PATCHING, RESURFACING AND LINE STRIPING OF SELECTED ROADS FOR THE COUNTY OF GREENWOOD
Solicitation number
2026-RFP-017
Issued by
Greenwood County, South Carolina

About this file

This is a General Conditions document for Greenwood County, South Carolina, establishing the standard contractual terms for a road construction project involving patching, resurfacing, and line striping of selected county roads during 2025-2026. The contract documents include the Invitation to Bid, Information to Bidders, Bid Form, Bid Bond, Agreement, Performance and Payment Bonds, General and Supplemental Conditions, and Detailed Specifications. The scope requires the contractor to furnish all labor, materials, equipment, transportation, supervision, and temporary construction necessary for proper execution and completion of work in accordance with contract documents. The contractor must maintain traffic control, signage, marking of temporary hazards, and ensure access to all residences throughout construction through detours or flagging operations, with particular attention to SCDOT requirements at intersections and turn-outs. The contract requires submission of a performance schedule showing the order and timing of work phases with estimated completion dates. Work shall commence upon written Notice to Proceed and must be completed within the contract time specified in the Agreement, with computation beginning on the date specified in the Notice to Proceed.

Payment is structured at ninety percent of the amount due on progress payments until substantial completion, with the potential for full payment of remaining progress estimates once the project reaches ninety percent completion. The Owner will process approved payment certificates within thirty days of receipt. The contractor must obtain all required federal, state, and municipal permits and licenses at their own expense and comply with all applicable laws and regulations, including OSHA safety standards and environmental requirements. Insurance requirements are extensive and include Worker's Compensation with statutory limits, comprehensive general liability of $1,000,000 per person and per accident for bodily injury and property damage, and comprehensive fleet liability with matching limits. The contractor must maintain a one-year guarantee period from final acceptance for all defective materials and workmanship and is responsible for all damage to property caused by their operations. Changes to the work up to twenty-five percent of the contract amount may be ordered by the Owner through written change orders with corresponding adjustments to compensation and completion time. The contractor is fully responsible for site conditions, traffic control, weather protection, and coordination of all subcontractors and trades.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Patching, Resurfacing and Line Striping on Selected Roads 2025-2026

General Conditions - Page 1 of 13

GENERAL CONDITIONS

SECTION 01000

1. GENERAL

1.1 THE CONTRACT DOCUMENTS: The Contract Documents consist of the Invitation to Bid, Information to Bidders, Bid Form, Bid Bond, Agreement, Performance and Payment Bonds, Conditions of the Contract (General and Supplemental and Special), and Detailed Specifications.

1.2 CORRELATION AND INTENT OF DOCUMENTS: The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all.

The intent of the Specifications is that the Contractor shall furnish all labor, supplies and materials, tools, machinery, equipment, transportation, supervision, temporary construction of any nature, and all other services, facilities and means necessary for the proper execution and completion of the Work in accordance with the Contract Documents and all incidental work necessary to complete the Project in an acceptable manner, and fully complete the work or improvement ready for use, occupancy and operation by the Owner.

1.3 CONFLICT OR INCONSISTENCY: If there is any conflict or inconsistency between the provisions of the Supplemental Conditions and the provisions of the other Contract Documents, the provisions of the Supplemental Conditions shall prevail. If there is any conflict or inconsistency between the provisions of the General Conditions and the provisions of any of the Contract Documents other than the Supplemental Conditions, the provisions of the General Conditions shall prevail.

Any discrepancies found between the Specifications and site conditions or any inconsistencies or ambiguities in the Specifications shall be immediately reported to the Engineer, in writing, who will promptly correct such inconsistencies or ambiguities in writing. Work done by the Contractor after their discovery of such discrepancies, inconsistencies or ambiguities shall be done at the Contractor's risk.

Should a conflict be discovered within the Contract Documents, the Contractor shall be deemed to have estimated the higher quality way of doing the Work unless they have asked for and obtained a decision in writing from the Engineer before entering into this Contract.

1.4 TECHNICAL REFERENCES: Wherever technical standards, such as (but not limited to) ASTM and ANSI are referenced in the Specifications, it shall mean the standards current on the date the Contract Agreement is finalized, unless otherwise noted.

2. OWNER'S RIGHTS AND RESPONSIBILITIES

2.1 CHANGES IN THE WORK: The Owner, without invalidating the Contract, may make changes in the Work and in the Specifications therefor by making alterations therein, additions thereto, or omissions therefrom. All Work resulting from such changes shall be performed and furnished under and pursuant to the terms and conditions of the Contract. If such changes result in an increase or decrease in the Work to be done hereunder, or increase or decrease the quantities thereof, adjustment in compensation will be made therefor through a change order submitted to and approved by Greenwood County.

Except in an emergency endangering life or property, no change will be made unless in pursuance of a written order from the Engineer authorizing the change and no claim for additional compensation will be valid unless the change is so ordered.

The Contractor agrees to neither have nor assert any claim for, or be entitled to, any additional compensation for damages or for loss of anticipated profits on work that is eliminated.

