About this file
This is a Fire Protection General Notes and Design Documents package for a Parking Ramp Expansion project at the U.S. Department of Veterans Affairs (VA) facility located at 3495 Bailey Avenue, Buffalo, NY 14215 (Project Number 528-18-375). The document was issued for bid on August 9, 2024, by the Office of Construction and Facilities Management.
The fire protection scope includes designing and installing a complete dry pipe standpipe system with automatic sprinkler protection throughout the new five-level parking garage addition. Key requirements include: dry standpipe risers (4-inch main risers with 2.5-inch hose valves) on each level with Fire Department Connections (FDCs) at Elevator/Stair Tower #3 and Stair Tower #1; hydraulic calculations prepared by a registered fire protection engineer or NICET Level III/IV technician per NFPA 13 (2022) standards; shop drawings coordinated with the architect and submitted for authority having jurisdiction approval; protection of existing sprinkler heads during construction; utilization of existing branch lines where feasible; system chlorination and pressure testing in compliance with local and federal plumbing codes; all components UL-listed and FM-approved; flexible connectors with 175 PSIG minimum rating; seismic design per NFPA 13 and ASCE 7; and compliance with the VA Fire Protection Design Manual (June 1, 2021). The contractor must be a licensed, authorized commercial sprinkler installer with minimum three years' experience, provide one-year warranty on all work and materials, pay all permit and inspection fees, establish safe working procedures per OSHA standards, and furnish operation and maintenance instruction to VA personnel upon completion.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SYMBOL DESCRIPTION
CHECK VALVE
SCOPE OF WORK BOUNDARY
NORMALLY CLOSED VALVE
WALL MOUNTED FIRE DEPARTMENT CONNECTION. - STD. CONNECTION
RISER
F
DRY STANDPIPE RISER NAME
GENERAL NOTES FOR CONTRACTORS: SEE ALL PROJECT GENERAL NOTES AND OTHER
REQUIREMENTS INCLUDING THE LIFE SAFETY AND INFECTION CONTROL WORK LOCATED WITHIN
THE GENERAL DRAWINGS SECTION. COMPLY WITH ALL REQUIREMENTS AS THEY ARE A DIRECT
PART OF THIS SECTION AS IF THEY WERE DIRECTLY INCLUDED AND PROVIDED HEREIN.
EQUIVALENCY SUBSTITUTIONS: THE “BASIS OF DESIGN (BOD) COMPLIANCE PROTOCOLS” ARE TO
BE FOLLOWED FOR ALL MATERIALS, EQUIPMENT, ASSEMBLIES AND SYSTEMS SPECIFIED AND
DETAILED THROUGHOUT ALL DRAWINGS AND SPECIFICATION SECTIONS, WHETHER THE BOD
DESIGNATE IS SPECIFICALLY REFERENCED THEREIN OR NOT. SEE THE GENERAL DRAWINGS
SECTION FOR THE SPECIFIC BOD COMPLIANCE REQUIREMENTS AND PROTOCOLS TO BE
FOLLOWED.
1. THIS CONTRACTOR SHALL REVIEW ENTIRE SET OF CONTRACT DOCUMENTS: INCLUDING
BUT NOT NECESSARILY LIMITED TO ARCHITECTURAL, STRUCTURAL, MECHANICAL,
PLUMBING, FIRE PROTECTION, ELECTRICAL DRAWIINGS AND ENTIRE PROJECT MANUAL.
THIS CONTRACTOR SHALL ACKNOWLEDGE AND INCLUDE IN THE SCOPE OF WORK
(CONTRACT) ALL CONDITIONS PERTINENT TO THE COMPLETION OF THEIR WORK. THE
CONTRACTOR SHALL FULLY COORDINATE THEIR WORK WITH THE INSTALLATION OF THEIR
WORK WITH THE INSTALLATION OF WORK BY OTHER TRADES AND MAKE NECESSARY
FIELD ADJUSTMENTS AS REQUIRED TO ACCOMMODATE THE INSTALLATION. ALL OF THE
ABOVE SHALL BE INCLUDED IN THE SCOPE OF WORK AT NO ADDITIONAL CHARGE TO THE
VA/GOVERNMENT.
2. THIS CONTRACTOR SHALL CAREFULLY EXAMINE THE DRAWINGS AND SPECIFICATIONS,
VISIT THE SITE OF THE WORK AND FULLY INFORM THEMSELVES AS TO ALL CONDITIONS
AND MATTERS THAT CAN, IN ANY WAY, AFFECT THE WORK OR THE COST THEREOF.
SHOULD THIS CONTRACTOR FIND DISCREPANCIES IN, OR OMISSIONS FROM THE
DRAWINGS, SPECIFICATIONS OR OTHER DOCUMENTS, OR BE IN DOUBT AS TO THEIR
MEANING, NOTIFY THE VA/CO AT ONCE, IN WRITING, OF ANY DISCREPANCIES BETWEEN
EXISTING CONDITIONS AND NEW WORK, OR BETWEEN THEIR WORK AND THE WORK OF
OTHER TRADES AND OBTAIN CLARIFICATION PRIOR TO SUBMITTING ANY BID. LACK OF
SUCH NOTIFICATION SHALL BE CONSTRUED AS TO INDICATE NO DISCREPANCIES OR
CONFLICTING CONDITIONS EXIST.
3. THE DRAWINGS INDICATE DIAGRAMMATICALLY THE INTENT, GENERAL CHARACTER,
REQUIREMENTS AND LOCATION OF THE WORK SHOWN AND INCLUDED. THE WORK
INDICATED BUT HAVING MINOR DETAILS OBVIOUSLY OMITTED SHALL BE PROVIDED AT NO
ADDITIONAL COST TO THE VA/GOVERNMENT.
