Abstract of Offers Huntington.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Huntington Ravine Winter Access Trail Replacement
Solicitation number
12445525B0013
Issued by

About this file

The file is an Abstract of Offers for the Huntington Ravine Winter Access Trail Replacement project, documenting bid details from seven potential contractors. The solicitation, issued by the U.S. Department of Agriculture Forest Service for the White Mountain National Forest, requires demolition of five existing trail bridges and construction of new trail bridges with varying lengths (41-foot, 26-foot, 30-foot, and 24-foot), including steel girder bridges with timber plank or dowel-lam decks on steel grade beam foundations.

The bid abstract reveals four contractors submitted pricing: Kovilic Construction Co, Rays Electric and General Contracting, J.P. Sicard Inc., with total bid prices ranging from $1,540,980 to $4,627,739. The project is set aside for small businesses, applies Davis-Bacon wage rates, and has a bid date of 22 September 2025 at 1:00 PM EST. A mandatory site visit is scheduled for 29 August 2025 at 10:00 AM EST at the Pinkham North Visitor Center in Gorham, NH, with contact information provided for Bryanne Thompson. Contractors must be active in SAM.gov to be eligible for award.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Abstract of Offerors
ISSUING OFFICE:
Address
SOLICITATION NO.:12445525B0013
PROJECT:Huntington Ravine Trail Bridges ReplacementOFFEROR NO. 1OFFEROR NO. 2OFFEROR NO. 3OFFEROR NO. 4OFFEROR NO. 5OFFEROR NO. 6OFFEROR NO. 7
Vendor Name:Kovilic Construction CoRays Electric and General ContractingJ.P. Sicard Inc.
Vendor City/State:
Amendments Acknowledged:
Acceptance Time:
SAM eUID
Business Size:
Bid Guarantee:YesYesYes
Government EstimateOFFEROR NO. 1 PRICEOFFEROR NO. 2 PRICEOFFEROR NO. 3 PRICEOFFEROR NO. 4 PRICEOFFEROR NO. 5 PRICEOFFEROR NO. 6 PRICEOFFEROR NO. 7 PRICE
ITEM
NO.DESCRIPTIONEST.
QTY.UNIT

OF

MEASUREUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL
AMOUNTUNIT
PRICETOTAL

AMOUNT

1Mobilization1LS$152,700.00$152,700.00$20,000.00$20,000.00$1,883,222.60$1,883,222.60$1,125,000.00$1,125,000.00$0.00$0.00
2Construction Survey and Staking, Method 1, Tolerance Class C1LS$48,000.00$48,000.00$30,000.00$30,000.00$5,000.00$5,000.00$12,500.00$12,500.00$0.00$0.00
3Silt Sock218LF$10.00$2,180.00$100.00$21,800.00$7.38$1,608.79$7.00$1,526.00$0.00$0.00
4Earth Berms30FT$335.00$10,050.00$500.00$15,000.00$105.73$3,171.80$23.00$690.00$0.00$0.00
5Clearing and Grubbing, Disposal Method A Removal of Old Structure, Portions, Disposal1LS$1,000.00$1,000.00$25,000.00$25,000.00$27,900.00$27,900.00$187,011.00$187,011.00$0.00$0.00
6Method A1LS$120,000.00$120,000.00$25,000.00$25,000.00$1,470.00$1,470.00$1,418,000.00$1,418,000.00$0.00$0.00
7Trail Excavation, Compaction Method B4CY$400.00$1,600.00$500.00$2,000.00$1,125.00$4,500.00$222.00$888.00$0.00$0.00
8Structure Excavation233CY$400.00$93,200.00$500.00$89,000.00$25.28$4,500.00$20.00$3,560.00$0.00$0.00
9Structural Backfill35CY$500.00$17,500.00$500.00$12,000.00$125.00$3,000.00$61.00$1,464.00$0.00$0.00
10Salvage Backfill, Compaction Method 775CY$350.00$26,250.00$500.00$33,500.00$44.78$3,000.00$27.00$1,809.00$0.00$0.00
11Riprap, Class VI, Machine Placed155CY$1,000.00$155,000.00$1,000.00$155,000.00$165.63$25,672.24$123.00$19,065.00$0.00$0.00
12Geotextile, Type III, Class I160SY$20.00$3,200.00$25.00$4,000.00$1.68$268.80$6.00$960.00$0.00$0.00
13Aggregate Base, Grading D, Compaction Method B Structural Steel, Galv, Furnished, Fabricated22CY$800.00$17,600.00$1,000.00$22,000.00$83.45$1,835.90$79.00$1,738.00$0.00$0.00
14Erected16013LBS$35.00$560,455.00$25.00$400,325.00$23.08$369,561.40$59.00$944,767.00$0.00$0.00
15Substructure Steel, Salvaged, Modified, and Erected15238LBS$10.00$152,380.00$60.00$914,280.00$17.78$271,000.00$8.00$121,904.00$0.00$0.00
16Treated Structural Timber1LS$123,200.00$123,200.00$700,000.00$700,000.00$233,696.20$233,696.20$625,734.00$625,734.00
17Underdrain System, 6 Inch120LF$28.00$3,360.00$100.00$12,000.00$54.63$6,555.43$14.00$1,680.00
18Placing Conserved Topsoil, 3 Inch39SY$15.00$585.00$100.00$3,100.00$16.13$500.00$152.00$4,712.00
19Seeding, Hydraulic or Dry Method1LS$6,000.00$6,000.00$20,000.00$20,000.00$1,955.80$1,955.80$2,062.00$2,062.00
20Mulching, Hydraulic or Dry Method Rolled Erosion Control Product, Type 2.D1LS$2,000.00$2,000.00$20,000.00$20,000.00$424.20$424.20$2,059.00$2,059.00
21Natural Netting31SY$15.00$585.00$100.00$3,100.00$36.87$1,143.08$35.00$1,085.00
22Signs, Type III Sheeting21SF$35.00$735.00$100.00$2,100.00$221.19$4,645.03$307.00$6,447.00
23Post, Steel 3 lb120LF$50.00$6,000.00$100.00$12,000.00$6.57$788.76$12.00$1,440.00
24Reflectivity20EA$370.00$7,400.00$100.00$2,000.00$146.50$2,930.00$19.00$380.00
25Temporary Trail Closure1LS$30,000.00$30,000.00$50,000.00$50,000.00$8,450.00$8,450.00$114,258.00$114,258.00
TOTAL PRICE$1,540,980.00$2,773,205.00$2,866,800.02$4,627,739.00$0.00
I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Signature:No Bid Guarantee, Past Performance or Technical Approach information provided.