General Conditions - Page 2 of 13

2.2 ENGINEER'S AUTHORITY: The Engineer will be the Owner's representative during the construction period and will observe the work in progress on behalf of the Owner. The Engineer will have the authority to act on behalf of the Owner in the following matters consistent with the Owner's rights and obligations as set forth in these Contract Documents:

1. Interpretation of Contract Documents.

2. Approval of Samples and shop drawings.

3. Preparation of supplementary details and instructions.

4. Inspection and approval of construction work.

5. Preliminary approval of progress payments applications.

Any instructions which the Engineer may issue the Contractor shall be adjudged an interpretation of the Contract requirements and not an act of supervision. The Engineer has no authority, nor accepts any responsibility, either direct or implied, to direct and superintend the construction operations.

The Contractor shall proceed without delay to perform the work as directed, instructed, determined, or decided by the Engineer and shall comply promptly with such directions, instructions, determinations, or decisions. If the Contractor has any objection thereto, the Contractor may require that any such direction, instruction, determination, or decision be put in writing and within 10 days after receipt of any such writing, the Contractor may file a written protest with the Owner stating clearly and in detail their objections, the reasons therefor, and the nature and amount of additional compensation, if any, to which the Contractor claims to be entitled thereby. A copy of such protest shall be filed with the Engineer at the same time it is filed with the Owner. Unless the Contractor files such written protest with the Owner and Engineer within such 10 day period, the Contractor shall be deemed to have waived all grounds for protest of such direction, instruction, determination, or decision and all claims for additional compensation or damages occasioned thereby, and shall further be deemed to have accepted such direction, instructions, determination, or decision as being fair, reasonable, and finally determinative of their obligations and rights under the Contract.

2.4 LIABILITY OF OWNER: No person, firm or corporation, other than the Contractor, who signed this Contract as such, shall have any interest herein or right hereunder. No claim shall be made or be valid either against the Owner or any agent of the Owner and neither the Owner nor any agent of the Owner will be liable for or be held to pay any money, except as herein provided. The acceptance by the Contractor of the payment as fixed in the final estimate shall operate as and shall be a full and complete release of the Owner and of every agent of the Owner from any and all claims, demands, damages and liabilities of, by or to the Contractor for anything done or furnished for or arising out of or relating to or by reason of the work or for or on account of any act or neglect of the Owner or of any agent of the Owner or of any other person, arising out of, relating to or by reason of the work, except the claim against the Owner for the unpaid balance, if any there be, of the amounts retained as herein provided.

2.5 OWNER'S RIGHT TO TERMINATE CONTRACT: If the Contractor should be adjudged bankrupt, or they make a general assignment for the benefit of their creditors, or if a receiver or trustee should be appointed on account of the Contractors insolvency, or if they should persistently or repeatedly refuse or should fail, except in cases for which extension of time is provided, to supply enough properly skilled workers or proper materials, or if the Contractor should fail to make prompt payment to Subcontractors or for material or labor, or persistently disregard laws, ordinances or the instructions of the Owner and their representatives, or otherwise be guilty of substantial violation of any provision of the Contract, then the Owner, may without prejudice to any other right or remedy and after giving the Contractor, and his surety, if any, seven days written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, as it may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the expense of finishing

General Conditions - Page 3 of 13 the work including compensation for additional engineering, managerial and administrative services shall exceed any unpaid balance, the Contractor shall pay the difference to the Owner.

2.6 SUSPENSION OF WORK, TERMINATION AND DELAY: The Owner may suspend the Work or any portion thereof for a period of not more than ninety days or such further time as agreed upon by the Contractor, by written notice to the Contractor and the Engineer, which notice shall fix the date on which Work shall be resumed. The Contractor shall resume that Work on the date so fixed. The Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to any suspension.

2.7 INSPECTIONS AND TESTING: If the Contract Documents, Owner's instructions, laws, ordinances or any public authority having jurisdiction require any work to be specially tested or approved, the Contractor shall give the Owner timely notice of its readiness for observation by the Owner or inspection by another authority, and if the inspection is by another authority rather than the Owner, of the date fixed for such inspection. The required certificates of such inspection shall be secured by the Contractor.

Observations by the Owner will be promptly made, and where practicable, at the source of supply. If any work should be covered up without approval or consent of the Owner, it must, if required by the Owner, be uncovered for examination, at the Contractor's expense.

2.8 INSPECTION OF WORK AWAY FROM THE SITE: If the work to be done away from the construction site is to be inspected on behalf of the Owner during its fabrication, manufacture, or testing, or before shipment, the Contractor shall give notice to the Engineer of the place and time where such fabrication, manufacture, testing, or shipping is to be done. Such notice shall be in writing and delivered to the Engineer in ample time so that the necessary arrangements for the inspection can be made.

2.9 PRIOR USE OR OCCUPANCY: The Owner reserves the right to use or occupy the Work or portion thereof, and to use equipment installed under the Contract, prior to final acceptance. Such use or occupancy will not constitute acceptance of the Work or any part thereof. Despite such use or occupancy, guarantee periods will not begin until the final completion of all work under the Contract, unless agreement to the contrary is made in writing between the parties.

