11-Equipment Vendor Post Installation Quality Assurance Inspection Checklist Punch List Form.pdf

PDF 153 KB Posted

Attached to
Uninterruptible Power Supply
Solicitation number
JV-250437
Issued by
Dallas County, Texas

About this file

This is an Equipment Vendor Post Installation Quality Assurance Inspection Checklist and Punch List Form for Dallas Independent School District (DISD) in Texas, related to an Uninterruptible Power Supply (UPS) procurement. The form serves as a quality assurance tool for evaluating installed equipment across various network cable categories and fiber optic specifications, including Cat 5e, Cat 6, Cat 6A, armored and non-armored cables, multimode fiber (MMF OM2 and OM4), and single-mode fiber (SMF OS2 and OS1). The UPS procurement is intended for district-wide use on an as-needed basis and will be administered in accordance with Title 2 of the Code of Federal Regulations Part 200 requirements. The resulting contract will have an initial three-year term with two successive one-year renewal options available, not to exceed five years total, contingent upon the district's long-range needs and mutual agreement with the awarded vendor. Either party must provide written notice at least ninety days prior to contract expiration if renewal is not intended.

The procurement is available to all vendors, including sole source providers, and may be funded through local, state, federal, and grant-funded programs. The checklist document specifically references a 50 micron/1Gbps specification line item, indicating technical performance standards for the installed infrastructure. No specific pricing terms, set-asides, incumbent information, or funding amounts are detailed in the provided documentation.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Item

Cat 5e Cat 6 Cat 6A Armored Non-Armored MMF OM2 MM OM4 SMF OS2 SMF OS1

50 micron/ 1Gbps <500m

50~125 microns/ 10~100 Gbps <550m

9~125 Microns/ <10Km/ 10Gbps to100Gbps

9~125 Microns/<10Km/ 10Gbs to100Gbps

Line Item

Objective Met (Y/N/O)

Date Resolved Post Remedial Rep

Initials (Vendor & DISD )

Line Item

SWITCH TYPE

Network Room

Name Populated Switch Port

(x/total) Switch QTY # Optics Used Optics Capacity Gbps

Optics Type ( LR/SR/DAC Cable)

Fiber Patch Cord Type (LC~LC/other)

Installed/Removed

Project Description

SWITCHES

Are cables patched into the switch by use? (Data, security and PA cables) Are the patch cables bundled together neatly and dressed properly into the wire managers?

Is the fiber and its patch cords properly dressed to avoid damage/mixing with power and copper patch cords?

Did vendor use the correct type and length of fiber patch cords?

Is existing fiber OM4 or OS2 type

Did the vendor installation meet the EIA/TIA, NEC, and TDG expectations?

Copper Fiber

Equipment Vendor Post-Installation Quality Assurance Inspection Checklist Form

Org #

Project PO #

Inspection Date

DISD Edtech Director

Vendor Project Manager /Leader

Checklist is based on DISD TDG specificationProject Management Office

DISD Project Manager:

VENDOR NAME

Project Site Formal Name

Project Site Address

City, State, Zip

Do the patch cables used match patch panel terminated cable type?

Assessment Objective Remedial Action Needed

Edtech Architecture And Operations

Project Cabling (Installation must conform to EIA/TIA Standards and NEC Codes and the DISD TDG)

DISD Edtech Project Owner

Objective Met (Y/N/O)

Date Resolved Post Remedial Rep

Initials (Vendor & DISD )

Line Item

Network Room Name

UPS Installed (Y/N)

UPS Type/ Model House L6-30 QTY House L6-20 QTY House 5-20 Quads QTY Installed/Removed

30 MDF

31 IDF01

32 IDF02

33 IDF03

34 IDF03

35 IDF04

36 IDF05

Line Item

Objective Met (Y/N/O)

Date Resolved Post Remedial Rep

Initials (Vendor & DISD )

Line Item

Connectivity Status WAP Connectivity Speeds (Mbps)

Installed/Removed

Wall-Mounted or Rail-Mounted QTYCeiling-Mounted QTY

Are all UPS labeled properly with visible name labels

Is there any physical damage/deformity to any UPS resulting from the transportation of the network gear?

