This is an Administrative Specifications document for Section 01700 Project Closeout prepared for Upper Darby Township, Delaware County, Pennsylvania, detailing the procedural requirements for completing construction projects. The section establishes a two-stage completion process beginning with substantial completion, wherein contractors must submit written notice accompanied by a comprehensive list of items requiring completion or correction. The Engineer will observe the work within a reasonable timeframe and either concur with substantial completion status or provide written notification of deficiencies requiring remedy. Following contractor correction of noted items, a second observation occurs to verify compliance. Once the Engineer determines substantial completion has been achieved, a letter is issued confirming the status along with a verified and amended list of remaining items. The final observation phase requires contractor certification that Contract Documents have been reviewed, work has been completed in compliance with specifications, equipment and systems have been tested and are operational, and work is ready for final inspection. Similar to the substantial completion process, the Engineer will observe the work promptly and either approve final completion or identify incomplete or defective work requiring immediate remedy and resubmission of certification itemizing corrective actions taken.
The specification establishes financial and administrative consequences for contractor non-performance during closeout, including deduction of Engineer re-inspection fees from final payment should a second observation be necessary due to contractor misrepresentation of completion status. Required closeout submittals include project record documents as detailed in Section 01720, spare parts and maintenance materials as specified throughout the contract documents, and a final accounting statement reflecting all adjustments to the Contract Sum including original contract amount, change orders, allowances, unit prices, deductions for uncorrected work, and re-inspection deductions. The Engineer prepares a final Change Order documenting approved adjustments not previously incorporated, with the contractor submitting a final Application for Payment in accordance with contract conditions upon completion of all closeout requirements.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01700-1
SECTION 01700
PROJECT CLOSEOUT
PART 1 GENERAL
1.1 RELATED WORK SPECIFIED ELSEWHERE
A. Project Record Documents - Section 01720.
1.2 SUBSTANTIAL COMPLETION
A. When the work is considered substantially complete, submit a written notice that the work, or a designated portion thereof, is substantially complete. Include a list of all items that require completion or correction.
B. Within a reasonable time after receipt of such notice, an observation will be made to determine the status of completion.
C. If the Work is not considered substantially complete, the Contractor will be notified in writing, giving the reasons therefore.
D. Contractor shall remedy the deficiencies in the Work, and send a second written notice of substantial completion. This notice shall include a statement of action taken on each item noted a requiring correction or completion to achieve "Substantial Completion" status.
E. The Work will be observed a second time.
F. When the Engineer concurs that the Work is substantially complete, he will:
1. Issue a letter accompanied by Contractor's list of items to be completed or corrected, as verified and amended by the Engineer.
1.3 FINAL OBSERVATION
A. When the Work is considered complete, submit written certification that:
1. Contract Documents have been reviewed.
2. Work has been observed and has been completed in compliance with
Contract Documents.
01700-2
3. Equipment and systems have been tested in the presence of the Engineer and are operational.
4. Work is ready for final observation.
B. Observation will be made to verify the status of completion with reasonable promptness after receipt of such certification.
C. If the Work is not considered complete, the Contractor will be notified in writing, listing the incomplete or defective work.
D. Contractor shall take immediate steps to remedy the stated deficiencies and, after correcting deficiencies, he shall send a second written certificate that the work is complete. This certification shall itemize each deficiency noted and a statement of action taken to remedy or complete the Work.
E. The work will be observed a second time.
F. When the Work is acceptable under the Contract Documents, the Contractor shall be required to make closeout submittals.
1.4 SECOND OBSERVATION FEES
A. Should the Engineer perform a second observation due to failure of the work to comply with the claims of status of completion made by the Contractor:
1. Engineer will deduct the amount of such compensation from the final payment to the Contractor.
1.5 CLOSEOUT SUBMITTALS
A. Project Record documents as specified under Section 01720.
1.6 SPARE PARTS AND MAINTENANCE MATERIALS
A. Furnish spare parts and maintenance materials as specified under various Sections of the Specifications.
B. Package and label parts and materials and store in area of the building where directed by the Engineer.
1.7 FINAL ADJUSTMENT OF ACCOUNTS
01700-3
A. Submit a final statement of accounting.
B. Statement shall reflect all adjustments to the Contract Sum:
1. The original Contract Sum.
2. Additions and deductions resulting from:
a. Previous Change Orders.
b. Allowances.
c. Unit Prices.
d. Deductions for uncorrected Work.
e. Deductions for re-inspection payments.
f. Other adjustments.
3. Total Contract Sum, as adjusted.
4. Previous payments.
5. Sum remaining due.
C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Orders.
1.8 FINAL APPLICATION FOR PAYMENT
A. Submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contracts.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION