milepostlocation
ppm—parts per millionvolume
STAstationlocation

101.04_National_9_5_2018 Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards — The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

103 - Scope of Work 103.00_National_11_9_2016 Delete all of Section 103 except Subsection 103.01 Intent of Contract.

Delete Subsections 103.02, 103.03, 103.04, 103.05.

104 - Control of Work 104.00_National_11_9_2016 Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016 Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

106 - Acceptance of Work 106.01_National_7_18_2017 Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

Sampling method;

Number of samples;

Sample transport;

Test procedures;

Testing laboratories;

Reporting;

Estimated time and costs; and Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

1. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017 Delete Subsection 107.05.

Delete Subsection 107.05.

108 - Prosecution and Progress 108.00_National_11_9_2016 Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment 109.00_National_11_9_2016 Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.01_National_2_22_2019 Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:

109.01 Measurement of Work.

Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.

Table 109-1 Decimal Accuracy of Quantities for Final Payment

Pay Item
Level of Precision
Linear Foot
1
Exception--Timber, Steel, and concrete Piles
0.1
Station
0.1
Mile
0.01
Square Foot
0.1
Square Yard
0.1
Each
1
Acre
0.01
Gallon
1
M-Gals.
0.1
Cubic Yard
1

Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;

0.1

Exception--Concrete; Masonry
0.01
Pound
1
Ton
0.1

Exception--Calcium Chloride;

Sodium Chloride; Hydrated Lime;

Bituminous Materials; Pavements;

Bed Course Materials 0.01

Hour
0.1
MFBM
0.01
Station Yard
1
Cubic Yard Mile
1
Ton Mile
1

109.02_National_11_9_2016 Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

153 - Contractor Quality Control 153.02_National_6_4_2019 Delete Subsection 153.02 and replace with the following:

153.02 Qualifications.

Submit the following for approval with the quality control plan:

(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years’ experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.

(b) Testers. Provide testers with at least one year experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:

(1) NICET Level II certification in highway material or equivalent state or industry certification;

(2) Certification by a regional certification program (such as Western Alliance for Quality Transportation Construction (WAQTC), Northeast Transportation Technician Certification Program (NETTCP), Southeast Task Force for Technician Training and Qualification (STFTTQ), or Multi Regional Training and Certification (M-TRAC)); or

(3) At least one year employment by an AASHTO accredited laboratory performing equivalent sampling and testing.

153.07_National_6_4_2019 Delete Subsection 153.07 and replace with the following:

153.07 Records and control charts.

Maintain complete testing and inspection records by pay item number and make them accessible to the CO.

155 - Schedules for Construction Contracts 155.00_National_11_9_2016 Delete Section 155 in its entirety.

Delete Section 155.

156 - Public Traffic 156.00_National_6_4_2019 Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Permanent Traffic Control633
Traffic Signing and Marking Material718
Concrete Barriers and Precast Guardwalls618
Temporary plastic fence710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 15 minutes at any one time followed by an open period of no less than 5 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1 Temporary Road Closures

Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
FSR 374
As indicated on Drawing C-01
As indicated on Drawing C-01
Road may be closed once for a period of 3 days.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.

157 - Soil Erosion and Sediment Control 157.04_National_6_4_2019 Delete Subsection 157.04 and replace with the following:

157.04 General.

Thirty (30) days prior to the start of construction, submit a written plan according to subsection 104.03 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.

When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.

201 - Clearing and Grubbing 201.04_National_6_4_2019 Add the following paragraph to Subsection 201.04:

201.04 Clearing.

(e) Do not cut vegetation less than 3 feet in height and less than 3 inches in diameter that is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road unless otherwise designated.

201.06_National_6_4_2019 Delete the first sentence of Subsection 201.06 and replace the following:

201.06 Disposal.

Merchantable timber is Government property.

203 - Removal of Structures and Obstructions 203.05_National_6_4_2019 Add the following to Subsection 203.05:

203.05 Disposing of Material.

(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.

(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.

(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.

(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.

(i) Decking. Remove brush from designated log deck areas. Limb and top logs.

Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than 30 feet and decked in designated log deck location.

Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).

Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

(j) Removal to designated locations. Remove construction slash to designated locations.

(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.

209 - Structure Excavation and Backfill 209.07_Forest_6_4_2019

209.07 Dewatering.

Add the following:

Do not pump water from foundation excavations directly into live streams or marine waters. Pump water into settling areas or filter bags as specified in the contract.

209.09_National_6_4_2019 Make the following Changes to Subsection 209.09:

209.09 Backfill.

Add the following to Subsection 209.09(a):

(a) General.

Backfill without damaging or displacing the culvert or structural plate structure. Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.

Add the following to Subsection 209.09(b)

(b) Pipe culverts.

Do not place or backfill pipe that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:

· Embankment height greater than 6 feet at subgrade centerline.

· Installation in a protected stream course.