4. THIS CONTRACTOR IS REQUIRED TO BID, AS SPECIFIED, ON THE DRAWINGS WITHOUT
DEVIATION FROM THE BOD.
5. IT IS THE INTENT OF THESE DOCUMENTS THAT THE FIRE PROTECTION CONTRACTOR
PROVIDE ALL LABOR, MATERIAL, EQUIPMENT AND TOOLS FOR THE COMPLETE
INSTALLATION OF ALL WORK SHOWN ON THE PLANS AND/OR DESCRIBED HEREIN,
INCLUDING ALL DEVICES, CONTROLS AND APPURTENANCES REQUIRED TO SET NEW
SYSTEMS INTO OPERATION.
6. SHOULD CONDITIONS NECESSITATE ANY REARRANGEMENTS, OR IF PIPING CAN BE RUN
TO BETTER ADVANTAGE, PREPARE AND SUBMIT SHOP DRAWINGS SHOWING THE
CHANGES BEFORE PROCEEDING WITH THE WORK. IF SUCH CHANGES ARE APPROVED BY
THE VA/COR AND SUCCESSFULLY REVIEWED BY THE ARCHITECT, THEY SHALL BECOME A
PART OF THE CONTRACT.
7. THIS CONTRACTOR SHALL VERIFY ALL MOUNTING, ALL ARRANGEMENTS, HEIGHTS AND
LOCATIONS PRIOR TO ROUGH-IN. ANY MENTION OF A SPECIFIC MOUNTING
ARRANGEMENT, WEIGHT OR LOCATION SHALL NOT RELIEVE THE CONTRACTOR OF THE
RESPONSIBILITY TO VERIFY THE SPECIFIC REQUIREMENT FURNISHED OR THE OTHER
TRADES WORKING IN THE SAME AREA. NO ADDITIONS TO THE CONTRACT SUM WILL BE
PERMITTED FOR ITEMS INSTALLED IN WRONG LOCATIONS, IN CONFLICT WITH OTHER
WORK, ETC.
8. ALL WORK SHALL BE DONE IN ACCORDANCE WITH ALL CURRENT FEDERAL BUILDING
CODES, REGULATIONS, AND REQUIREMENTS, LOCAL UTILITY COMPANY REQUIREMENTS,
NFPA, IPC, AND ASHRAE STANDARDS. ALL COMPONENTS SHALL BE UL LISTED AND FM
APPROVED.
9. THIS CONTRACTOR SHALL PAY ALL PERMIT FEES, PLAN REVIEW FEES, LICENSE FEES,
INSPECTIONS, AND TAXES APPLICABLE TO THEIR DIVISION AND SHALL BE INCLUDED IN
THE BASE BID AS PART OF THEIR CONTRACT.
10. THIS CONTRACTOR SHALL BE LICENSED, BONDED, INSURED AND CAPABLE OF
PERFORMING QUALITY WORKMANSHIP. THIS CONTRACTOR GUARANTEES ALL OF HIS
WORK AND MATERIALS FOR THE PERIOD OF ONE YEAR. FROM FINAL ACCEPTANCE BY THE
VA/GOVERNMENT.
11. THIS CONTRACTOR SHALL ESTABLISH SAFE WORKING PROCEDURES FOR THE
PROTECTION OF THE WORKMEN IN ALL PHASES OF WORK, COMPLYING WITH ALL
APPLICABLE PROVISIONS OF CITY, STATE, AND FEDERAL SAFETY LAWS (OSHA) AND AS
RECOMMENDED IN THE "MANUAL OF ACCIDENT PREVENTION IN CONSTRUCTION" AS
ISSUED BY THE ASSOCIATION OF GENERAL CONTRACTORS OF AMERICA, IN., 20TH AND E.
STREETS, N.W. WASHINGTON, D.C.
12. THIS CONTRACTOR IS RESPONSIBLE FOR SCHEDULING THE PURCHASE, DELIVERY,
RECEIVING, UNLOADING, UNCRATING, STORING, SETTING IN PLACE, AND PROTECTING ALL
NEW EQUIPMENT FURNISHED BY THIS CONTRACTOR AND EQUIPMENT FURNISHED BY
VA/GOVERNMENT FROM DAMAGE BY VANDALISM AND WEATHER DURING CONSTRUCTION.
13. THIS CONTRACTOR SHALL PROVIDE A COMPETENT OPERATING TECHNICIAN TO INSTRUCT
THE VA/GOVERNMENT IN THE OPERATION AND MAINTENANCE OF THE NEW EQUIPMENT.
14. UPON COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REVIEW AND CHECK THE
ENTIRE PORTION OF WORK, CLEAN EQUIPMENT AND DEVICES. REMOVE SURPLUS
MATERIALS AND RUBBISH FROM THE PROPERTY AND LEAVE THE WORK IN NEAT AND
CLEAN ORDER AND IN COMPLETE WORKING CONDITION. EACH RESPECTIVE CONTRACTOR
SHALL BE RESPONSIBLE FOR THE REMOVAL OF ANY CARTONS, DEBRIS, EQUIPMENT, ETC.,
INSTALLED BY THIS CONTRACTOR INCLUDING EQUIPMENT FURNISHED BY OTHERS AND
UNPACKED OR REMOVED FROM CARTONS BY THIS CONTRACTOR.
15. THIS CONTRACTOR SHALL FURNISH AND INSTALL ALL STRUCTURAL STEEL MEMBERS,
SLEEVES, AND SHIMS REQUIRED TO LEVEL AND SUPPORT EQUIPMENT AND PIPES.
