Text version
Eng Estimate
| Trail IDIQ - TASK ORDER - WOOD RUN TRL EXT. ENGINEER'S ESTIMATE | ||||||
| Base Bid 1 - Wood Run Trail Extension #396 STA. 00+00 to STA. 47+23 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 981, 982, 983 | Work items on Trail Maintenance & Construction sections to include: Brush Cutting, Logging Out, Danger Tree Removal, Erosion Control (includes dual trail length) | AQ | Mile | 0.94 | ||
| 915, 991 | Existing 8 ft. wide trail tread maintenance / restoration (includes 8 ft. wide crowned tread grading with on-site soil, ditches, grade dips, etc.) | AQ | LF | 919 | ||
| 941 | 3 ft. wide Stone Layer -imported aggregate armoring | AQ | LF | 402 | ||
| 941 | 3 ft. wide Crowned Turnpike / No Excavation (imported soil-aggregate turnpike) | AQ | LF | 831 | ||
| 941 | 3 ft. wide Crowned Turnpike (imported soil-aggregate turnpike) | AQ | LF | 263 | ||
| 911, 912 | 2 ft. wide new trail construction (includes dual trail length) | AQ | LF | 2,552 | ||
| 935 | Crib wall - on-site rock | AQ | SF | 15 | ||
| TOTAL BASE BID 1: | $0 | |||||
| Option Bid 1 - Wood Run Trail Bridge | ||||||
| Special Project Specs & Dwgs | Bridge, including 30 LF turnpiked approaches | AQ | LS | 1 | ||
| TOTAL BASE 1 + OPTION 1 BID: | $0 |
| Trail IDIQ - TASK ORDER -HELEN'S LOOP & LARRY'S LINK TRLS ENGINEER'S ESTIMATE | ||||||
| Base Bid 2 - Larry's Link Trail: TR711 STA. 0+00 to 32+91 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, turnpike construction, brushing & clearing, logging out, danger tree removal, erosion control | AQ | mile | 0.62 | ||
| 944 | Armoring of trail tread at stream approaches - ACB with Geotextile | AQ | SF | 100 | ||
| 912 | Imported suitable soil for tread restoration & turnpike construction | AQ | CY | 110 | ||
| 941 | Imported #57 stone for turnpike construction | AQ | Ton | 8 | ||
| TOTAL Base 2: | $0 |
| Base Bid 3 - Helen's Loop Trail: TR712A STA. 0+00 to 43+84 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 916,981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, turnpike construction, brushing & clearing, logging out, danger tree removal, erosion control | AQ | mile | 0.83 | ||
| 912 | Imported suitable soil for tread restoration & turnpike construction | AQ | CY | 170 | ||
| 941 | Imported #57 stone for turnpike construction | AQ | Ton | 25 | ||
| TOTAL Base 3: | $0 |
TOTAL BASE BIDS 2&3: $0
| Option Bid 2 - Helen's Loop Trail: TR712B STA. 0+00 to 19+07 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, clearing & brushing, road to trail conversion, logging out, danger tree removal, erosion control | AQ | mile | 0.36 | ||
| TOTAL Option Bid 2: | $0 |
TOTAL BASE 2&3 and OPTION BID 2: $0
TOTAL ALL BASE BIDS: $0
TOTAL ALL OPTION BIDS: $0
TOTAL ALL BIDS: $0
Bid Schedule
| Trail IDIQ - TASK ORDER - WOOD RUN TRL EXT. BID SCHEDULE | ||||||
| Base Bid 1 - Wood Run Trail Extension #396, STA. 00+00 to STA. 47+23 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 981, 982, 983 | Work items on Trail Maintenance & Construction sections to include: Brush Cutting, Logging Out, Danger Tree Removal, Erosion Control (includes dual trail length) | AQ | Mile | 0.94 | ||
| 915, 991 | Existing 8 ft. wide trail tread maintenance / restoration (includes 8 ft. wide crowned tread grading with on-site soil, ditches, grade dips, etc.) | AQ | LF | 919 | ||
| 941 | 3 ft. wide Stone Layer -imported aggregate armoring | AQ | LF | 402 | ||
| 941 | 3 ft. wide Crowned Turnpike / No Excavation (imported soil-aggregate turnpike) | AQ | LF | 831 | ||
| 941 | 3 ft. wide Crowned Turnpike (imported soil-aggregate turnpike) | AQ | LF | 263 | ||
| 911, 912 | 2 ft. wide new trail construction (includes dual trail length) | AQ | LF | 2,552 | ||
| 935 | Crib wall - on-site rock | AQ | SF | 15 | ||
| TOTAL BASE BID 1: | ||||||
| Option Bid 1 - Wood Run Trail Bridge | ||||||
| Special Project Specs & Dwgs | Bridge, including 30 LF turnpiked approaches | AQ | LS | 1 |
| TOTAL BASE 1 + OPTION 1 BID: | ||||||
| Trail IDIQ - TASK ORDER -HELEN'S LOOP & LARRY'S LINK TRLS BID SCHEDULE | ||||||
| Base Bid 2 - Larry's Link Trail: TR711 STA. 0+00 to 32+91 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, turnpike construction, brushing & clearing, logging out, danger tree removal, erosion control | AQ | mile | 0.62 | ||
| 944 | Armoring of trail tread at stream approaches - ACB with Geotextile | AQ | SF | 100 | ||
| 912 | Imported suitable soil for tread restoration & turnpike construction | AQ | CY | 110 | ||
| 941 | Imported #57 stone for turnpike construction | AQ | Ton | 8 | ||
| TOTAL Base 2: |
| Base Bid 3 - Helen's Loop Trail: TR712A STA. 0+00 to 43+84 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 916,981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, turnpike construction, brushing & clearing, logging out, danger tree removal, erosion control | AQ | mile | 0.83 | ||
| 912 | Imported suitable soil for tread restoration & turnpike construction | AQ | CY | 170 | ||
| 941 | Imported #57 stone for turnpike construction | AQ | Ton | 25 | ||
| TOTAL Base 3: |
TOTAL BASE BID 2&3:
| Option Bid 2 - Helen's Loop Trail: TR712B STA. 0+00 to 19+07 | ||||||
| ITEM NO. | DESCRIPTION | MEASURE | UNIT | Quantity | Unit Price | TOTALS |
| 912, 915, 981, 982,983, 985, 988, 991 | Tread Maintenance - including tread & drainage restoration, clearing & brushing, road to trail conversion, logging out, danger tree removal, erosion control | AQ | mile | 0.36 | ||
| TOTAL Option Bid 2: |
TOTAL BASED BIDS 2 & 3 AND OPTION BID 2:
TOTAL ALL BASE BIDS:
TOTAL ALL OPTION BIDS:
TOTAL ALL BIDS:
| Any other work required by the specifications or detail drawings will be considered incidental to the above items and |
| no additional payment will be made. |