2.10 WEATHER CONDITIONS: In the event of temporary suspension of work, or during inclement weather, or whenever the Engineer shall direct, the Contractor shall, and shall cause all subcontractors to, protect carefully all of their work and materials against damage or injury from the weather. If, in the opinion of the Engineer, any work or materials shall have been damaged or injured by reason of failure on the part of the Contractor or any of their subcontractors to protect its work, such materials shall be removed and replaced at the expense of the Contractor.

3. CONTRACTOR'S RIGHTS AND RESPONSIBILITIES

3.1 ACCESS TO WORK: The Owner, the Engineer, and their officers, agents, servants, and employees plus representatives of the various participating Federal or State agencies may at any and all times and for any and all purposes, enter upon the work and site thereof and the premises used by the Contractor, and the Contractor shall at all times provide safe and proper facilities therefor.

3.2 ACCIDENT PREVENTION: In the performance of the contract the Contractor shall comply with the most current applicable provisions of the regulations issued by the Secretary of Labor pursuant to section 107 of the Contract Work Hours and Safety Standards Act entitled "Safety and Health Regulations for Construction" (29 CFR Part 1518, renumbered as Part 1926). Occupational Safety and Health Standards (29 CFR Part 1910) issued by the Secretary of Labor pursuant to the Williams-Steiger Occupational Safety and Health Act of 1970 are applicable to work performed by the contractor subject to the provisions of the Act.

3.3 OBLIGATIONS OF CONTRACTOR: The Contractor shall and will, in good workmanlike manner, do and perform all work and furnish all supplies and materials, tools, machinery, equipment, transportation, General Conditions - Page 4 of 13 supervision, temporary construction of any nature, and all other services, means and facilities except as herein otherwise expressly specified, necessary or proper to perform and complete all work required by this Contract, within the time herein specified, in accordance with the provisions of this Contract and in accordance with the Drawings and/or Specifications and in accordance with the direction of the Engineer as given from time to time during the progress of the work. The Contractor shall furnish, erect, maintain and remove such temporary works as may be required.

The Contractor shall observe, comply with, and be subject to all terms, conditions, requirements, and limitations of the Contract and Specifications, and shall do, carry on, and complete the entire work to the satisfaction of the Engineer and the Owner.

3.4 CLEANING UP: The Contractor at all times shall keep the site of the work free from rubbish and debris caused by their operation under the Contract. When the work has been completed, the Contractor shall remove from the site of the work all of their plant, machinery, tools, construction equipment, temporary work and surplus materials so as to leave the work and the site clean and ready for use.

All public streets adjacent to the site and all taxiways at the site shall be kept clean of debris, spilled materials, and wet and dry earth at all times and shall be cleaned at the end of each working day. When wet earth is encountered, it shall be cleaned from the vehicles before they leave the site.

3.5 NON-COMPLIANCE WITH CONTRACT REQUIREMENTS: In the event the Contractor, after receiving written notice from the Owner of non-compliance with any requirement of this Contract, fails to initiate promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the Owner shall have the right to order the Contractor to stop any or all work under the Contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.

3.6 COMMUNICATIONS: The Contractor shall forward all communications to the Owner through the Engineer.

3.7 NO DISCRIMINATION IN EMPLOYMENT: In connection with the performance of work under this Contract, the Contractor agrees not to discriminate against any employee or applicant for employment because of race, religion, color, or national origin. The aforesaid provision shall include, but not be limited to, the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising;

layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.

3.8 EMPLOY COMPETENT PERSONS: The Contractor shall endeavor to employ only competent persons on the Work. Whenever the Engineer notifies the Contractor in writing that in their opinion any person on the Work is incompetent, unfaithful, disorderly, or otherwise unsatisfactory, or not employed in accordance with the provisions of the Contract, such person shall be discharged from the Work and shall not again be employed on it, except with the written consent of the Engineer.

3.9 EMPLOY SUFFICIENT LABOR AND EQUIPMENT: If, in the judgment of the Engineer, the Contractor is not employing sufficient labor, plant, equipment or other means to complete the work within the time specified, the Engineer may, after giving written notice, require the Contractor to employ such additional labor, plant, equipment and other means as the Engineer may deem necessary to enable the work to progress properly.

3.10 EXISTING STRUCTURES: Where the dimensions and locations of existing structures are of importance in the installation or connection of any part of the Work, the Contractor shall verify such dimensions and locations in the field before the fabrication of any material or equipment which is dependent on the correctness of such information.

3.11 INDEMNIFICATION: The Contractor shall indemnify and hold harmless the Owner and the

General Conditions - Page 5 of 13

Engineer and their agents and employees from and against all claims, damages, losses and expenses, including attorneys' fees, arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property including the loss of use resulting therefrom; and is caused in whole or in part by any negligent or willful act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable.

In any and all claims against the Owner or the Engineer, or any of their agents or employees, by any employee of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any Subcontractor under worker's compensation acts, disability benefit acts or other employee benefits acts.