16. BEFORE PLACING WATER SYSTEM IN OPERATION, CHLORINATE ENTIRE SYSTEM IN
ACCORDANCE WITH THE REQUIREMENTS OF THE SPECIFICATIONS AND IN CONJUNCTION
WITH ALL LOCAL, STATE AND FEDERAL PLUMBING CODES, SUPPLY CERTIFICATE.
17. EXISTING SERVICE VALVES AT ALL BRANCH SUPPLY PIPING SHALL REMAIN AS IS. SUCH
SERVICE VALVES SHALL BE AS PER THE SPECIFICATIONS AND/OR IN KEEPING WITH THE
FACILITY STANDARDS.
18. SPRINKLER HEADS SHALL BE LOCATED IN CEILING GRID IN A SYMMETRICAL PATTERN,
COORDINATED WITH OTHER DEVICES MOUNTED IN OR ON THE CEILING. PROVIDE
ADDITIONAL SPRINKLER HEADS REQUIRED TO ACHIEVE SYMMETRY. LOCATE SPRINKLER
HEADS IN THE CENTER OF CEILING TILES.
19. SPRINKLER CONTRACTOR SHALL PROVIDE A COORDINATED REFLECTED CEILING PLAN AS
PART OF THE SUBMITTAL TO THE VA/COR SHOWING SPRINKLER HEAD LOCATIONS
COORDINATED WITH CEILING AND ALL OBJECTS MOUNTED IN OR ON THE CEILING.
20. THE SPRINKLER CONTRACTOR SHALL BE A LICENSED, AUTHORIZED INSTALLER OF
COMMERCIAL SPRINKLER SYSTEM AND SHALL HAVE HAD A MINIMUM OF THREE (3) YEARS
OF EXPERIENCE IN THE INSTALLATION OF SPRINKLER SYSTEMS.
21. THE CONTRACTOR IS RESPONSIBLE FOR THE COMPLETE DESIGN OF THE SPRINKLER
SYSTEM AND TO SUBMIT HYDRAULIC CALCULATIONS PER NFPA 13 IN SUBMITTAL OF SHOP
DRAWINGS AND FOR THE COMPLETE DESIGN OF THE SPRINKLER SYSTEM. THE
SPRINKLER SYSTEM SHALL BE:
A. A DESIGNED SYSTEM IN ACCORDANCE WITH NFPA 13, 2019 AND SPECIFICATION.
B. DESIGNED TO CONFORM WITH BUILDING STRUCTURAL, MECHANICAL, AND
ELECTRICAL SYSTEM, AS INDICATED AND DESCRIBED ON THE CONTRACT
DOCUMENTS.
C. ACCEPTABLE TO THE FIRE MARSHAL AND OR ALL LOCAL AUTHORITIES HAVING
JURISDICTION.
22. THE SPECIFICATIONS, THE CONTRACTOR SHALL SUBMIT FOR APPROVAL TO THE
AUTHORITIES HAVING JURISDICTION, FULLY COORDINATED SHOP DRAWINGS OF
SPRINKLER HEADS, HANGERS AND SUPPORTS. DESIGN PLAN SHALL BE PREPARED AND
SIGNED/SEALED BY A REGISTERED FIRE PROTECTION ENGINEER IN ACCORDANCE WITH
UCF REQUIREMENT OR BY A NICET LEVEL III/IV TECHNICIAN.
23. THE SPRINKLER SYSTEM SHALL BE INSPECTED AND TESTED IN ACCORDANCE WITH THE
REQUIREMENTS OF THE NATIONAL FIRE PROTECTION CODE, AND ALL LOCAL
AUTHORITIES HAVING JURISDICTION.
24. THE CONTRACTOR SHALL ARRANGE FOR INSPECTION AND TEST OF ANY OR ALL PARTS OF
THE WORK AS REQUIRED BY AUTHORITIES HAVING JURISDICTION AND PAY ALL CHARGES
FOR SAME.
25. ARCHITECT/ENGINEER SHALL BE RESPONSIBLE FOR OBTAINING ACCURATE FLOW TEST
DATA OR PERFORMING AN UPDATED FLOW TEST AS PER NFPA 13 AND NFPA 25.
26. AREA SHALL BE DESIGNED IN ACCORDANCE WITH THE REQUIREMENT FOR OCCUPANCY
PER NFPA 13.
27. THE AUTOMATIC WET FIRE SPRINKLER SYSTEM SHALL BE INSTALLED IN SUCH A MANNER
TO PREVENT THE SYSTEM PIPING OR SPRINKLER HEAD EXPOSURE TO TEMPERATURES
LESS THAN 40 DEGREES F.
28. PAINT NEW SPRINKLER PIPING RED AND LABEL PER NFPA 13.
29. CONTRACTOR SHALL PROVIDE COORDINATED PIPE SLEEVE DRAWINGS SHOWING ALL
PENETRATIONS THROUGH FLOORS.
30. PROVIDE OR EXTEND STANDPIPE SYSTEM IN ACCORDANCE WITH NFPA 14.
31. ALL FIRE PROTECTION VALVES SHALL BE SUPERVISED.
32. CONTRACTOR SHALL PROVIDED COORDINATED PIPE SLEEVE DRAWINGS SHOWING ALL
PENETRATIONS THROUGH FLOORS.
33. INSTALLER QUALIFICATIONS: CONTRACTOR'S RESPONSIBILITY SHALL INCLUDE
DESIGNING, FABRICATING AND INSTALLING FIRE-SUPPRESSION SYSTEMS AND PROVIDING
PROFESSIONAL ENGINEERING SERVICES OR THE SERVICES OF A NICET LEVEL III/IV
TECHNICIAN AS NEEDED TO ASSUME ENGINEERING RESPONSIBILITY. CALCULATIONS
BASED ON RESULTS OF THE FIRE-HYDRANT FLOW TEST(S) THEY PERFORM.