WAPs (Wireless Access Points)

Does UPS system have an Extended Battery Module (EBM) installed with it?

Did UPS come with external power distribution units (PDUs) and humidity sensors? Are they installed?

WAP Type/Model #

Are the UPS power cables secured properly?

Did the vendor distribute 50% to UPS and 50% to house power for each switch and to each UPS?

Are all installed UPS working and online?

UPS & Electrical Power

Assessment Objective Remedial Action Needed

Are the UPS installed in the racks properly and to code?

Did the vendor properly dress all cables (power, fiber, and copper)?

50-50 UPS/ House Power (Y/N)

Are all installed switches working and online?

Are all switches labelled properly with visible labels?

Is there any physical damage/deformity to any switch resulting from the transportation of the network gear?

Did the vendor properly dress all cables (power, fiber, and copper)?

Are the switches' power cables secured properly? Did the vendor return and close all vertical wire managers?

Did the vendor distribute the switch power cords at 50% to UPS and 50% to house power?

Assessment Objective Remedial Action Needed

Are the switches installed in the racks properly and to code? Did the switches fit into existing racks

Objective Met (Y/N/O)

Date Resolved Post Remedial Rep

Initials (Vendor & DISD )

Line Item

Room # With Removed Devices

Line Item

Objective Met (Y/N/O)

Date Resolved Post Remedial Rep

Initials (Vendor & DISD )

74 Signed DATE Signed DATE

75 Print Name Print Name

76 Title Titlle

1. This form is to be read and executed together with the Edtech Equipment Vendor Punchlist Form. This form is an expanded compilation of punchlist items

2. Upon discovering any deficiencies that immediately impact connectivity and the learning environment, the vendor must promptly correct and complete these items. Dallas ISD is not required to complete the QA and punch list forms before the vendor takes action to address issues that affect the learning environment when students are present in the school.

3. The vendor is required to correct and complete the listed QA/Punchlist items within 10 business days if the items do not impact connectivity and the learning environment.

4. This form is issued first without signature by a DISD Edtech project personnel for the vendor to immediately begin corrective measures. It will only have all signatures once all remedial work has satisfied the quality assurance matrix as set in this document

5. Dallas ISD reserves the right to revoke any signed QA and Punch List forms at any moment if a discovery is made that reveals the vendor has failed to meet the installation standards as outlined in this document and or the EIA/TIA, and Dallas ISD Technical Design Guidelines.

DISD Approval Authority Vendor Approval Authority

Disclosures

Did the vendor remove the existing installed equipment? Is the removed equipment gathered, tallied, and packaged ready for pick-up by the Edtech warehouse?

Did the vendor properly clean up the project site after install?

Did the vendor take away all packaging materials? Cardboard, plastics, etc were not left or dumped into project trash dumpsters

Remedial Action Needed

Did the vendor install/use all materials/accessories ordered with the UPS? special mounting brackets, humidity sensors, PDUs, etc

Assessment Objective

Project: Scope Items and General Presentability

Network Switches and Closets Wireless Access Points Cleanliness &

Coverage UPS systems and Power Removed Devices Gathered & Secured (Y/N)

Did the vendor properly clean all WAPs and any smudged ceiling tiles?

Are the WAP cables dressed and secured properly without excessive visibility?

Are all the WAPs installed properly and to code?

Are all the WAPs properly labeled with visible name labels?

Did the vendor use strong and aesthetically good-looking wall-mount brackets for the WAPs?

Are all installed WAPs working and online?

Assessment Objective Remedial Action Needed

Did the vendor close and return all ceiling tiles properly?

Did some of the WAPs come with externally attached antennas?

Are these antennas properly installed?

Is there any physical damage/deformity to any WAPs resulting from the transportation of the network gear?

Did the vendor install/use all materials/accessories ordered with the switches? SFPs, DAC Cables, Fiber patch cords, special mounting brackets

Did the vendor install/use all materials/accessories ordered with the WAPs? special mounting brackets, external antennas

Eqpmt Vendor QA Form

File details come from the government source that posted it. Updated .