3.12 LEGAL ADDRESS OF CONTRACTOR: The Contractor's business address is hereby designated as the place to which communications may be delivered. The depositing of any letter, notice or other communication in a postpaid wrapper directed to the Contractor's business address in a post office box regularly maintained by the U. S. Postal Service or the delivery of any letter, notice, or other communication by mail or otherwise shall be deemed sufficient service thereof upon the Contractor, and the date of such service shall be the date of receipt. The business address may be changed at any time by an instrument in writing, executed and acknowledged by the Contractor and delivered to the Engineer.

Service of any notice, letter or other communication upon the Contractor personally shall likewise be deemed sufficient service.

3.13 NIGHT AND SUNDAY WORK: No work shall be done at night or on Sunday except:

1. Usual protective work, such as pumping and the tending of lights and fires;

2. Work done in case of emergency threatening injury to persons or property;

3. When provided for under Supplemental Conditions as herein specified;

4. The Engineer has given written permission for such night work

Any work necessary to be performed after regular hours, on Sundays, or Legal Holidays, shall be performed without additional expense to the Owner.

3.14 PERMITS AND RESPONSIBILITIES: The Contractor shall, without additional expense to the Owner, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State and municipal laws, codes, and regulations, in connection with the prosecution of the work. The Contractor shall be similarly responsible for all damages to persons or property that occur as a result of their fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire construction work, except for any completed unit of construction thereof which theretofore may have been accepted.

3.15 PRECAUTIONS DURING ADVERSE WEATHER: During adverse weather and against the possibility thereof, the Contractor shall take all necessary precautions so that the Work may be properly done and satisfactory in all respects.

The Engineer may suspend construction operations at any time when, in their judgment, the conditions are unsuitable or the proper precautions are not being taken, whatever the weather may be, in any season.

The Contractor agrees not to have or assert any claim for or be entitled to any additional compensation or damages on account of any such suspension.

3.16 PROTECTION OF WORK, PROPERTY AND PERSONS: The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work.

The Contractor shall take all necessary precautions for the safety of, and shall provide the necessary

General Conditions - Page 6 of 13 protection to prevent damage, injury or loss to all employees on the Work and other persons who may be affected thereby, all the Work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, taxiways, structures and utilities during the course of construction.

The Contractor shall comply with all applicable laws, ordinances, rules, regulations and orders of any public body having jurisdiction. The Contractor shall erect and maintain as required by the conditions and progress of the Work, all necessary safeguards for safety and protection. The Contractor shall notify owners of adjacent utilities when prosecution of the Work may affect them. The Contractor shall remedy all damage, injury or loss to any property caused, directly or indirectly, in whole or in part, by the Contractor, any Subcontractor or anyone directly or indirectly employed by any of them or anyone for whose acts any of them be liable, except damage or loss attributable to the fault of the Contract Documents or to the acts or omissions of the Owner or the Engineer or anyone employed by either of them or anyone for whose acts either of them may be liable and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of the Contractor.

3.17 PROTECTION OF WORK, PROPERTY AND PERSONS IN AN EMERGENCY: In emergencies affecting the safety of persons or the Work or property at the site or adjacent thereto, the Contractor, without special instruction or authorization from the Engineer or Owner, shall act to prevent threatened damage, injury or loss. The Contractor shall give the Engineer prompt Written Notice of any significant changes in the Work or deviations from the Contract Documents caused thereby, and a Change Order will thereupon be issued covering the changes and deviations involved.

3.18 PROTECTION AGAINST WATER AND STORM: The Contractor shall take all precautions necessary to prevent damage to the Work by storms or by water entering the site of the Work directly. In case of damage by storm or water, the Contractor shall at his own cost and expense make such repairs or replacements or rebuild such parts of the Work as the Engineer may require in order that the finished work may be completed as required by the Contract.

3.19 RESTORATION OF PROPERTY: All existing surfaces, including lawns, grassed and planted areas which have been injured by the Contractor's operations, shall be restored to a condition at least equal to that in which they were found immediately before work was begun.

3.20 TRAFFIC CONTROL: The Contractor shall be fully responsible for traffic control, signage, and marking of temporary hazards incident to or resulting from the repaving operations specified herein. When work on county roads enters SCDOT rights-of-ways for intersections and turn-outs, the Contractor shall use temporary signage and flagmen as required by the SCDOT. Access to all residences must be maintained throughout construction through detour or flagging operations.

3.21 SITE INVESTIGATION: The Contractor acknowledges that they have investigated and satisfied themselves as to the conditions affecting the Work, including but not restricted to those bearing upon transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads and uncertainties of weather, or physical conditions at the site, the character of equipment and facilities needed preliminary to and during prosecution of the Work. The Contractor further acknowledges that they have satisfied themselves as to character, quality and quantity of obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, as well as from information presented by the Drawings and/or Specifications made a part of this Contract.

3.22 SUBCONTRACTING: The Contractor shall be fully responsible to the Owner for the acts and omissions of their Subcontractors, and of persons either directly or indirectly employed by them, as they are for the acts and omissions of persons directly employed by the Contractor. The Contractor shall cause appropriate provisions to be inserted in all sub-contracts relative to the Work to bind Subcontractors to the Contractor by the terms of the Contract Documents insofar as applicable to the Work of Subcontractors and to give the Contractor the same power as regards terminating any subcontract that the Owner may exercise over the Contractor under any provisions of the Contract Documents.

General Conditions - Page 7 of 13

If any other contractor or any subcontractor of any such other contractor shall suffer or claim to have suffered loss, damage or delay by reason of the acts or omissions of the Contractor or of any of their subcontractors, the Contractor agrees to assume the defense against any such claim and to reimburse such other contractor or subcontractor for such loss or damage. The Contractor agrees to and does hereby indemnify and save harmless the Owner from and against any and all claims by such other contractors or subcontractors alleging such loss, damage or delay and from and against any and all claims, demands, costs and expenses, including attorney's fees, arising out of, relating to or resulting from such claims.

The Contractor shall be responsible for the coordination of the trades, subcontractors, and material providers engaged upon their work. The Owner or Engineer will not undertake to settle any differences between the Contractor and their subcontractors or between subcontractors. If any subcontractor on the project, in the opinion of the Engineer, proves to be incompetent or otherwise unsatisfactory, they shall be replaced if and when directed in writing.

Nothing contained in this Contract shall create any contractual relation between any Subcontractor and the Owner.

3.23 SUPERVISION: The Contractor shall keep on their work, during its progress, a competent superintendent and any necessary assistants, all satisfactory to the Owner. The Owner will not be responsible for the acts or omissions of the superintendent or their assistants.

3.24 TAXES: The Contractor shall promptly pay all federal, state and local taxes which may be assessed against them in connection with the work or their operations under the Agreement and/or the other Contract Documents, including, but not limited to, taxes attributable to the purchase of materials and equipment, to the performance of services, and the employment of persons in the prosecution of the work.

3.25 SANITARY FACILITIES: The Contractor shall provide adequate sanitary facilities for the use of those employed on the Work. The Engineer shall have the right to inspect such facilities at all times to determine whether or not they are being properly and adequately maintained.

3.26 TEMPORARY UTILITIES: Not applicable.

3.27 UNCOVERING AND CORRECTION OF WORK: The Engineer shall be furnished by the Contractor with every reasonable facility for examining and inspecting the work and for ascertaining that the work is being performed in accordance with the requirements and intent of the Contract, even to the extent of requiring the uncovering or taking down of portions of finished work by the Contractor.

Should the work thus uncovered or taken down prove satisfactory, the cost of uncovering or taking down and the replacement thereof shall be considered as extra work unless the original work was done in violation of the Contract in point of time or in the absence of the Engineer or their inspector and without their written authorization, in which case said cost shall be borne by the Contractor. Should the work uncovered or taken down prove unsatisfactory, said cost shall likewise be borne by the Contractor.

4. MATERIALS, EQUIPMENT AND WORKMANSHIP

4.1 CHEMICAL USAGE: All chemicals used during project construction or furnished for project operation, whether herbicide, pesticide, disinfectant, polymer, reactant or of other classification, shall show approval of either EPA or U.S.D.A. The use of all such chemicals and disposal of residues shall be in strict conformance with manufacturer and U.S.D.A. instructions. Material Safety Data Sheets shall be supplied to the owner.

4.2 CONTRACTOR'S TITLE TO MATERIALS: No materials or supplies for the Work shall be purchased by the Contractor or by any subcontractor subject to any chattel mortgage or under a conditional sale contract or other agreement by which an interest is retained by the seller. The Contractor warrants they have good title to all materials and supplies used by them, in the Work, free from all liens, claims or

General Conditions - Page 8 of 13 encumbrances.

4.3 CORRECTION OF WORK BEFORE COMPLETION: The Contractor shall promptly remove from the premises all work condemned by the Owner as failing to conform to the Contract Documents, whether incorporated or not and the Contractor shall promptly replace and re-execute their own work in accordance with the Contract and without expense to the Owner and shall bear the expense of making good all work of other contractors destroyed or damaged by such removal or replacement. The fact that the Engineer may have previously overlooked such defective work shall not constitute an acceptance of any part of it.

4.4 CORRECTION OF WORK AFTER COMPLETION: The Contractor shall remedy any defects due to faulty materials or workmanship and pay for any damage to other work resulting therefrom which shall appear within a period of one year from the date of final acceptance of the work except where longer periods are specified and in accordance with the terms of any special guarantees provided in the Contract. The Owner will give notice of observed defects with reasonable promptness.

4.5 CORRECTNESS OF WORK AFTER GUARANTEE PERIOD: It shall be the responsibility of the Contractor to permanently correct all defective items called to their attention within the guarantee period, whether such correction be made within the guarantee period or not. The Contract shall not be fully performed until such permanent corrections are made.

