121021 OR AMENDED BID TAB FINAL.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
1.5" Crusher Run Rock and Optional Rock Aggregate Materials
Solicitation number
121021 OR
Issued by
Douglas County, Nebraska

About this file

The document is a bid tabulation (bid tab) spreadsheet for the Nebraska Department of Transportation (NDOT), detailing pricing from six vendors for rock aggregate materials across multiple districts. The solicitation covers 1.5" Crusher Run Rock, with optional materials including 3/8" Washed Rock, 1" Crusher Run Rock, and Crushed Rock for Surfacing Aggregate. The procurement encompasses approximately 16,500 tons of materials to be delivered to various NDOT maintenance yards and roadside locations across different districts, including sites in Greenwood, Superior Street, Wahoo, David City, and other Nebraska locations. The bid opening is scheduled for February 21, 2025, with delivery requirements of 14-21 business days after order receipt, between 8:00 AM and 4:00 PM Monday through Friday, excluding state holidays.

The bid tab reveals unit pricing from six vendors: Armstrong Rentals, LLC; CenCon of KANSAS LLC; Gana Trucking & Excavating; Jeffres Sand and Gravel Inc; Koch Excavating Co, Inc.; and Wessels Trucking. Pricing varies by location and material type, ranging from approximately $29.80 to $88.60 per ton. The total bid values for the six vendors range from $577,935 to $693,884. The contract will have an initial one-year term with potential extension options, and pricing is to remain firm for 180 days from the award date. Vendors are required to provide certified weight tickets for each load, with pricing inclusive of all transportation costs. The State reserves the right to reject any bids and is not obligated to a minimum order quantity, with the potential to contract with multiple sources if deemed necessary.

View the file

Other files

File Type Posted
121021 OR Armstrong.pdf PDF
121021 SOLICITATION ADDENDUM ONE.docx DOCX document
121021 OR ITB Crushed Rock 1-15-25 bms.docx DOCX document
121021 OR Westover Rock and Sand.pdf PDF
121021 OR Jeffres.pdf PDF
121021 OR Attachment A Cost Sheet 1-15-25 bms.docx DOCX document
121021 OR BID TAB FINAL.xlsx XLSX spreadsheet
121021 OR AWARDED BID TAB FINAL Crushed Rock.xlsx XLSX spreadsheet
121021 OR ITB Gana Tucking.pdf PDF
121021 OR Koch Excavating.pdf PDF
121021 OR CenCon of Kansas Bid.pdf PDF
SOLICITATION ADDENDUM Three.docx DOCX document
121021 OR WESSELS Crushed Rock.pdf PDF
Intent to award.docx DOCX document
121021 OR AMENDED BID TAB FINAL.xlsx XLSX spreadsheet
121021 OR Armstrong.pdf PDF
121021 OR CenCon of Kansas Bid.pdf PDF
121021 OR Koch Excavating.pdf PDF
121021 OR ITB Crushed Rock 1-15-25 bms.docx DOCX document
SOLICITATION ADDENDUM Three.docx DOCX document
121021 OR AWARDED BID TAB FINAL Crushed Rock.xlsx XLSX spreadsheet
121021 SOLICITATION ADDENDUM ONE.docx DOCX document
121021 OR Attachment A Cost Sheet 1-15-25 bms.docx DOCX document
121021 OR Westover Rock and Sand.pdf PDF
Intent to award.docx DOCX document
121021 OR Jeffres.pdf PDF
121021 OR BID TAB FINAL.xlsx XLSX spreadsheet
121021 OR ITB Gana Tucking.pdf PDF
121021 OR AMENDED BID TAB FINAL.xlsx XLSX spreadsheet
121021 OR Attachment A Cost Sheet 1-15-25 bms.docx DOCX document
121021 OR BID TAB FINAL.xlsx XLSX spreadsheet
SOLICITATION ADDENDUM Three.docx DOCX document
121021 OR ITB Crushed Rock 1-15-25 bms.docx DOCX document
121021 SOLICITATION ADDENDUM ONE.docx DOCX document
121021 SOLICITATION ADDENDUM ONE.docx DOCX document
121021 OR ITB Crushed Rock 1-15-25 bms.docx DOCX document
121021 OR Attachment A Cost Sheet 1-15-25 bms.docx DOCX document
121021 OR Attachment A Cost Sheet 1-15-25 bms.docx DOCX document
121021 OR ITB Crushed Rock 1-15-25 bms.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