A. ENGINEERING RESPONSIBILITY: PREPARATION OF WORKING PLANS, CALCULATIONS,
AND FIELD TEST REPORTS BY A QUALIFIED PROFESSIONAL FIRE PROTECTION
ENGINEER.
34. WELDING: QUALIFY PROCESSES AND OPERATORS ACCORDING TO ASME BOILER AND
PRESSURE VESSEL CODE, SECTION IX.
35. NFPA STANDARDS: FIRE SUPPRESSION SYSTEM EQUIPMENT, SPECIALTIES, ACCESSORIES,
INSTALLATION AND TESTING SHALL COMPLY WITH THE FOLLOWING:
A. NFPA 13, 2022 INSTALLATION OF SPRINKLER SYSTEMS.
B. NFPA 101, 2024 LIFE SAFETY CODE.
C. NFPA 72 , 2022 FIRE ALARM CODE.
36. FIRE-SUPPRESSION SPRINKLER SYSTEM DESIGN SHALL BE APPROVED BY AUTHORITIES
HAVING JURISDICTION.
A. MARGIN OF SAFETY FOR AVAILABLE WATER FLOW AND PRESSURE: 10 PERCENT,
INCLUDING LOSSES THROUGH WATER-SERVICE PIPING, VALVES, AND BACKFLOW
PREVENTERS.
37. CONTRACTOR SHALL SUBMIT FOR REVIEW TO THE VA/COR A COMPLETE LIST OF ITEMS TO
BE FURNISHED AND INSTALLED UNDER THIS CONTRACT. INCLUDING, BUT NOT BE LIMITED
TO THE FOLLOWING:
A. DIMENSIONED SHOP DRAWINGS OF MATERIALS AND FIXTURES. DIMENSIONED SHOP
DRAWINGS OF EQUIPMENT AND PIPING PLAN LAYOUT(S).
38. REQUIRED ITEMS TO BE SUBMITTED SHALL INCLUDE, BUT NOT BE LIMITED TO THE
FOLLOWING:
A. PRODUCT DATA.
B. APPROVED SPRINKLER PIPING DRAWINGS: WORKING PLANS, PREPARED ACCORDING
TO NFPA, AND HAVE BEEN APPROVED BY AUTHORITIES HAVING JURISDICTION,
INCLUDING HYDRAULIC CALCULATIONS.
C. FIELD QUALITY-CONTROL TEST REPORTS.
D. FIELD TEST CERTIFICATES.
E. OPERATION AND MAINTENANCE DATA.
39. SEISMIC PERFORMANCE: FIRE-SUPPRESSION PIPING SHALL BE CAPABLE OF
WITHSTANDING THE EFFECTS OF EARTHQUAKE MOTIONS DETERMINED ACCORDING TO
NFPA 13 AND APPLICABLE CODE REQUIREMENTS. ASCE 7, VA 11-18-8. REFER TO
ARCHITECTURAL DESIGN FOR SEISMIC HAZARD LEVEL CLASSIFICATIONS.
40. CONTRACTOR SHALL SUBMIT FOR REVIEW TO THE VA/COR A COMPLETE LIST OF ITEMS TO
BE FURNISHED AND INSTALLED UNDER THIS CONTRACT. INCLUDING, BUT NOT BE LIMITED
TO THE FOLLOWING:
A. DIMENSIONED SHOP DRAWINGS OF MATERIALS, FIXTURES AND EQUIPMENT.
B. DIMENSIONED SHOP DRAWINGS OF EQUIPMENT AND PIPING PLAN LAYOUT(S).
41. FLEXIBLE CONNECTORS:
A. FLEXIBLE CONNECTORS SHALL HAVE MATERIALS SUITABLE FOR SYSTEM FLUID.
INCLUDE 175 PSIG MINIMUM WORKING-PRESSURE RATING AND ENDS ACCORDING TO
THE FOLLOWING:
a. NPS 2 AND SMALLER: THREADED.
b. NPS 2-1/2 AND LARGER: GROOVED FOR USE WITH GROOVED-END PIPE
COUPLINGS.
B. STAINLESS-STEEL-HOSE/STEEL PIPE, FLEXIBLE CONNECTORS: CORRUGATED,
STAINLESS-STEEL, INNER TUBING COVERED WITH STAINLESS-STEEL WIRE BRAID.
INCLUDE STEEL NIPPLES OR FLANGES, WELDED TO HOSE.
C. STAINLESS-STEEL-HOSE/STAINLESS-STEEL PIPE, FLEXIBLE CONNECTORS:
CORRUGATED STAINLESS-STEEL, INNER TUBING COVERED WITH STAINLESS-STEEL
WIRE BRAID. INCLUDE STAINLESS-STEEL NIPPLES OR FLANGES, WELDED TO HOSE.
D. ALL CONNECTIONS AND FLEXIBLE HOSES SHALL BE FM APPROVED.
THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR DESIGNING AND PROVIDING A COMPLETE, FUNCTIONAL, AND CODE COMPLIANT DRY PIPE STANDPIPE SYSTEM. REFER TO GENERAL NOTES FOR ADDITIONAL DETAIL CONCERNING DESIGN PER NFPA 13, 14 TO BE SUBMITTED, COORDINATION AND SHOP DRAWINGS
REQUIREMENTS.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
1.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
FIRE PROTECTION SYMBOL LIST
AutoCAD SHX Text
FIRE PROTECTION GENERAL NOTES
AutoCAD SHX Text
FIRE PROTECTION DELEGATED-DESIGN NOTE
AutoCAD SHX Text
FIRE PROTECTION - GEN NOTES ABBREVIATIONS AND SYMBOLS
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP001
cverdu Image
UP
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10 11.5
C
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10
C
11 12
DN
VANVANVAN VAN
VAN VAN
C.3
C.2
B.6
C.1
UP
LEVEL 1
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL. FOR
GENERAL INFORMATION ONLY AND SHALL NOT BE CONSTRUED AS
FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE
DESIGN BUILD FIRE PROTECTION CONTRACTOR. THIS INCLUDES
THE RELOCATION OF SPRINKLER MAINS, BRANCH PIPING AND
HEADS AS NECESSARY FOR THE NEW DESIGN. REFER
SPECIFICATION FOR DESIGN CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION
DESIGN MANUAL, DATED JUNE 1, 2021 AND THE LATEST EDITION OF
THE NATIONAL FIRE PROTECTION STANDARD #13.
C. CONTRACTOR TO TO PROTECT EXISTING HEADS FROM DAMAGE
DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS,
AND FEED MAINS, SERVING NEW SPRINKLER LOCATIONS WITH
MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET .
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN SPRINKLER HEADS OVER AND KEEP FIRE
PROTECTION PIPING ACTIVE DURING CONSTRUCTION.
F. REFER TO SHEET 1/GC400 FOR FIRE TRUCK TURNING RADIUS.
FIRE PROTECTION GENERAL NOTES
EXISTING ELEVATOR
TO BE ABANDONED
4" MANUAL DRY STAND PIPE
UP TO FLOOR ABOVE. DRAIN
VALVE AT THE BOTTOM OF
THE PIPE (OPTIONAL)
2 1/2" DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
F
F
FDC-2
HV-1
HV-1
HV-1
HV-1
EXISTING FACP LOCATION
TO REMAIN AS IS
LEVEL 1
LEVEL 2
LEVEL 3
(NEW ADDITION)
LEVEL 4
(NEW ADDITION)
LEVEL 5
LEVEL 4
LEVEL 5
WEST
MEDICAL
CENTER
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
LEVEL 0
MED. CENTER
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
SOUTH
4"FP PIPING ROUTE
TIGHT TO STRUCTURE
4"FP PIPING ROUTE
TIGHT TO STRUCTURE
F
F
CHECK VALVE
FDC-1
130'-0"
130'-0"
130'-0"
130'-0"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
1.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text F.D.
AutoCAD SHX Text F.D.
AutoCAD SHX Text F.D.
AutoCAD SHX Text F.D.
AutoCAD SHX Text F.D.
AutoCAD SHX Text F.D.
AutoCAD SHX Text
RAMP UP
AutoCAD SHX Text
ELECTRIC
AutoCAD SHX Text
STORAGE
AutoCAD SHX Text
ELVR
AutoCAD SHX Text
PARKING GARAGE
AutoCAD SHX Text
NEW STAIR / ELEVATOR TOWER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ISOMETRIC DIAGRAM
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 1
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP101
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 1/16"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION DRY STANDPIPE PIPING PLAN - LEVEL 1
AutoCAD SHX Text N
DN
UP
DN
DN
DN
LEVEL 2
ELEVATORS
MEDICAL
CENTER
LOBBY
VAN
VAN
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10 11.5
C
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10
C
C.3
C.2
B.6
C.1
DN
UP
EXISTING ELEVATOR
TO BE ABANDONED
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY STAND
PIPE DOWN RISER
2 1/2"DRY PIPE
HOSE VALVE
YCO
F
F
F
F
HV-1
HV-1
HV-1
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL. FOR
GENERAL INFORMATION ONLY AND SHALL NOT BE CONSTRUED AS
FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE
DESIGN BUILD FIRE PROTECTION CONTRACTOR. THIS INCLUDES
THE RELOCATION OF SPRINKLER MAINS, BRANCH PIPING AND
HEADS AS NECESSARY FOR THE NEW DESIGN. REFER
SPECIFICATION FOR DESIGN CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION
DESIGN MANUAL, DATED JUNE 1, 2021 AND THE LATEST EDITION OF
THE NATIONAL FIRE PROTECTION STANDARD #13.
C. CONTRACTOR TO TO PROTECT EXISTING HEADS FROM DAMAGE
DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS,
AND FEED MAINS, SERVING NEW SPRINKLER LOCATIONS WITH
MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET .
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN SPRINKLER HEADS OVER AND KEEP FIRE
PROTECTION PIPING ACTIVE DURING CONSTRUCTION.
F. REFER TO SHEET 1/GC400 FOR FIRE TRUCK TURNING RADIUS.
FIRE PROTECTION GENERAL NOTES
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
(NEW ADDITION)
LEVEL 4
LEVEL 4
LEVEL 5
WEST
MEDICAL
CENTER
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
SOUTH
130'-0"
130'-0"
130'-0"
130'-0"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
2.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
RAMP UP
AutoCAD SHX Text
RAMP DN
AutoCAD SHX Text
PARKING GARAGE
AutoCAD SHX Text
NEW STAIR / ELEVATOR TOWER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ISOMETRIC DIAGRAM
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 2
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP102
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 1/16"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION DRY STANDPIPE PIPING PLAN - LEVEL 2
AutoCAD SHX Text N
DN
UP
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10 11.5
C
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10
C
C.3
C.2
B.6
C.1
LEVEL 3
ELEVATORS
VAN
VAN
DN
DN
UP
EXISTING ELEVATOR
TO BE ABANDONED
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
F
F
F
F
HV-1
HV-1
HV-1
HV-1
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL. FOR
GENERAL INFORMATION ONLY AND SHALL NOT BE CONSTRUED AS
FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE
DESIGN BUILD FIRE PROTECTION CONTRACTOR. THIS INCLUDES
THE RELOCATION OF SPRINKLER MAINS, BRANCH PIPING AND
HEADS AS NECESSARY FOR THE NEW DESIGN. REFER
SPECIFICATION FOR DESIGN CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION
DESIGN MANUAL, DATED JUNE 1, 2021 AND THE LATEST EDITION OF
THE NATIONAL FIRE PROTECTION STANDARD #13.