4.6 GENERAL GUARANTY: The Contractor warrants to the Owner that all materials and equipment furnished under this Contract will be new unless otherwise specified, and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents.

The Contractor shall further provide performance guarantees as specified in the detailed specifications.

4.7 HANDLING AND DISTRIBUTION: Not applicable.

4.8 MANUFACTURER'S DIRECTIONS: All manufactured articles, material and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned as directed by the manufacturers, unless herein specified to the contrary, and such action shall not void any manufacturer’s warranty.

4.9 MATERIALS, SERVICES AND FACILITIES: It is understood that, except as otherwise specifically stated in the Contract Documents, the Contractor shall provide and pay for all labor, supplies and materials, tools, machinery, equipment, transportation, supervision, temporary construction of any nature, and all other services, means and facilities of any nature whatsoever necessary to execute, complete, and deliver the Work within the specified time.

Materials and equipment shall be so stored as to insure the preservation of their quality and fitness for the Work. Stored materials and equipment to be incorporated in the Work shall be located so as to facilitate prompt inspection.

Materials, supplies and equipment shall be in accordance with samples submitted by the Contractor and approved by the Engineer.

4.10 MISCELLANEOUS ITEMS: The work to be done by the Contractor, specified and enumerated under this Contract, shall include any minor details of the Work not specifically mentioned in the Specifications or shown on the Drawings, but obviously necessary for the proper completion of the Work, which shall be considered incidental and as being a part of and included with the Work for which prices are given in the Bid. The Contractor will not be entitled to any additional compensation therefor.

4.11 MISTAKES OF CONTRACTOR: The Contractor shall promptly correct and make good any and all defects, damages, omissions, or mistakes, for which they and/or their agents, employees or subcontractors are responsible, and they shall pay to the Owner all costs, expenses, losses, and damages resulting therefrom or by reason thereof as determined by the Engineer.

General Conditions - Page 9 of 13

4.12 RIGHT TO MATERIALS: Nothing in the Contract shall be construed as vesting in the Contractor any right of property in the materials, equipment, apparatus and other items furnished after they have been installed or incorporated in or attached or affixed to the work or the site, but all such materials, equipment, apparatus and other items shall, upon being so installed, incorporated, attached or affixed, become the property of the Owner.

4.13 ROYALTIES AND PATENTS: The Contractor shall pay all applicable royalties and license fees.

They shall defend all suits or claims for infringement of any patent rights and shall save the Owner harmless from loss on account thereof, except that the Owner will be responsible for all such loss when a particular process or the product of a particular manufacturer or manufacturers is specified, but if the Contractor has information that the process or article specified is an infringement of a patent, the Contractor shall be responsible for such loss unless they promptly give such information to the Owner in writing.

4.14 INSPECTION AND TESTING: All materials and equipment used in the construction of the Project shall be subject to adequate inspection and testing in accordance with generally accepted standards, as required and defined in the Contract Documents.

4.15 SUBSTITUTIONS: The Contractor may recommend the substitution of a material, article or piece of equipment of equal function for those referred to in the Contract Documents by reference to brand name or catalogue number, and if, in the opinion of the Engineer, such material, article, or piece of equipment is of equal function to that specified, the Engineer may approve its substitution and use by the Contractor.

Any cost differential shall be deductible from the Contract Price and the Contract Documents shall be appropriately modified by Change Order. The Contractor warrants that if substitutes are approved, no major changes in the function or general design of the Project will result. Incidental changes or extra component parts required to accommodate the substitute will be made by the Contractor without a change in the Contract Price or Contract Time. All requests for substitutions must be submitted to the Engineer ten

(10) days prior to the bid opening.

4.16 "OR EQUAL" CLAUSE: The phrase "or equal" shall be construed to mean that material or equipment will be acceptable only when in the judgment of the Engineer they are composed of parts of equal quality, or equal workmanship and finish, designed and constructed to perform or accomplish the desired result as efficiently as the indicated brand, pattern, grade, class, make or model.

Whenever a material, article or piece of equipment is identified on the Drawings or in the Specifications by reference to manufacturers' or vendors' names, trade names, catalogue numbers, etc., it is intended merely to establish a standard of quality and function; and, any material, article, or equipment of other manufacturers and vendors which will perform adequately the duties imposed by the general design will be considered equally acceptable provided the material, article, or equipment so proposed, is, in the opinion of the Engineer, of equal substance and function. It shall not be purchased or installed by the Contractor without the Engineer's written approval.

4.17 WAGES AND OVERTIME COMPENSATION: The Contractor and each of their subcontractors shall comply with all applicable State and local laws or ordinances with respect to the hours worked by laborers and mechanics engaged in work on the project and with respect to compensation for overtime.

