C04b New SOW 1240LT26Q0109 102026.docx
DOCX document 29 KB Posted
- Solicitation number
- 1240LT26Q0109
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the USDA Forest Service Region 4 Buckboard Marina Water System Improvements project located at Flaming Gorge National Recreation Area in Sweetwater County, Wyoming, approximately 24 miles north of Manila, Utah. The base contract work involves reconstruction of the raw water intake system and related infrastructure, including directional drilling of a new intake casing pipe, installation of a cofferdam, submersible pump and intake pipe, new intake pumphouse with booster pump, raw water pipeline to the treatment plant, raw water storage tank, irrigation booster pump and pipeline, overhead power supply, native-surface access road, SCADA system for pump operations, and design/build of electrical and communications systems. The contract start date is November 2026 with a base contract duration of 120 calendar days.
The SOW identifies five optional work packages that may be awarded: Option #1 (Underground Storage Tanks, 30 days) includes installation of five underground finish water storage tanks and associated infrastructure; Option #2 (Looped Water Distribution System, 30 days) involves replacement of water distribution portions, air release valves, fire hydrant installation, and asphalt repairs; Option #3 (Water Meters) is included with Option #2; Option #4 (Upgrade Treatment Plant, 30 days) requires removal of existing 20 GPM treatment plant and installation of new 40 GPM unit; and Option #5 (Waterline Extension, 15 days) for future dock location. The contractor is responsible for stream protection planning, equipment pressure washing to prevent noxious weed transportation, coordination of temporary power, provision of temporary toilet facilities, traffic control conforming to MUTCD standards, and maintaining public water system operations during construction. Planned reservoir elevation is 5990 feet or less from April through November 2027, with design assumptions for structural temporary work at 6010 feet elevation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04f New SOI 1240LT26Q0109 102026.xlsx | XLSX spreadsheet | |
| C04c New Specs 1240LT26Q0109 102026.docx | DOCX document | |
| C04a RFI QA 1240LT26Q0109 102026.docx | DOCX document | |
| C04 SF30 1240LT26Q0109-0003.pdf | ||
| C04d Measurement PYMT Sup 1240LT26Q0109 102026.docx | DOCX document | |
| C04e Measurement PYMT Spec 1240LT26Q0109 102026.pdf | ||
| C04g Options Supplement 1240LT26Q0109 102026.pdf | ||
| C05a Site Visit 1240LT26Q0109.pdf | ||
| C05 SF30 1240LT26Q0109-0002.pdf | ||
| C05 SF30 1240LT26Q0109-0001.pdf | ||
| C04d Attachment 4 General Decision WY20260044 07302026.pdf | ||
| C04f Attachment 6 Site Visit 1240LT26Q0109.docx | DOCX document | |
| C04b Attachment 2 Specifications 1240LT26Q0109.pdf | ||
| C04c Attachment 3 Plans 1240LT26Q0109.pdf | ||
| C04e Attachment 5 RFI Form 1240LT26Q0109.docx | DOCX document | |
| C04a Attachment 1 SOI 1240LT26Q0109.xlsx | XLSX spreadsheet | |
| C04 SF1442 1240LT26Q0109.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA FOREST SERVICE, R-4
BUCKBOARD MARINA WATER SYSTEM IMPROVEMENTS
SECTION 01 00 10 – STATEMENT OF WORK AND GENERAL CONDITIONS
PART 1 - GENERAL
1.1 SCOPE OF CONTRACT
A. This project is for reconstruction of the raw water intake and various portions of the Buckboard Marina public water system at the Flaming Gorge National Recreation Area.
B. The base work, New Raw Water Intake and Irrigation, includes:
1. Directional drilling of a new intake casing pipe into the reservoir,
2. Installation and removal of a cofferdam to construct the intake below water level,
3. Installation of new submersible pump and intake pipe within the intake casing
4. Installation of a new intake pumphouse with booster pump and associated controls and plumbing infrastructure,
5. New raw water pipeline to the existing water treatment plant, including associated valves, drains, and combination air valve,
6. New raw water storage tank and in-line pump to the water treatment plant,
7. New irrigation booster pump and pipeline to connection to existing irrigation system,
8. New overhead power supply to the intake pumphouse,
9. New native-surface access road to the intake pumphouse,
10. New SCADA system for pump operations, and
11. Design/build of the electrical and communications systems.
C. Optional work that may be awarded includes all work described above associated with:
1. Option #1 – Underground Storage Tanks:
Installation of 5 underground finish water storage tanks, New in-line booster pump to distribution system, and Associated drainage and domestic water piping, valve, and drains.
2. Option #2 – Looped Water Distribution System:
Replacement of a portion of the water distribution including associated valves, drains, and service connections, Installation of combination air release valves, Installation of fire hydrant, and Asphalt pavement repairs.
3. Option #3 – Water Meters:
Installation of water meters and boxes at various points on the distributions system or at service connections.
4. Option #4 – Upgrade Treatment Plant:
Removal and disposal of an existing 20 GPM package water treatment plant within an existing CMU building to remain, Design and construction of a new 40 GPM package water treatment plant within an existing CMU building, and Installation of associated plumbing, electrical, and SCADA for a complete operational unit.
5. Option #5 – Waterline Extension to Future Dock Location:
Installation of new waterline including associated valves and drains.
D. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located on the Flaming Gorge Ranger District of the Ashley National Forest, Sweetwater County, Wyoming, in Section 29, T 15 N, R 108 W. It is located approximately 24 miles North of Manila, Utah. The project may be accessed from State Highway 530 and Forest Road 009.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. With some exceptions, construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.
Exceptions will be Forest Road 009 to and including the Marina parking area and boat ramp; and the store, housing, and RV park owned and operated under permit.
2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.
3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
Pick and edit the following items to fit the project.
4. Reservoir water is available at the site for construction purposes subject to approval by the Bureau of Reclamation and local authorities.
5. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
6. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
7. The existing water system, or parts of the system as appropriate for options selected, are to remain active to the extent possible until final tie-in to services or downstream infrastructure is complete. No portion of the public water supply is to be connected to the new work until the new work has been tested and approved for drinking water use.
8. Planned Outages: With the exception of the package water treatment plant, the Contracting Officer shall be notified 7 days in advance of any planned outages and only after all affected customers have been notified at least 48 hours in advance. Outages shall be limited to 24 hours.
Outage for the package treatment plant is limited to 15 days and all affected customers are to be notified 14 days in advance.
9. Planned reservoir elevation: The planned reservoir elevation is 5990’ or less during the expected work period of April through November, 2027, according to the Bureau of Reclamation. Payment for construction of the cofferdam and underwater work assumes this elevation. However, design of any structural temporary work should assume an elevation of 6010’. Should the water level exceed 5990’, additional payment will be considered for additional height of cofferdam. No additional payment will be made for reconstruction of cofferdam foundations or other structural elements to support additional wall height up to 6010’.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Wyoming Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.
B. No overnight camping will be allowed on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. November, 2026.
1.8 CONTRACT TIME
A. Base Bid: 120 Calendar Days B. Option #1: 30 Calendar Days C. Option #2: 30 Calendar Days D. Option #3: Included with Option #2.
E. Option #4: 30 Calendar Days F. Option #5: 15 Calendar Days
REVISION HISTORY:
| 2/2/2010 | D. Wewer: Added state options for departments of transportation. |
| 2/18/2014 | D. Wewer: Removed reference to “015000 Temporary Facilities” regarding temporary porta potties. This section does not exist in the R4 standards at this time. |
END OF SECTION C