12-UPS Pre-Installation Project Scope Validation Form Exhibit.pdf
PDF 729 KB Posted
- Attached to
- Uninterruptible Power Supply
- Solicitation number
- JV-250437
- Issued by
- Dallas County, Texas
About this file
Summary
This is a UPS Pre-Installation Project Scope Validation Form used by Dallas Independent School District's Educational Technology Project Management team to document vendor field surveys of network closets prior to UPS installation. The form serves as a controlled project record that validates existing UPS conditions, electrical readiness, plug compatibility, equipment placement, power redistribution requirements, and telecommunications grounding conditions to support Phase 2 solution design and quotation. The vendor is required to complete one report per campus or site, identifying all surveyed Main Distribution Frame (MDF), Intermediate Distribution Frame (IDF), and other designated network closets. The validation process categorizes findings as PASS, PASS WITH EXCEPTION, FAIL/HOLD, or NOT APPLICABLE, with mandatory submission of completed campus/site summaries, closet-by-closet validation sheets, existing UPS inventory and disposition schedules, receptacle and circuit schedules, load and power redistribution analyses, grounding and bonding inspection logs, photo logs, deficiency and exception registers, and recommended Phase 2 power solutions. No material procurement, purchase order processing, logistics mobilization, or installation shall proceed until identified deficiencies and design exceptions have been reviewed and approved in writing by the District's Educational Technology Project Management team.
The form establishes a structured gating process for UPS deployment with vendor certification requirements and District approval checkpoints at sections 12.1 and 12.2. Deficiencies are categorized by severity level (Critical, High, Medium, Low) with corresponding work gates that determine whether quotation, procurement, or installation can proceed. The District's three-year UPS supply agreement with two successive one-year renewal options (not to exceed five years total) requires written notice of non-renewal ninety days prior to expiration. Site constraints including restricted access, after-hours work requirements, stairs or elevator limitations, loading constraints, hazardous work areas, insufficient staging space, and temperature or ventilation concerns must be documented with operational impact assessments and required coordination or mitigation strategies. The validation form requires comprehensive photo documentation including overall closet views, rack elevations, existing UPS nameplates, receptacle and power clusters, panel and circuit identification, UPS placement areas, grounding busbars and conductors, rack bonding connections, deficiencies or exceptions, and delivery or access constraints.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DALLAS INDEPENDENT SCHOOL DISTRICT | EDUCATIONAL TECHNOLOGY PROJECT MANAGEMENT
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 1
UPS PRE-INSTALLATION
PROJECT SCOPE VALIDATION REPORT
Vendor Field Survey and District Approval Form
Project / Program Report No.
Campus / Site Building
Vendor Survey Date
Prepared By Report Version
District PM Submission Date
DOCUMENT PURPOSE
This form documents the vendor’s exhaustive pre-installation survey of designated network closets before logistics mobilization. It validates existing UPS conditions, electrical readiness, plug compatibility, equipment placement, power redistribution requirements, and telecommunications grounding conditions to support Phase 2 solution design, quotation, purchase order processing, and installation authorization.
☐ Original Submission ☐ Revised Submission ☐ Final Approved Record
No material procurement, purchase order processing, logistics mobilization, or installation shall proceed for the surveyed sector until identified deficiencies and design exceptions have been reviewed and approved in writing by the District’s EDUCATIONAL
TECHNOLOGY Project Management team.
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 2
1. Instructions and Required Submission Elements
VENDOR CERTIFICATION REQUIREMENT
The vendor shall complete one report for each campus/site and shall identify every surveyed MDF, IDF, and other designated network closet. All entries must reflect verified field conditions. Use “N/A” only when the item does not apply and provide a brief explanation.
1.1 Required Attachments
☐ Completed campus/site summary ☐ Closet-by-closet validation sheets
☐ Existing UPS inventory and disposition schedule ☐ Receptacle and circuit schedule
☐ Load and power redistribution analysis ☐ Grounding and bonding inspection log
☐ Photo log with identifiers and captions ☐ Deficiency and exception register
☐ Recommended Phase 2 power solution ☐ Vendor certification and District approval page
1.2 Status Definitions
Status Definition
PASS Condition is present, verified, and compliant with the stated project requirement.