4.18 NO WAIVER: Neither the inspection by the Owner or the Engineer, nor any order, measurement, approval, determination, decision or certificate by the Engineer, nor any order by the Owner for the payment of money, nor any payment for or use, occupancy, possession or acceptance of the whole or any part of the work by the Owner, nor the extension of time, nor any other act or omission of the Owner or of the Engineer shall constitute or be deemed to be an acceptance of any defective or improper work, materials, or equipment nor operate as a waiver of any requirement or provision of the Contract, nor of any remedy, power or right of or herein reserved to the Owner, nor of any right to damages for breach of contract. Any and all rights and/or remedies provided for in the Contract are intended and shall be construed to be

General Conditions - Page 10 of 13 cumulative; and, in addition to each and every other right and remedy provided for herein or by law, the Owner shall be entitled as a right to a writ of injunction against any breach or threatened breach of the Contract by the Contractor, by their Subcontractors or by any other person or persons.

5. INSURANCE, LEGAL RESPONSIBILITY AND SAFETY

5.1 COMPLIANCE WITH LAWS: The Contract shall be governed by the law of the place where the Project is located. The Contractor shall abide by all local and State Laws or ordinances to the extent that such requirements do not conflict with Federal laws or regulations. The Contractor shall keep themselves fully informed of all existing and future Federal, State and local laws, ordinances, rules and regulations affecting those engaged or employed on the work, the materials and equipment used in the work or the conduct of the work, and of all orders, decrees and other requirements of bodies or tribunals having any jurisdiction or authority over the same, including, but not limited to the U.S. Department of Labor and Bureau of Standards Safety and Health Regulations for Construction and its amendments as set up under the Williams-Steiger Occupational Safety and Health Act of 1970.

5.2 REQUIRED PROVISIONS DEEMED INSERTED: Not applicable.

5.3 LIENS: If at any time any notice of liens are filed for labor performed or materials or equipment manufactured, furnished, or delivered to or for the Work, the Contractor shall, at its own cost and expense, promptly discharge, remove or otherwise dispose of the same, and until such discharge, removal or disposition, the Owner shall have the right to retain from any monies payable hereunder an amount which, in its sole judgment, it deems necessary to satisfy such liens and pay the costs and expenses, including attorney's fees, of defending any actions brought to enforce the same, or incurred in connection therewith or by reason thereof.

The Contractor shall file no mechanic's or materialmen's lien or maintain any claim against the Owner's real estate or improvements for or on account of any work done, labor performed or materials furnished under this Contract.

5.4 CLAIMS: If at any time there may be any evidence of any claims for which the Contractor is or may be liable or responsible hereunder, the Contractor shall promptly settle or otherwise dispose of the same, and until such claims are settled or disposed of, the Owner may retain from any monies which would otherwise be payable hereunder so much thereof as, in its judgment, it may deem necessary to settle or otherwise dispose of such claims and to pay the costs and expenses, including attorney's fees, of defending any actions brought to enforce such claims, or incurred in connection therewith or by reason thereof.

5.5 INSURANCE: The Contractor shall not commence any work until they obtains, at their own expense, all required insurance. Such insurance must have the approval of the Owner as to limit, form, and amount. The Contractor shall not permit any Subcontractor to commence work on this project until the same insurance requirements have been complied with by such Subcontractor.

The Contractor shall furnish the Owner with certificates showing the type, amount, class of operations covered, effective dates and dates of expiration of policies. Such certificates shall also contain substantially the following statement: "The insurance covered by this certificate will not be canceled or materially altered, except after ten (10) days notice in writing and delivered by registered mail to the Owner".

Should any policy be canceled before final payment by the Owner to the Contractor and the Contractor fails immediately to procure other insurance as specified, the Owner reserves the right to procure such insurance and to deduct the cost thereof from any sum due the Contractor under this Contract.

Any insurance bearing on adequacy of performance shall be maintained after completion of the project for the full guaranty period. Should such insurance be canceled before the end of the guaranty period and the Contractor fails immediately to procure other insurance as specified, the Owner reserves the right to procure such insurance and to charge the cost thereof to the Contractor.

Nothing contained in these insurance requirements is to be construed as limiting the extent of the

General Conditions - Page 11 of 13

Contractor's responsibility for payment of damages resulting from their operation under this Contract.

The Contractor is required to obtain and maintain for the full period of the contract the following types of insurance coverages with limits not less than stated below:

A. The Contractor and all Subcontractors shall carry Worker’s Compensation and Employer’s Liability Insurance with the statutory limits applying to employer’s liability ($100,000.00) covering all employees employed by the Contractor or Subcontractors while engaged under this Contract.

B. The Contractor shall carry comprehensive general liability insurance with limits of liability not less than:

Bodily Injury: $1,000,000.00 - Each Person $1,000,000.00 - Each Accident

Property Damage: $1,000,000.00 - Each Accident

$1,000,000.00 - Aggregate

The liability coverage under this policy shall contain no exclusion relative to blasting, explosive, collapse of buildings or damage to underground property.

Liability limits under this policy shall be not less than the following:

Bodily Injury: $1,000,000.00 Each Person

$1,000,000.00 Each Accident

Property Damage: $1,000,000.00 Each Accident $1,000,000.00 Aggregate

C. The Contractor shall carry comprehensive fleet liability policy with limits of liability not less than:

Bodily Injury: $1,000,000.00 - Each Person

$1,000,000.00 - Each Accident

Property Damage: $1,000,000.00 - Each Accident

Fire, Windstorm and Vandalism insurance shall be carried and maintained by the Contractor in the name of the Owner and General Contractor as their interest may appear.

