Amendment 0003 - J.12 GRDO Statement of Work.pdf

PDF 2 MB Posted

Attached to
Monongahela National Forest Electrical Improvements Project Federal contract opportunity
Solicitation number
12445523Q0014
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Monongahela National Forest Electrical Improvements Project, newest first.
File Type Posted
Amendment 0003 - J.15 GRDO Specifications.pdf PDF
Amendment 0003 - J.14 GRDO Project Plans.pdf PDF
Amendment 0003 - J.2 MRDW Statement of Work.pdf PDF
Amendment 0003 - J.9 GRDW Project Plans.pdf PDF
Amendment 0003 - J.5 MRDW Project Specifications.pdf PDF
Amendment 0003 - J.7 GRDW Statement of Work.pdf PDF
Amendment 0003 - J.4 MRDW Project Plans.pdf PDF
Amendment 0003 - SF30 - Please sign and return with quote package.pdf PDF
Amendment 0003 - Additional Questions and Answers Document.pdf PDF
Amendment 0003 - J.10 GRDW Specifications.pdf PDF
Amendment 0003 - RFQ_12445523Q0014 Revised.pdf PDF
Amendment 0002 SF30 - Sign and return.pdf PDF
Amendment 0001 SF30 - Sign and return.pdf PDF
Amendment 0001 J.12 GRDO Statement of Work Updated 2.14.23.pdf PDF
Amendment 0001 J.2 MRDW Statement of Work Updated 2.14.23.pdf PDF
Amendment 0001 J.4 MRDW Project Plans Updated 2.14.23.pdf PDF
Amendment 0001 J.5 MRDW Project Specifications Updated 2.14.23.pdf PDF
Amendment 0001 J.7 GRDW Statement of Work Updated 2.14.23.pdf PDF
Amendment 0001 J.9 GRDW Project Plans Updated 2.14.23.pdf PDF
Amendment 0001 Monongahela NF Electrical Improvements Project -Q and A Document.pdf PDF
Amendment 0001 J.10 GRDW Project Specifications Updated 2.14.23.pdf PDF
Amendment 0001 J.15 GRDO Project Specifications Updated 2.14.23.pdf PDF
J.11 DBA WD WV0021 - Nicholas County.pdf PDF
J.14 GRDO Project Plans.pdf PDF
J.2 MRDW Statement of Work.pdf PDF
J.4 MRDW Project Plans.pdf PDF
J.13 GRDO Project Maps.pdf PDF
J.12 GRDO Statement of Work.pdf PDF
J.10 GRDW Project Specifications.pdf PDF
J.7 GRDW Statement of Work.pdf PDF
J.9 GRDW Project Plans.pdf PDF
J.8 GRDW Project Maps.pdf PDF
J.6 DBA WD-WV0022 Pocahontas County.pdf PDF
J.3 MRDW Project Maps.pdf PDF
J.1 DBA WD WV0022 - Poncahontas County.pdf PDF
J.5 MRDW Project Specifications.pdf PDF
J.15 GRDO Project Specifications.pdf PDF
RFQ_12445523Q0014.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work Revised 03/08/23

Project Gauley Ranger Station Electrical Improvements

General Information

1.0 Scope of Work

The contractor shall provide the following under this contract:

• All work must comply with contract plans and specifications.

• The contractor shall supply all materials and labor to install the outlets and complete all work described in the contract documents and any incidental work.

• Base Bid:

o Mobilize o Provide and install 21 new duplex power outlets including adding circuits as necessary.

o Replace a GFCI Circuit Breaker in the warehouse.

• Optional Items:

o Provide and install a 30amp circuit with a L5-30R outlet in the location indicated on the plans.

o Provide and install 2 double CAT6 data ports with corresponding CAT6 homeruns, raceways, appropriate grounding installations, and other items as necessary to comply with contract documents. Provide and Install 6 wireless access point hookups with corresponding CAT6a homeruns, raceways, grounding installations and other items as necessary to comply with contract documents.