1.5" CRUSHER RUN ROCK AND OPTIONAL 3/8 " WASHED, 1" CRUSHER RUN ROCK AND CRUSHED ROCK FOR SURFACING AGGREGATEArmstrong Rentals, LLCCenCon of KANSAS LLCGana Trucking & ExcavatingJeffres Sand and Gravel IncKoch Excavating Co, Inc.Wessels TruckingWestover Rock & Sand, Inc.
DescriptionQtyUOMUNIT PRICEEXTENDED PRICEUNIT PRICEEXTENDED PRICEUNIT PRICEEXTENDED PRICEUNIT PRICEEXTENDED PRICEUNIT PRICEEXTENDED PRICEUNIT PRICEEXTENDED
PRICEUNIT PRICEEXTENDED PRICE
11-1/2" CRUSHER RUN ROCK - D1
GREENWOOD YARD500TN$ 30.55$ 15,275.00$ 32.57$ 16,285.00$ 31.25$ 15,625.00$ 36.65$ 18,325.00$ 30.90$ 15,450.00$ 29.80$ 14,900.00
21-1/2" CRUSHER RUN ROCK - D1
SUPERIOR STREET YARD300TN$ 33.15$ 9,945.00$ 35.63$ 10,689.00$ 32.85$ 9,855.00$ 40.45$ 12,135.00$ 34.60$ 10,380.00$ 34.40$ 10,320.00
31-1/2" CRUSHER RUN ROCK - D1
WAHOO YARD300TN$ 34.15$ 10,245.00$ 37.08$ 11,124.00$ 34.25$ 10,275.00$ 39.65$ 11,895.00$ 36.65$ 10,995.00$ 35.35$ 10,605.00
41-1/2" CRUSHER RUN ROCK - D1
DAVID CITY YARD300TN$ 37.93$ 11,379.00$ 41.90$ 12,570.00$ 37.20$ 11,160.00$ 43.43$ 13,029.00$ 41.65$ 12,495.00$ 38.95$ 11,685.00
51-1/2" CRUSHER RUN ROCK - D1

HWY 136

MM 172 2.5 MI South West of BEATRICE1500TN$ 36.10$ 54,150.00$ 41.26$ 61,890.00$ 38.45$ 57,675.00$ 29.75$ 44,625.00$ 40.65$ 60,975.00$ 36.00$ 54,000.00
61-1/2" CRUSHER RUN ROCK - D1

