This document is an amendment to a solicitation providing responses to contractor questions and revising specifications. The solicitation is for construction of a new storage building for the US Forest Service Sisters Ranger District in Oregon. The amendment responds to contractor questions on interior wall heights, use of waterguard trim, and specifications for 4-inch CMU veneer. It also confirms old equipment will be removed and provides an itemized list and photos of equipment to be removed and hauled off by the contractor. The proposal due date for the solicitation remains July 7, 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 5.pdf | ||
| Amend4 - Equipment Removal List for Sisters Ranger District.pdf | ||
| Amend3 - 07 25 00-RIB-Weather Barriers-06-20-2022.pdf | ||
| Amendment 3.pdf | ||
| Amendment 2.pdf | ||
| Amend2 - P002 - SCHEDULES - PLUMBING.pdf | ||
| Amendment 1.pdf | ||
| Amend1 - E100 - SITE PLAN - ELECTRICAL.pdf | ||
| Amend1 - T100 - SITE PLAN - TECHNOLOGY.pdf | ||
| Amend1 - C3.1.Util Plan PH I.pdf | ||
| Amend1 - Exhibit 01.pdf | ||
| Amend1 - E501 - SINGLE LINE DIAGRAMS - ELECTRICAL.pdf | ||
| Specifications.pdf | ||
| Drawings.pdf | ||
| CompleteSolicitation.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240BH22R0014
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40BH
PORTLAND OR 97204-2829
STE 310
1220 SW 3RD AVE
USDA-FS CSA NORTHWEST 6
06/28/20220004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/18/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See attached.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
DARCY J. RAPOZA
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
/s/ Darcy J. Rapoza 28 June 2022
Amendment 4 to RFP 1240BH22R0014
This Amendment provides the following information:
• Provides responses to all unanswered RFI’s received to date
No RFI’s will be accepted beyond COB Wednesday 6/29/2022.
The proposal due date remains 7/7/2022.
RFI’s
RFI-050
Drywall subcontractor is looking for confirmation of the interior wall heights of the walls that separate the group of rooms such as showrooms, janitor rooms, etc. Those rooms have a lower ceiling height of 9' and unsure if the intent is still to run the framing to 16' to underside if trusses.
Response: Framing and Drywall will go to 16’ to underside of trusses.
RFI-051
Waterguard trim at base of drywall is specified but unclear to the extent of use. Can you confirm that this product is limited to the “wet areas” such as the restroom/shower rooms, laundry room, janitor room and mechanical room?
Response: Waterguard is only to be used in rooms that have wet areas Is waterguard also to be used at backerboard locations as well?
Response: It is not necessary at the areas that have backerboard in the open shop area
RFI-052
Please clarify the color, texture and manufacturer of the 4” CMU Veneer;
Response:
The revised basis of design for the 4” CMU Veneer shall be:
Manufacturer: Willamette Greystone Texture: Split Face Color: Natural 211, Pewter 234, or Midnight 225. Physical samples will be required for review and color selection.
RFI-053
During the pre-proposal site visit on 6/1/2022, USFS indicated a desire to have some “old equipment” removed by the contractor and that USFS would provide an itemized list of that equipment. Please confirm if Gov’t equipment is to be removed by the Contractor under this contract, and could you provide a list the exact equipment to be removed/hauled off by contractor.
Response: Confirmed, old equipment shall be removed as part of this contract. See attached itemized list with photos.