The Contractor and Subcontractors shall submit certificates of insurance to Owner at the same time as signed contracts and bonds.

5.6 ORAL AGREEMENTS: No oral order, objection, claim or notice by any party to the others shall affect or modify any of the terms or obligations contained in any of the Contract Documents, and none of the provisions of the Contract Documents shall be held to be waived or modified by reason of any act whatsoever, other than by a definitely agreed waiver or modification thereof in writing, and no evidence shall be introduced in any proceeding of any other waiver or modification.

5.7 SAFETY: In accordance with generally accepted construction practices, the Contractor shall be solely and completely responsible for conditions of the job site, including safety of all persons and property affected directly or indirectly by their operations during the performance of the work. This requirement will apply continuously 24 hours per day until acceptance of the work by the Owner and shall not be limited to normal working hours.

General Conditions - Page 12 of 13

6. PROGRESS AND COMPLETION OF WORK

6.1 NOTICE TO PROCEED: Following the execution of the Agreement by the Owner and the Contractor, written Notice to Proceed with the work will be given by the Owner to the Contractor. The Contractor shall begin, per the terms in the agreement, and shall prosecute the work regularly and uninterruptedly thereafter (except as provided for herein) with such force as to secure the completion of the work within the Contract Time.

6.2 CONTRACT TIME: The Contractor shall complete, in an acceptable manner, all of the work contracted for in the time stated in the Agreement. Computation of Contract Time shall commence the day to be specified in the Notice to Proceed and every calendar day following, except as herein provided, shall be counted as Contract Time.

6.3 PAYMENTS AND COMPLETION:

A. Until Substantial Completion, the Owner will pay ninety percent (90%) of the amount due the Contractor on account of progress payments. If the manner of completion of the Work and its progress are and remain satisfactory to the Owner, and in absence of other good and sufficient reasons, when the Project is indicated ninety percent (90%) or more complete (Work in Place, not including stored materials) in the Application For Payment, the Owner may, without reduction of previous retainage, decide any remaining progress payments be paid in full.

B. After review and approval of a certificate for payment, the Owner shall make Payment as follows:

1. A progress payment will be made within thirty (30) days of receipt of approved request.

2. In preparing estimates, the material delivered on the site, off site (in a bonded warehouse within state lines and 100 miles from the project site) and preparatory work done may be taken into consideration.

6.4 SCHEDULE OF COMPLETION: The Contractor shall submit, at such times as may reasonably be requested by the Engineer, schedules showing the order in which the Contractor proposes to carry on the work, with dates at which the Contractor shall start the various parts of the work, and estimated date of completion of each part.

6.5 WORK CHANGES: The Owner may, as the need arises, order changes in the work through additions, deletions, or modifications to the extent of 25% of the Contact Amount, without invalidating the Contract. Compensation and time of completion affected by the change shall be adjusted at the time of ordering such change.

6.6 EXTRA WORK: New and unforeseen items of work found to be necessary, and which cannot be covered by any item or combination of items for which there is a Contract Price, shall be classed as Extra Work. The Contractor shall do such Extra Work and furnish such materials as may be required for the proper completion or construction of the whole work contemplated, upon written order from the Owner as approved by the Engineer. In the absence of such written order, no claim for Extra Work shall be considered. Extra Work shall be performed in accordance with these Contract Documents where applicable and work not covered by such shall be done in accordance with the best construction practice and in a workmanlike manner. Extra Work required in an emergency to protect life and property shall be performed by the Contractor as required.

6.7 EXTENSION OF CONTRACT TIME: A delay beyond the Contractor's control occasioned by an Act of God, by act or omission on the part of the Owner or by strikes, lockouts, fire, etc., may entitle the Contractor to an extension of time in which to complete the work as agreed by the Owner, provided, however, that the Contractor shall immediately give written notice to the Owner of the cause of such delay.

General Conditions - Page 13 of 13

Act of God shall mean an earthquake, flood, cyclone or other cataclysmic phenomenon of nature. Rain, wind, flood, or other natural phenomenon of normal intensity for the locality shall not be construed as an Act of God and no reparation shall be made to the Contractor for damages to the work resulting therefrom.

All claims for extension of time shall be made in writing to the Engineer no more than twenty days after the occurrence of the delay; otherwise they shall be waived. In the case of continuing cause of delay only one claim is necessary. Any claim should include complete justification for the extent of the delay claimed.

7. SUPPLEMENTAL CONDITIONS

7.1 CONFLICT OF INTEREST: No official of the Owner who is authorized in such capacity and on behalf of the Owner to negotiate, make, accept or approve, or to take part in negotiation, making, accepting, or approving any architectural, engineering, inspecting, construction, or material supply contract, or any subcontract in connection with the construction of the project, shall become directly or indirectly interested personally in this Contract or in any part thereof.