· Round pipe with a diameter of 48 inches or greater.

· Pipe arches with a span of 50 inches or greater.

· Any box culvert or structure other than pipe culverts.

209.10_National_6_4_2019 Delete Subsection 209.10 and replace with the following:

209.10 Compacting.

Compact the embankment using one of the following methods as specified.

(a) Compaction Method 1. Use AASHTO T 27 to determine the quantity of material retained on a No. 4 (4.75-millimeter) sieve. Compact as follows:

(1) More than 80 percent retained on a No. 4 (4.75-millimeter) sieve. Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation:

(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds (180 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute;

(b) Eight roller passes of a 20-ton (20-metric ton) compression-type roller; or

(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.

Increase the compactive effort for layers deeper than 12 inches (300 millimeters) as follows:

For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 209.10(a)(1)(a), by four passes; or For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 209.10(a)(1)(b) and (c), by eight passes.

(2) 50 to 80 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content. Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 (4.75-millimeter) sieve. Multiply this number by the percentage of material passing a No. 4 (4.75-millimeter) sieve, and add 2 percent to determine the optimum moisture content of the material.

Use nonvibratory rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet(1 meter) per second. Compact each layer of material full width according to Subsection 209.10(a)(1).

(3) Less than 50 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. For material classified A-1 or A-2-4, determine the maximum density according to AASHTO T 99, Method C..

Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A6 and A-7 to within 2 percent of the optimum moisture content.

Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.

(b) Compaction Method 2. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate roller compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Ensure rollers meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch (4.5 kilogram/millimeter) of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi (550 Kilopascals).

(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 pounds per inch (4.5 kilogram/millimeter) of width of roller drum.

(c) Compaction Method 3. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer until there is no visible evidence of further consolidation. Make at least three complete passes.

(d) Compaction Method 4. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer.

(e) Compaction Method 5. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact the complete surface with a bucket of an excavator larger than 39,000 pounds (18 metric ton) Gross Vehicle Weight using a minimum of three blows. Overlap compaction by ½ width of bucket.

(f) Compaction Method 6. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact using an approved mechanical tamper for a minimum of three complete passes.

When compacting with rollers or hauling and spreading equipment is not practical, use approved mechanical tampers for a minimum of three complete passes.

302 - Minor Crushed Aggregate 302.04_National_6_4_2019 Add the following to Subsection 302.04 and 302.04(a)

302.04 Placing Crushed Aggregate.

Written approval of the surface is required before placing aggregate.

(a) Roadway aggregate.

For pit run or grid-rolled material, furnish material smaller than the maximum size, no gradation will be required otherwise. After processing on the road, remove all oversize material from the road and dispose as directed by the CO.

625 - Turf Establishment 625.00_National_6_13_2019 Delete Section 625 in its entirety and replace with the following:

Section 625. — TURF ESTABLISHMENT Description

625.01 This work consists of soil preparation, seeding, and mulching. Seeding and mulching methods are designated as dry or hydraulic.

Material

625.02 Conform to the following Subsections:

Mulch
713.05
Seed
713.04

Construction Requirements

625.03 General. Apply turf establishment to the areas shown on the plans or worklists within 10 days after completion of ground disturbing activities.

Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage. Do not seed during windy weather or when the ground is excessively wet, frozen, or snow covered.

Assure that all seed and mulch used in the work conforms to the weed free requirements of Section 713.

625.04 Preparing Seedbed. Ensure that the surface soil is in a roughened condition favorable for germination and growth.

625.05 Watering. Maintain moisture as follows:

No watering is required for this project.

625.06 Fertilizing. Apply fertilizer by the following methods:

No fertilizing is required for this project.

625.07 Seeding. Apply seed by the following methods:

(a) Dry Method. Apply the seed with approved power driven seeders, drills, or other mechanical equipment. Hand-operated seeding methods are satisfactory on areas inaccessible to mechanical equipment; or

Furnish and apply the following kinds and amounts of pure live seed:

Seed mix shall be WISDOT #75 applied at a minimum rate of 300 pounds per acre.

Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

625.08 Mulching. Apply Mulch within 8 hours after seeding by the following methods.

(a) Dry Method. Apply mulch with a hand spreader or a spreader utilizing forced air at a rate of 3000 pounds per acre.

625.09 Protecting and Caring for Seeded Areas. Protect and care for seeded areas including watering according to 625.05. Repair or apply supplemental applications of seed, mulch, fertilizer, and water according to 625.05 as many times as needed until turf is established or final acceptance.

625.10 Acceptance. Material for turf establishment will be evaluated under Subsections 106.02 and 106.03.

Placing of turf establishment will be evaluated under Subsections 106.02 and 106.04.

Measurement

625.11 Measure the Section 625 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:

When measuring turf establishment and supplemental applications by the acre (hectare), measure on the ground surface.