HWY 50, MM14

NORTH SIDE OF PAWNEE CITY2000TN$ 34.65$ 69,300.00$ 41.26$ 82,520.00$ 35.85$ 71,700.00$ 32.20$ 64,400.00$ 36.65$ 73,300.00$ 34.50$ 69,000.00
71-1/2" CRUSHER RUN ROCK - D1
HWY 33, 0.5 MI EAST OF DORCHESTER500TN$ 36.00$ 18,000.00$ 39.49$ 19,745.00$ 38.40$ 19,200.00$ 32.95$ 16,475.00$ 38.90$ 19,450.00$ 36.00$ 18,000.00
81-1/2" CRUSHER RUN ROCK - D1
HWY 15, MM 24 13 MI North of FAIRBURY1500TN$ 38.49$ 57,735.00$ 43.35$ 65,025.00$ 42.50$ 63,750.00$ 33.25$ 49,875.00$ 41.65$ 62,475.00$ 39.30$ 58,950.00
91-1/2" CRUSHER RUN ROCK - D1
SALT VALLEY YARD800TN$ 31.75$ 25,400.00$ 43.35$ 34,680.00$ 34.00$ 27,200.00$ 37.34$ 29,872.00$ 35.40$ 28,320.00$ 34.40$ 27,520.00
101-1/2" CRUSHER RUN ROCK - D1
NEBRASKA CITY YARD1500TN$ 30.78$ 46,170.00$ 33.37$ 50,055.00$ 31.85$ 47,775.00$ 35.00$ 52,500.00$ 33.50$ 50,250.00$ 30.75$ 46,125.00
111-1/2" CRUSHER RUN ROCK - D1
DUNBAR YARD1500TN$ 30.55$ 45,825.00$ 31.93$ 47,895.00$ 31.65$ 47,475.00$ 33.00$ 49,500.00$ 31.65$ 47,475.00$ 30.45$ 45,675.00
121-1/2" CRUSHER RUN ROCK - D1
FALLS CITY YARD1000TN$ 38.60$ 38,600.00$ 43.51$ 43,510.00$ 41.65$ 41,650.00$ 49.72$ 49,720.00$ 42.65$ 42,650.00$ 37.50$ 37,500.00
131-1/2" CRUSHER RUN ROCK - D1
HWY 136 MM 2091500TN$ 31.74$ 47,610.00$ 34.34$ 51,510.00$ 34.85$ 52,275.00$ 31.98$ 47,970.00$ 47.05$ 70,575.00$ 31.55$ 47,325.00
141-1/2" CRUSHER RUN ROCK - D1
HWY 4, MM 2041500TN$ 35.35$ 53,025.00$ 28.00$ 42,000.00$ 36.90$ 55,350.00$ 37.53$ 56,295.00$ 45.65$ 68,475.00$ 34.35$ 51,525.00
151-1/2" CRUSHER RUN ROCK - D2
FREMONT YARD100TN$ 36.65$ 3,665.00$ 38.84$ 3,884.00no bid$ 34.35$ 3,435.00$ 37.40$ 3,740.00$ 35.00$ 3,500.00
161-1/2" CRUSHER RUN ROCK - D2
BLAIR YARD100TN$ 35.15$ 3,515.00$ 37.88$ 3,788.00no bid$ 32.40$ 3,240.00$ 33.65$ 3,365.00$ 30.75$ 3,075.00
171-1/2" CRUSHER RUN ROCK - D2
108TH Street Yard, OMAHA100TN$ 34.15$ 3,415.00$ 33.70$ 3,370.00no bid$ 38.15$ 3,815.00$ 35.40$ 3,540.00$ 34.00$ 3,400.00
181-1/2" CRUSHER RUN ROCK - D2
MORMON BRIDGE YARD100TN$ 34.15$ 3,415.00$ 35.63$ 3,563.00no bid$ 32.80$ 3,280.00$ 35.15$ 3,515.00$ 31.00$ 3,100.00
191-1/2" CRUSHER RUN ROCK - D2
SOUTH OMAHA YARD100TN$ 34.15$ 3,415.00$ 34.82$ 3,482.00no bid$ 39.40$ 3,940.00$ 35.64$ 3,564.00$ 34.00$ 3,400.00
201-1/2" CRUSHER RUN ROCK - D2
MELIA HILL YARD100TN$ 32.65$ 3,265.00$ 33.37$ 3,337.00no bid$ 32.65$ 3,265.00$ 34.15$ 3,415.00$ 31.25$ 3,125.00
211-1/2" CRUSHER RUN ROCK - D2
ELKHORN YARD100TN$ 33.00$ 3,300.00$ 36.11$ 3,611.00no bid$ 39.75$ 3,975.00$ 35.65$ 3,565.00$ 34.00$ 3,400.00
221-1/2" CRUSHER RUN ROCK - D2
PLATTSMOUTH YARD100TN$ 34.00$ 3,400.00$ 34.02$ 3,402.00no bid$ 33.65$ 3,365.00$ 32.65$ 3,265.00$ 33.00$ 3,300.00
231-1/2" CRUSHER RUN ROCK - D7
HWY N-23, MM 13, NEAR GRANT1000TN$ 88.60$ 88,600.00$ 76.95$ 76,950.00No Bid$ 80.085$ 80,085.00$ 83.61$ 83,610.00$ 92.65$ 92,650.00$ 75.95$ 75,950.00
ALTERNATE OPTIONAL LOCATIONS AND MATERIALS
243/8" WASHED CRUSHED ROCK - D1