PASS WITH EXCEPTION Work may proceed only after the documented exception and mitigation are accepted by the District.
FAIL / HOLD Condition prevents quoting, procurement, or installation until corrected and approved.
NOT APPLICABLE Item does not apply; vendor must explain the basis for this designation.
1.3 Survey Personnel and Access
Lead Surveyor Title / Qualification
Electrical Reviewer Company
District Escort Access Window
Site Contact Contact Information
1.4 Applicable Project References
Reference Document / Requirement Revision or Date Verified
1 UPS RFP / Statement of Work
2 Dallas ISD Division 27 Standards
3 District EDUCATIONAL TECHNOLOGY UPS Replacement Criteria
4 Approved UPS Equipment Profiles
5 Applicable NEC and manufacturer requirements
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 3
2. Executive Site Validation Summary
Campus / Site Total Closets Surveyed
MDF Count IDF Count
Other Closet Count Survey Completion Date
Validation Category Pass Pass w/ Exception
Fail / Hold N/A Comments / Issue IDs
Existing UPS inventory and disposition ☐ ☐ ☐ ☐
Receptacles and circuit availability ☐ ☐ ☐ ☐
Plug compatibility and cord reach ☐ ☐ ☐ ☐
Electrical capacity ☐ ☐ ☐ ☐
UPS placement and access ☐ ☐ ☐ ☐
Power redistribution ☐ ☐ ☐ ☐
Rack and busbar bonding ☐ ☐ ☐ ☐
Telecommunications grounding compliance ☐ ☐ ☐ ☐
Overall site readiness ☐ ☐ ☐ ☐
2.1 Overall Recommendation
☐ Approved to proceed to Phase 2 design and quotation
☐ Approved with documented exceptions and conditions
☐ Design review and remediation required before quotation
☐ Not ready for procurement or installation
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 4
2.2 Executive Findings and Recommended Action
Summary of Existing Conditions Recommended Phase 2 Power Setup Solution Decision / Required Action
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 5
3. Closet Survey Register
Campus / Site Building / Wing
Survey Team Date
Item Closet ID Type Floor / Location Rack Qty
Existing UPS Qty Readiness Detail Sheet
☐ MDF
☐ IDF
☐ Other
☐ Ready ☐ Exception ☐ Hold
☐ MDF
3.1 General Site Constraints
☐ Restricted access / escort required ☐ After-hours work required
☐ Stairs or elevator limitations ☐ Loading / inside-delivery constraints
☐ Hazardous or obstructed work area ☐ Insufficient staging space
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 6
☐ Temperature / ventilation concern ☐ Other condition noted below
Constraint / Location Operational Impact Required Coordination or Mitigation
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 7
4. Closet-Level Validation Sheet
Campus / Site Closet ID
Closet Type ☐ MDF ☐ IDF ☐ Other Building / Floor
Survey Date Surveyor
Rack Quantity Photo Range
4.1 Existing UPS Units Audit
UPS ID Rack / U Manufacturer / Model Serial No. VA / W Status
Age / Battery
Date Disposition Justification / Issue
ID
UPS-01
☐ Working ☐ Failed ☐ Unknown
☐ Keep ☐ Upgrade ☐ Remove
UPS-02
☐ Working
UPS-03
UPS-04
UPS-05
UPS-06
4.2 Required UPS Classification
Validation Item Yes No N/A Finding / Evidence / Required Action
Non-working UPS identified for decommissioning ☐ ☐ ☐
Installed working UPS identified for upgrade ☐ ☐ ☐
Working UPS approved to remain under current RFP SLA ☐ ☐ ☐
Model, serial number, condition, and disposition verified ☐ ☐ ☐
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 8
4.3 UPS Condition Notes
Observed Condition Evidence / Test Performed Recommendation
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 9
5. Network Load and Power Redistribution Validation
Campus / Site Closet ID
Prepared By Date
Rack Switch / Device Model Qty PSU / Feed
PoE or Connected
Load
Current
UPS
Current Distribution
Required Redistribution
Proposed UPS / Feed
R1
R2
R3
R4
R5
R6
R7
R8
5.1 Redistribution and Resiliency Checks
Validation Item Complian t Deficient N/A Comments / Issue ID
Every dependent switch is identified ☐ ☐ ☐
UPS capacity is adequate for connected equipment ☐ ☐ ☐
No UPS is overloaded ☐ ☐ ☐
Power supplies are distributed as required ☐ ☐ ☐
Single points of failure are identified ☐ ☐ ☐
Required runtime and future growth are considered ☐ ☐ ☐