C. CONTRACTOR TO TO PROTECT EXISTING HEADS FROM DAMAGE
DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS,
AND FEED MAINS, SERVING NEW SPRINKLER LOCATIONS WITH
MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET .
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN SPRINKLER HEADS OVER AND KEEP FIRE
PROTECTION PIPING ACTIVE DURING CONSTRUCTION.
FIRE PROTECTION GENERAL NOTES
(NEW ADDITION)
LEVEL 4
LEVEL 4
LEVEL 5
WEST
MEDICAL
CENTER
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
SOUTH
130'-0"
130'-0"
130'-0"
130'-0"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
3.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
RAMP DN
AutoCAD SHX Text
RAMP UP
AutoCAD SHX Text
(NEW AT LEV. 3)
AutoCAD SHX Text
PARKING GARAGE
AutoCAD SHX Text
NEW STAIR / ELEVATOR TOWER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ISOMETRIC DIAGRAM
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 3
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP103
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 1/16"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION DRY STANDPIPE PIPING PLAN - LEVEL 3
AutoCAD SHX Text N
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10 11.5
C
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10
C
C.3
C.2
B.6
C.1
LEVEL 4
ELEVATORS
VAN
VAN
DN
DN
UP
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE RISER
2 1/2"DRY PIPE
HOSE VALVE
F
F
F
F
HV-1
HV-1
HV-1
HV-1
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL. FOR
GENERAL INFORMATION ONLY AND SHALL NOT BE CONSTRUED AS
FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE
DESIGN BUILD FIRE PROTECTION CONTRACTOR. THIS INCLUDES
THE RELOCATION OF SPRINKLER MAINS, BRANCH PIPING AND
HEADS AS NECESSARY FOR THE NEW DESIGN. REFER
SPECIFICATION FOR DESIGN CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION
DESIGN MANUAL, DATED JUNE 1, 2021 AND THE LATEST EDITION OF
THE NATIONAL FIRE PROTECTION STANDARD #13.
C. CONTRACTOR TO TO PROTECT EXISTING HEADS FROM DAMAGE
DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS,
AND FEED MAINS, SERVING NEW SPRINKLER LOCATIONS WITH
MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET .
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN SPRINKLER HEADS OVER AND KEEP FIRE
(NEW ADDITION)
LEVEL 4
LEVEL 4
LEVEL 5
WEST
MEDICAL
CENTER
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
SOUTH
130'-0"
130'-0"
130'-0"
130'-0"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
4.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
RAMP DN
AutoCAD SHX Text
RAMP UP
AutoCAD SHX Text
PARKING GARAGE
AutoCAD SHX Text
NEW STAIR / ELEVATOR TOWER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ISOMETRIC DIAGRAM
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 4
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP104
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 1/16"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION DRY STANDPIPE PIPING PLAN - LEVEL 4
AutoCAD SHX Text N
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10 11.5
C
D
C
B
A.3
A.2
A
1 1.7 2 9 9.4 10
1 2 3 4 5 6 7 8 9 10
C
C.3
C.2
B.6
C.1
LEVEL 5
ELEVATORS
DN
DN
4" MANUAL DRY
STAND PIPE DOWN
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE DOWN
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE DOWN
2 1/2"DRY PIPE
HOSE VALVE
4" MANUAL DRY
STAND PIPE DOWN
2 1/2"DRY PIPE
HOSE VALVE
VAN
VAN
F
F
F
F
HV-1 HV-1
HV-1
HV-1
A. THE FIRE PROTECTION DRAWINGS ARE CONCEPTUAL. FOR
GENERAL INFORMATION ONLY AND SHALL NOT BE CONSTRUED AS
FINAL DESIGN OR INSTALLATION DOCUMENTS. THE SPRINKLER
DESIGN AND INSTALLATION SHALL BE THE RESPONSIBILITY OF THE
DESIGN BUILD FIRE PROTECTION CONTRACTOR. THIS INCLUDES
THE RELOCATION OF SPRINKLER MAINS, BRANCH PIPING AND
HEADS AS NECESSARY FOR THE NEW DESIGN. REFER
SPECIFICATION FOR DESIGN CRITERIA.
B. DESIGN TO BE IN ACCORDANCE WITH THE VA FIRE PROTECTION
DESIGN MANUAL, DATED JUNE 1, 2021 AND THE LATEST EDITION OF
THE NATIONAL FIRE PROTECTION STANDARD #13.
C. CONTRACTOR TO TO PROTECT EXISTING HEADS FROM DAMAGE
DURING CONSTRUCTION ACTIVITIES.
D. CONTRACTOR TO UTILIZE EXISTING BRANCH LINES, CROSS MAINS,
AND FEED MAINS, SERVING NEW SPRINKLER LOCATIONS WITH
MODIFIED ARM-OVER CONNECTIONS FED FROM EXISTING OUTLET .
SHOW ALL PIPING ON SHOP DRAWING SUBMITTAL.
E. CONTRACTOR TO TURN SPRINKLER HEADS OVER AND KEEP FIRE
(NEW ADDITION)
LEVEL 4
LEVEL 4
LEVEL 5
WEST
MEDICAL
CENTER
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
PARKING
GARAGE
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
STAIR /
ELEV.