ALTERNATE OPTIONAL LOCATIONS

1400 HICKMAN ROAD

ROCO, NE 6843025TN$ 45.40$ 45.64$ 0.22$ 53.19$ 46.90
251.0" CURSHER RUN ROCK -D1

ALTERNATE OPTIONAL LOCATIONS

1400 HICKMAN ROAD

ROCO, NE 6843025TN$ 32.65$ 35.79$ 0.22$ 42.41$ 36.15
261.5" CURSHER RUN ROCK -D1

ALTERNATE OPTIONAL LOCATIONS

1400 HICKMAN ROAD

ROCO, NE 6843025TN$ 32.65$ 35.79$ 0.22$ 42.41$ 36.15
27CRUSHED ROCK - SURFACING -D1

ALTERNATE OPTIONAL LOCATIONS

1400 HICKMAN ROAD

ROCO, NE 6843025TN$ 32.65$ 35.79$ 0.22$ 42.41$ 36.15
283/8" WASHED CRUSHED ROCK - D2

ALTERNATE OPTIONAL LOCATIONS

4425 S. 108TH STREET

OMAHA, NE 6813725TN$ 43.40$ 44.45$ 0.22$ 45.93$ 46.15
291.0" CRUSHER RUN ROCK - D2

ALTERNATE OPTIONAL LOCATIONS

4425 S. 108TH STREET

OMAHA, NE 6813725TN$ 31.65$ 33.70$ 0.22$ 35.65$ 35.40
301.5" CRUSHER RUN ROCK - D2

ALTERNATE OPTIONAL LOCATIONS

4425 S. 108TH STREET

OMAHA, NE 6813725TN$ 31.65$ 33.70$ 0.22$ 35.65$ 35.40
31CRUSHED ROCK - SURFACING - D2

ALTERNATE OPTIONAL LOCATIONS

4425 S. 108TH STREET

OMAHA, NE 6813725TN$ 31.66$ 33.70$ 0.22$ 35.65$ 35.40
323/8" WASHED CRUSHED ROCK - D3

ALTERNATE OPTIONAL LOCATIONS

HWY 32, MM 33.27

1 MI WEST OF MADISON25TN$ 61.55No Bid$ 0.19$ 58.73$ 64.15
331.0" CRUSHER RUN ROCK - D3

ALTERNATE OPTIONAL LOCATIONS

HWY 32, MM 33.27

1 MI WEST OF MADISON25TN$ 49.80No Bid$ 0.19$ 47.98$ 53.40
341.5" CRUSHER RUN ROCK - D3

ALTERNATE OPTIONAL LOCATIONS

HWY 32, MM 33.27

1 MI WEST OF MADISON25TN$ 49.80No Bid$ 0.19$ 47.98$ 53.40
35CRUSHED ROCK- SURFACING - D3

ALTERNATE OPTIONAL LOCATIONS

HWY 32, MM 33.27

1 MI WEST OF MADISON25TN$ 49.80No Bid$ 0.19$ 47.98$ 53.40
363/8" WASHED CRUSHED ROCK - D4

ALTERNATE OPTIONAL LOCATIONS

I-80/L40C ALDA INTERCHANGE

NORTHEAST CORNER25TN$ 64.55$ 62.95No Bid$ 0.19$ 62.05$ 64.40
371.0" CRUSHER RUN ROCK - D4

ALTERNATE OPTIONAL LOCATIONS

I-80/L40C ALDA INTERCHANGE

NORTHEAST CORNER25TN$ 53.80$ 58.95No Bid$ 0.19$ 51.30$ 53.65
381.5" CRUSHER RUN ROCK - D4

ALTERNATE OPTIONAL LOCATIONS

I-80/L40C ALDA INTERCHANGE

NORTHEAST CORNER25TN$ 53.80$ 58.95No Bid$ 0.19$ 51.30$ 53.65
39CRUSHED ROCK-SURFACING - D4

ALTERNATE OPTIONAL LOCATIONS

I-80/L40C ALDA INTERCHANGE

NORTHEAST CORNER25TN$ 53.80$ 58.95No Bid$ 0.19$ 51.30$ 53.65
403/8" WASHED CRUSHED ROCK - D5

ALTERNATE OPTIONAL LOCATIONS

140375 RUNDELL ROAD

GERING, NE 6934125TNNo bidNo Bid$ 0.18$ 114.52$ 103.15
411.0" CRUSHER RUN ROCK - D5