Proposed distribution meets District specifications ☐ ☐ ☐
5.2 Proposed Phase 2 Power Distribution Narrative
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 10
6. Receptacle and Electrical Audit
Electrical Panel(s) Survey Date
Rec. ID Mounting / Location NEMA Type IG Dedicated Condition Cord Reach / Compatibility
RCP-01
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-02
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-03
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-04
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-05
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-06
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-07
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
RCP-08
☐ Ladder rack ☐ Back Wall Top ☐ Back wall Bottom ☐ Other
☐ L6-30R ☐ L6-20R ☐ 5-20R ☐ Other
☐ Y ☐ N ☐ Y ☐ N ☐ Good
☐ Deficient
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 11
6.1 Electrical Validation Checklist
Requirement Pass Fail N/A Verified Condition / Measurement / Issue ID
Existing receptacles match the approved UPS input requirements ☐ ☐ ☐
Required circuit pairs are available where applicable ☐ ☐ ☐
Breaker and panel circuit identification labels are verified ☐ ☐ ☐ *Vendor is required to record field observation only, not the accuracy of panel description*
Plug and receptacle configurations are compatible ☐ ☐ ☐
UPS power cord reaches without extension cords or unsafe routing ☐ ☐ ☐
Electrical capacity supports the proposed UPS load ☐ ☐ ☐
UPS placement meets access, clearance, and ventilation needs
6.2 Required Electrical Work
☐ None required ☐ New circuit
☐ Receptacle replacement ☐ Circuit relabeling
☐ Circuit capacity review ☐ Relocation / cord-routing correction
Required Work Location Responsible Trade / Party Required Before Issue ID
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 12
7. UPS Placement and Constructability
Proposed UPS Profile Survey Date
Placement Requirement Pass Fail N/A Field Measurement / Finding
Rack space and depth are adequate ☐ ☐ ☐
Four-post mounting / stabilization can be supported ☐ ☐ ☐
Floor or rack loading condition is acceptable for planned equipment ☐ ☐ ☐
Front and rear service clearances are adequate ☐ ☐ ☐
Ventilation and ambient conditions are suitable ☐ ☐ ☐
UPS and EBM arrangement permits safe service access ☐ ☐ ☐
Delivery path supports equipment dimensions and handling ☐ ☐ ☐
Placement avoids interference with cabling, ladder racks, and other systems ☐ ☐ ☐
7.1 Proposed Placement
UPS / EBM ID
Rack / U
Position or Floor Location
Clearance / Mounting Notes Photo ID Disposition
7.2 Placement Sketch or Marked-Up Rack Elevation
Attach marked-up rack elevation if additional space is required.
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 13
8. Grounding and Bonding Compliance Inspection
Inspector Inspection Date
INSPECTION LIMITATION
This section records the vendor’s required visual inspection of network closet grounding and bonding conditions. Any unsafe, inaccessible, uncertain, or structurally non-compliant condition shall be reported as a deficiency and referred to the District for review by the appropriate qualified party before installation proceeds.
Inspection Item Present Complian t Deficient N/A Evidence / Conductor / Issue ID
Telecommunications grounding busbar is present ☐ ☐ ☐ ☐
Busbar bonding conductor is visibly connected ☐ ☐ ☐ ☐
Busbar connection to building grounding matrix is verified or documented ☐ ☐ ☐ ☐
Each network rack is bonded ☐ ☐ ☐ ☐
Rack bonding conductors are intact and properly terminated ☐ ☐ ☐ ☐
Bonding path is accessible for inspection ☐ ☐ ☐ ☐
Grounding labels and identification are present where required ☐ ☐ ☐ ☐
No ungrounded racks or missing bonding conductors observed ☐ ☐ ☐ ☐
8.1 Grounding Deficiency Action
☐ No deficiency observed
☐ Correction required before quotation
☐ Correction required before installation
☐ District design review required
☐ Qualified electrical review required
Deficiency / Location Safety or Project Impact Recommended Corrective Action Issue ID
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 14
9. Deficiency, Exception, and Decision Register
Campus / Site Report No.