SOUTH
130'-0"
130'-0"
130'-0"
130'-0"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
5.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
RAMP DN
AutoCAD SHX Text
PARKING GARAGE
AutoCAD SHX Text
NEW STAIR / ELEVATOR TOWER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ISOMETRIC DIAGRAM
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 5
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP105
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 1/16"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION DRY STANDPIPE PIPING PLAN - LEVEL 5
AutoCAD SHX Text N
2 1/2" FIRE DEPARTMENT VALVE 5'-0"
AFF. PROVIDE 2 1/2" x 1 1/2" REDUCING
COUPLINGS, CAPS AND CHAINS (TYP.)
LEVEL 2 LOBBY 201
LEVEL 1 LOBBY 101/ ELEVATOR/STAIR TOWER #3
4" DRY STANDPIPE
PIPE SLEEVE THRU FLOOR (TYP.)
4" DRY STANDPIPE
LEVEL 3 LOBBY 301
LEVEL 4 LOBBY 401
LEVEL 5 LOBBY 501
4" DRY STANDPIPE
4" DRY STANDPIPE
4" DRY STANDPIPE
HV-1
HV-1
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
AIR RELEASE VALVE
HV-1
HV-1
HV-1
GRADE LEVEL/PAVEMENT
36" (MIN.) ABOVE EXTERIOR
GRADE/PAVEMENT LEVEL FIRE
DEPARTMENT ACCESS
FDC-1
STANDPIPE CONNECTION
LETTERING TO READ "DRY
STANDPIPE FIRE
DEPARTMENT USE ONLY".
2 1/2" FIRE DEPARTMENT VALVE 5'-0"
AFF. PROVIDE 2 1/2" x 1 1/2" REDUCING
COUPLINGS, CAPS AND CHAINS (TYP.)
PARKING LEVEL 201
PARKING LEVEL 101
4" DRY STANDPIPE
PIPE SLEEVE THRU FLOOR (TYP.)
4" DRY STANDPIPE
PARKING LEVEL 301
PARKING LEVEL 401
PARKING LEVEL 501
4" DRY STANDPIPE
4" DRY STANDPIPE
4" DRY STANDPIPE
HV-1
HV-1
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
AIR RELEASE VALVE
HV-1
HV-1
HV-1
GRADE LEVEL/PAVEMENT
F
F
4"FP PIPE TIGHT TO STRUCTURE4"FP PIPE TIGHT TO STRUCTURE
2 1/2" FIRE DEPARTMENT VALVE 5'-0"
AFF. PROVIDE 2 1/2" x 1 1/2" REDUCING
COUPLINGS, CAPS AND CHAINS (TYP.)
LEVEL 2 LOBBY 201
LEVEL 1 LOBBY 101/STAIR TOWER #2
4" DRY STANDPIPE
PIPE SLEEVE THRU FLOOR (TYP.)
4" DRY STANDPIPE
LEVEL 3 LOBBY 301
LEVEL 4 LOBBY 401
LEVEL 5 LOBBY 501
4" DRY STANDPIPE
4" DRY STANDPIPE
4" DRY STANDPIPE
HV-1
HV-1
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
AIR RELEASE VALVE
HV-1
HV-1
HV-1
GRADE LEVEL/PAVEMENT
36" (MIN.) ABOVE EXTERIOR
GRADE/PAVEMENT LEVEL FIRE
DEPARTMENT ACCESS
FDC-2
STANDPIPE CONNECTION
LETTERING TO READ "DRY
STANDPIPE FIRE
DEPARTMENT USE ONLY".
2 1/2" FIRE DEPARTMENT VALVE 5'-0"
AFF. PROVIDE 2 1/2" x 1 1/2" REDUCING
COUPLINGS, CAPS AND CHAINS (TYP.)
PARKING LEVEL 201
PARKING LEVEL 101 /OVERHANG
4" DRY STANDPIPE
PIPE SLEEVE THRU FLOOR (TYP.)
4" DRY STANDPIPE
PARKING LEVEL 301
PARKING LEVEL 401
PARKING LEVEL 501
4" DRY STANDPIPE
4" DRY STANDPIPE
4" DRY STANDPIPE
HV-1
HV-1
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
SECURE STANDPIPE TO WALL
(TYPICAL) SEE SPECIFICATIONS.
AIR RELEASE VALVE
HV-1
HV-1
HV-1
GRADE LEVEL/PAVEMENT
F
F
4"FP PIPE TIGHT TO STRUCTURE4"FP PIPE TIGHT TO STRUCTURE
COLUMN 4D
COLUMN 4D
COLUMN 4D
REFER TO SHEET 1/FP101 FOR
CONTINUATION AND ROUTING TO
CONNECT TO RISER F3.
REFER TO SHEET 1/FP101 FOR
CONTINUATION AND ROUTING TO
CONNECT TO RISER F4.
REFER TO SHEET 1/FP101 FOR
CONTINUATION AND ROUTING TO
CONNECT TO RISER F1.