ALTERNATE OPTIONAL LOCATIONS

140375 RUNDELL ROAD

GERING, NE 6934125TNNo BidNo Bid$ 0.18$ 103.77$ 92.40
421.5" CRUSHER RUN ROCK - D5

ALTERNATE OPTIONAL LOCATIONS

140375 RUNDELL ROAD

GERING, NE 6934125TNNo BidNo Bid$ 0.18$ 103.77$ 92.40
43CRUSHED ROCK - SURFACING - D5

ALTERNATE OPTIONAL LOCATIONS

140375 RUNDELL ROAD

GERING, NE 6934125TNNo BidNo Bid$ 0.18$ 103.77$ 92.40
443/8" WASHED CRUSHED ROCK- D6

ALTERNATE OPTIONAL LOCATIONS

123 LAKE AVE, PO BOX 394

GOTHENBURG, NE 6913825TN$ 79.40$ 60.95No Bid$ 0.18$ 81.05$ 84.40
451.0 CRUSHER RUN ROCK - D6

ALTERNATE OPTIONAL LOCATIONS

123 LAKE AVE, PO BOX 394

GOTHENBURG, NE 6913825TN$ 67.65$ 56.95No Bid$ 0.18$ 70.31$ 73.65
461.5 CRUSHER RUN ROCK - D6

ALTERNATE OPTIONAL LOCATIONS

123 LAKE AVE, PO BOX 394

GOTHENBURG, NE 6913825TN$ 67.65$ 56.95No Bid$ 0.18$ 70.31$ 73.65
47CRUSHED ROCK - SURFACING - D6

ALTERNATE OPTIONAL LOCATIONS

123 LAKE AVE, PO BOX 394

GOTHENBURG, NE 6913825TN$ 67.65$ 56.95No Bid$ 0.18$ 70.31$ 73.65
483/8" WASHED CRUSHED ROCK - D7

ALTERNATE OPTIONAL LOCATIONS

38764 US HIGHWAY 6

2 MI EAST OF MCCOOK25TN$ 84.49$ 64.75No Bid$ 0.18$ 86.52$ 91.00
491.0" CRUSHER RUN ROCK - D7

ALTERNATE OPTIONAL LOCATIONS

38764 US HIGHWAY 6

2 MI EAST OF MCCOOK25TN$ 72.74$ 60.75No Bid$ 0.18$ 75.77$ 80.25
501.5" CRUSHER RUN ROCK - D7

ALTERNATE OPTIONAL LOCATIONS

38764 US HIGHWAY 6

2 MI EAST OF MCCOOK25TN$ 72.74$ 60.75No Bid$ 0.18$ 75.77$ 80.25
51CRUSHED ROCK - SURFACING - D7

ALTERNATE OPTIONAL LOCATIONS

38764 US HIGHWAY 6

2 MI EAST OF MCCOOK25TN$ 72.74$ 60.75No Bid$ 0.18$ 75.77$ 80.25
523/8" WASHED CRUSHED ROCK - D8

ALTERNATE OPTIONAL LOCATIONS

HWY 12, MM 80.6

SPRING VIEW, NE 6877825TN$ 94.00No Bid$ 0.18$ 85.80$ 96.40
531.0" CRUSHER RUN ROCK - D8

ALTERNATE OPTIONAL LOCATIONS

HWY 12, MM 80.6

SPRING VIEW, NE 6877825TN$ 82.00No Bid$ 0.18$ 75.05$ 85.65
541.5" CRUSHER RUN ROCK - D8

ALTERNATE OPTIONAL LOCATIONS

HWY 12, MM 80.6

SPRING VIEW, NE 6877825TN$ 82.00No Bid$ 0.18$ 75.05$ 85.65
55CRUSHED ROCK - SURFACING - D8

ALTERNATE OPTIONAL LOCATIONS

HWY 12, MM 80.6

SPRING VIEW, NE 6877825TN$ 82.00No Bid$ 0.18$ 75.05$ 85.65
TOTAL$ 618,649.00$ 76,950.00$ 577,935.00$ 611,050.00$ 628,541.00$ 693,884.00$ 605,380.00
Payment Terms
Delivery Days ARO
**BID TAB UUPDATED VENDOR WESSELS LEFT OFF ORIGINAL BID TAB**

PROCUREMENT CONTRACTS OFFICER

BRENDA SENSIBAUGH 121021 OR AMENDED BID TAB

&9 1.5" CRUSHER RUNN ROCK AND OPTIONAL 3/8 " WASHED, 1" CRUSHER RUN ROCK AND CURSHED ROCK FOR SURFACING AGGREGATE &10

NDOT OPENING DATE: FEBRUARY 21, 2025

Page &P of &N