When measuring water by volume or mass, measure in the hauling vehicle or by metering.

Payment

625.12 The accepted quantities will be paid at the contract price per unit of measurement for the Section 625 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

703 - Aggregate 703.05_National_7_2_2019 Delete 703.05 and replace with the following:

703.05 Subbase, Base, Surface Course, and Screened Aggregate.

(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:

(1) GradationTable 703-2
(2) Liquid limit, AASHTO T 8925 max.
(3) Plastic limit, AASHTO T 90Nonplastic
(4) Los Angeles abrasion, AASHTO T 9640% max.
(5) Sodium sulfate soundness loss (5 cycles),12% max.

AASHTO T 104

(6) Durability index (coarse), AASHTO T 21035 min.
(7) Durability index (fine), AASHTO T 21035 min.
(8) Fractured faces, ASTM D 582150% min.

(9) Free from organic matter and lumps or balls of clay

Do not use material that breaks up when alternately frozen and thawed or wetted and dried.

Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.

(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:

(1) GradationTable 703-3
(2) Liquid limit, AASHTO T 8935 max.

(3) Plastic Index, AASHTO T 90

a) If the percent passing the No. 200 sieve is less than 12%2 to 9
b) If the percent passing the No. 200 sieve is greater than 12%Less than 2
(4) Los Angeles abrasion, AASHTO T 9640% max.
(5) Sodium sulfate soundness loss (5 cycles),12% max.

AASHTO T 104

(6) Durability index (coarse), AASHTO T 21035 min.
(7) Durability index (fine), AASHTO T 21035 min.
(8) Fractured faces, ASTM D 582175% min.

(9) Free from organic matter and lumps or balls of clay

Do not use material that breaks up when alternately frozen and thawed or wetted and dried.

Do not furnish material that contains asbestos fibers.

Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.

(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:

(1) GradationTable 703-16
(2) Plastic Index, AASHTO T 90Less than 9
(3) Los Angeles abrasion, AASHTO T 9655% max.

(4) Free from organic matter and lumps or balls of clay.

Do not use material that breaks up when alternately frozen and thawed or wetted and dried.

Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.

Delete Table 703-2 and replace with the following:

Table 703-2 Target Value Ranges for Subbase and Base Gradation

Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
E (Base)
62 – 90 (6)
36 – 74 (6)
12 – 26 (4)
4.0 – 7.0 (3)

( ) The value in the parentheses is the allowable deviation () from the target values..

D (Base)

100
86 – 100 (6)
51 – 82 (6)
36 – 64 (6)
12 – 26 (4)
4.0 – 7.0 (3)

C (Base)

80 – 100 (6)
64 – 94 (6)
40 – 69 (6)
31 – 54 (6)

4.0 –7.0 (3)

B (Subbase)

100
97 – 100

40 – 60 (8)

4.0 – 12.0 (4)

A (Subbase)
100
97 – 100

65 – 79 (6)

45 – 59 (7)

28 – 42 (6)
9 – 17 (4)
4.0 – 8.0 (3)
Sieve Size
2½ inch
2 inch
1½ inch
1 inch
3/4 inch
1/2 inch
3/8 inch
No. 4
No. 40
No. 200

Delete Table 703-3 and replace with the following:

Table 703-3 Target Value Ranges for Surface Gradation

Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
U
71 – 90 (6)
50 – 68 (7)
34 – 51 (6)
19 – 30 (5)
8.0 – 15.0 (4)

( ) The value in the parentheses is the allowable deviation () from the target values.

If the plasticity index (PI) is greater than 0, the TV range for the No. 200 sieve size is 8-12 (4).

T

71 – 91 (6)

43 – 60 (7)
30 – 46 (6)
16 – 28 (5)
8.0 – 15.0 (4)
S
100
72 – 92 (6)
51 – 71 (6)
36 – 53 (7)
26 – 40 (6)
14 – 25 (5)
8.0 – 15.0 (4)

H

97 - 100

80 – 92 (6)
58 – 70 (7)
28 – 40 (6)
16 – 26 (5)
9.0 – 14.0 (4)

G

100
97 - 100
70 – 80 (6)
51 – 63 (7)
28 – 39 (6)
19 – 27 (5)
10.0 – 16.0 (4)
F
100
97-100
76-89 (6)
56-68 (6)
43-53 (7)
23-32 (6)
15-23 (5)
10.0-16.0 (4)
Sieve Size
1 1/2 inch
1 inch
3/4 inch
1/2 inch
3/8 inch
No. 4
No. 8
No. 16
No. 40
No. 200

Add Table 703-13:

Table 703-13 Gradation Requirements for Screened Aggregate

Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)

Grading Designation

L
M
N
O
P
Q
R
6 inch
100
100

4 inch

100
100

3 inch

100
100

2 inch

No. 4

15-45

15-45

15-45 image1.png