Provide and install 1-48 port patch panel meeting contract specifications at the existing data rack. The patch panel shall be Leviton 49255-L48 or approved equal. CAT6a and CAT6 individual ports shall be installed in this panel as applicable.

• An existing 12 port patch panel may have to be moved to allow for space in the existing rack.

If so, all terminations from that panel shall be moved to the new 48 port panel.

See Section 270000 Part 3.07 of the specifications for the definition of wireless access point hookups.

Locations shall be approved by the COR.

o Provide and install a Telecommunications Main Grounding Busbar in the Data Room.

o Provide and install a surge protective device (SPD) at the panel with new circuits installed. See specification

Section 264313 for product and installation details.

General Information:

• There is access to the data rack and subpanel as show on the plans. There is access to electrical panels in the utility closet.

• The wires for the outlets and data ports shall be ran in the crawlspace, walls, or attic space.

• The wires for the wireless access point hookups shall be run in the attic and terminate in the drop ceiling.

• Installation of conduit, wire, and any other work to electrify the outlets, provide data to the ports, and provide data to the wireless access point hookups shall be incidental to the installation of the electrical outlets and data ports.

• All work shall comply with the NEC.

• All work shall be installed and tested in accordance with project plans and specifications.

• Contractor shall not purchase or install any new data switches.

• The contractor shall coordinate moving the furniture with the government COR and site manager. The contractor is responsible for moving furniture as necessary for the work.

2.0 Background

The Gauley Ranger District Office on the Monongahela National Forest is in Richwood, WV. The building was built in 1991 and needs electrical upgrades.

Contractor Requirements

3.0 Technical Requirements / Tasks

Contractor shall be a licensed electrician in the state of West Virginia and shall be insured. Contractor shall have experience with electrical renovation projects, installing electrical system/components in reduced working environments such as crawl spaces.

4.0 Government Furnished

Government shall furnish access to the facility during normal working hours. 8:00AM – 4:30 PM Monday through Friday (unless otherwise approved by COR), excluding Federal Holidays.

5.0 Deliverables / Schedule

Key Deliverables

Item No. Deliverable Objective Due 0001 Mobilization Mobilize to the site. -

0002 Power Outlets Provide and install 21 single gang duplex electrical outlets. Work also includes running of electrical wire, installation of new breakers/circuits as necessary, testing of circuits/outlets, administrative items, and any incidentals.

Period of Performance End Date

0003 Replace faulty GFCI Breaker in Shop

Replace GFCI Breaker. Period of Performance End Date

Option Item 30A Circuit/Outlet - Option A

Add 30 Amp circuit to existing sub-panel, with L5- 30R wall outlet as shown on plans.

Period of Performance End Date

Option Item Provide and Install Wireless Access Points, CAT6 Double Data Ports - Option B

Provide and Install Wireless Access Points, CAT6a Patch Ports, CAT6 Double Data Port WAOs, Associated Cable, Raceways, Boxes, etc to make operational.

Period of Performance End Date

Option Item Telecommunications Main Grounding Busbar - Option C Provide and Install Telecommunications Main

Grounding Busbar Period of Performance End Date

Option Item Provide Patch Cables for WAOs and Patch Panels - Option D

Provide and install patch cables for each of the ports for each WAO and patch cables for each of the patch panel ports with homerun terminations.

Period of Performance End Date

Option Item Surge Protective Device in Panel with New Circuits - Option E

Provide and install a surge protective device (SPD) at the panel with new circuits installed. See specification Section 264313 for product and installation details.

Period of Performance End Date

Attachment See Attached Photos.

Figure 1: Conduit feeds from panel, view from crawl space

Figure 2: View of Crawl Space

Figure 3: Existing Sub-Panel B

Figure 4: Breaker Panel A

Figure 5: Crawl Space Access Door (All 3 access points are similar)

Figure 6: Warehouse Breaker Panel, Replace 20A GFCI Breaker #15

Figure 7: Warehouse Breaker Panel Diagram

Project
General Information
Contractor Requirements