Vendor Revision
Issue ID Closet Category Severity Condition /
Evidence Proposed Resolution Resolution
Scope Owner
Required Date Status
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High ☐ Medium ☐ Low
☐ Open ☐ Accepted ☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 15
Issue ID Closet Category Severity Condition /
Evidence Proposed Resolution Resolution
Scope Owner
Required Date Status
DEF-
☐ UPS
☐ Electrical ☐ Grounding ☐ Placement ☐ Other
☐ Critical ☐ High
☐ Closed
9.1 Severity and Work-Gate Definitions
Severity Definition Work Gate
Critical Immediate safety, code, or infrastructure condition that prevents work. Stop. No quotation, procurement, or installation.
High Condition materially affects compliance, design, or successful installation. District review and approved resolution required.
Medium Additional scope or coordination is required but can be designed around. Document and obtain approval before affected activity.
Low Minor issue that does not prevent work when properly documented. Track through closeout or agreed corrective action.
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 16
10. Phase 2 Scope Recommendation and Cost Basis
10.1 Recommended UPS Solution by Closet
Closet ID UPS Profile / Qty
EBM /
Accessories
Legacy UPS Disposition
Electrical Work
Grounding Work
Power Redistribution Basis / Issue IDs
10.2 Scope Assumptions and Exclusions
No. Assumption / Exclusion Impact if Incorrect District Disposition
10.3 Quote Readiness Checklist
☐ All closets physically surveyed ☐ Existing UPS disposition validated
☐ UPS profiles and quantities established ☐ Electrical work identified
☐ Grounding work identified ☐ Power redistribution documented
☐ Photos and evidence attached ☐ Exceptions reviewed with District
☐ Phase 2 design basis complete ☐ Vendor quote may be prepared
10.4 Recommended Next Step
☐ Proceed to vendor quotation
☐ Proceed after listed corrections
☐ Return for design clarification
☐ Return for additional survey
☐ Hold pending District decision
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 17
11. Photo and Evidence Log
Campus / Site Report No.
Vendor Survey Date
Photo ID Closet / Location Subject Description and Relevance Related Issue
ID File Name
P-001
P-002
P-003
P-004
P-005
P-006
P-007
P-008
P-009
P-010
P-011
P-012
11.1 Minimum Photo Coverage Confirmation
☐ Overall closet view ☐ Each rack elevation
☐ Each existing UPS and nameplate ☐ Each receptacle / power cluster
☐ Panel and circuit identification where accessible ☐ UPS placement area
☐ Grounding busbar and conductor ☐ Each rack bonding connection
☐ Each deficiency or exception ☐ Delivery / access constraint
UPS Pre-Installation Project Scope Validation Form | Controlled Project Record | Page 18
12. Vendor Certification and District Approval
12.1 Vendor Certification
I certify that the vendor physically surveyed the site and designated network closets identified in this report; that the recorded findings accurately represent observed field conditions; and that all known deficiencies, exceptions, assumptions, and additional scope items affecting the proposed UPS solution have been disclosed. I understand that the District may reject or return an incomplete report and that work shall not proceed in an affected sector until required approvals are obtained.
Vendor Company Representative Name
Title Email / Phone
Signature Date
12.2 District EDUCATIONAL TECHNOLOGY Project Management Review
☐ Approved to proceed to Phase 2 design and quotation
☐ Approved with conditions listed below
☐ Returned for correction or additional validation
☐ Not approved; affected scope remains on hold
District Review Comments / Conditions of Approval
District Project Manager
Signature
Title Approval Date
Technical Reviewer Signature / Date
12.3 Final Work Authorization Gate
Activity Authorized Not Authorized Conditions / Reference
Vendor quotation preparation ☐ ☐
Purchase order processing ☐ ☐
Equipment procurement ☐ ☐ Vendor purchases only with a PO# from DISD at hand
Logistics mobilization ☐ ☐
Installation scheduling and field work ☐ ☐ Field work will not be performed when school/classes are in session.