REFER TO SHEET 1/FP101 FOR
CONTINUATION AND ROUTING TO
CONNECT TO RISER F2.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
1.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text
DRY PIPE RISER DETAIL - ELEVATOR/STAIR TOWER #3
AutoCAD SHX Text
FIRE DEPARTMENT CONNECTION AND HOSE VALVE
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text
HOSE VALVE DRY PIPE RISER CONNECTION DETAIL
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text
DRY PIPE RISER DETAIL - STAIR TOWER #2
AutoCAD SHX Text
FIRE DEPARTMENT CONNECTION AND HOSE VALVE
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text
HOSE VALVE DRY PIPE RISER CONNECTION DETAIL
AutoCAD SHX Text
FIRE PROTECTION - DRY STANDPIPE RISER
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP601
FIRE PROTECTION SCHEDULE
MARK LOCATION MANUFACTURER MODEL SIZE DESCRIPTION
HV-1 REFER TO SHEETS POTTER ROEMER 4315 2 1/2"
HOSE GATE VALVES, CAST BRASS VALVE WITH NON-RISING STEM, READ HANDWHEEL. FEMALE N.P.T. INLET x MALE HOSE THREAD OUTLET. BRASS SOLID WEDGE DISC AND TAPERED SEAT. THREADS SHALL CONFORM
TO LOCAL FIRE DEPARTMENT CONFIGURATION. PROVIDE BALL DRIP CAST BRASS CAP WITH CHAIN.
FDC-1 ELEVATOR/STAIR
TOWER #3 POTTER ROEMER 5751 4" x 2 1/2" x 2 1/2" EXPOSED FIRE DEPARTMENT INLET CONNECTIONS, 2-WAY DOUBLE CLAPPER TYPE. CAST BRASS, PIN LUG
SWIVELS AND PLUGS AND CHAINS. CAST BRASS ROUND WALL PLATE WITH LETTERIN "DRY STANDPIPE".
FDC-2 STAIR TOWER #1 POTTER ROEMER 5751 4" x 2 1/2" x 2 1/2" EXPOSED FIRE DEPARTMENT INLET CONNECTIONS, 2-WAY DOUBLE CLAPPER TYPE. CAST BRASS, PIN LUG SWIVELS AND PLUGS AND CHAINS. CAST BRASS ROUND WALL PLATE WITH LETTERIN "DRY STANDPIPE".
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
1.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text
FIRE PROTECTION - SCHEDULES
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP701
PROPOSED PARKING GARAGE
150'-0"
150'-0" 150'-0"
150'-0"
150'-0"
EXISTING FIRE
HYDRANT
EXISTING FIRE
HYDRANT
EXISTING FIRE
HYDRANT
EXISTING FIRE HYDRANT WITH EXISTING CONDITION
EXCEEDS 150'-0". REFER TO CHECKLIST: C-FH-601
FOR 2ND FIRE HYDRANT FULL-FLOW TEST
BLDG '7' - REFER TO
CHECKLIST: C-FH-601 FOR
RESIDUAL FIRE HYDRANT
FULL-FLOW TEST
OXYGEN TANKS - REFER
TO CHECKLIST: C-FH-601
FOR 1ST FIRE HYDRANT
FULL-FLOW TEST
SITE HYDRANT PLAN
1. REFER TO CIVIL DRAWINGS FOR FINAL LOCATION OF NEW FIRE
HYDRANT. FIRE HYDRANT SHALL HAVE NO LESS THAN 950 GPM
FLOW RATE WITH A PRESSURE NO LESS THAN 40 PSI STATIC AND
35 PSI RESIDUAL. NOTE, CIVIL ENGINEER TO COORDINATE
MANUFACTURER MAKE AND MODEL OF FIRE HYDRANT WITH
EXISTING.
X FIRE PROTECTION KEY NOTES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
1\
-1
Pa rk in g R am p
(B uf fa lo
, N Y)
\4
- D es
D oc s\
2- D ra w in gs
\W O
R
KI
N G
\2 1-
3_
FP
1.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024
AutoCAD SHX Text T
AutoCAD SHX Text T
AutoCAD SHX Text
CURB
AutoCAD SHX Text
CONC.
AutoCAD SHX Text
SANDSTONE CURB
AutoCAD SHX Text
CONC. SIDEWALK
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text
MULTI-STORY
AutoCAD SHX Text
HOSPITAL BUILDING
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text
OE
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text
BAILEY
AutoCAD SHX Text
AVENUE
AutoCAD SHX Text
LE BRUN
AutoCAD SHX Text
ROAD
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text
CONC. CURB
AutoCAD SHX Text
CONC. CURB
AutoCAD SHX Text
CONC.
AutoCAD SHX Text
WALK
AutoCAD SHX Text
CONC. CURB
AutoCAD SHX Text
CONC.
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text x
AutoCAD SHX Text
STOP
AutoCAD SHX Text C
AutoCAD SHX Text
AutoCAD SHX Text C
AutoCAD SHX Text
PAVEMENT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text
UT
AutoCAD SHX Text N.F.V.
AutoCAD SHX Text 'A'
AutoCAD SHX Text
WING
AutoCAD SHX Text
WING
AutoCAD SHX Text 'D'
AutoCAD SHX Text
WING
AutoCAD SHX Text 'B'
AutoCAD SHX Text 'C'
AutoCAD SHX Text
WING
AutoCAD SHX Text
NEW PARKING RAMP
AutoCAD SHX Text
FIRE PROTECTION - SITE PLAN
AutoCAD SHX Text
RH
AutoCAD SHX Text
HS
AutoCAD SHX Text
FP801
AutoCAD SHX Text
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text 32'
AutoCAD SHX Text 64'
AutoCAD SHX Text 1/32"=1'-0"
AutoCAD SHX Text
AutoCAD SHX Text
FIRE PROTECTION SITE PLAN - EXISTING FIRE HYDRANT LOCATIONS
AutoCAD SHX Text N
| Sheets and Views |
| FP001 FIRE PROTECTION - GEN NOTES ABBREVIATIONS AND SYMBOLS |
| FP101 FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 1 |
| FP102 FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 2 |
| FP103 FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 3 |
| FP104 FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 4 |
| FP105 FIRE PROTECTION - DRY STANDPIPE PIPING PLAN - LEVEL 5 |
| FP601 FIRE PROTECTION - DRY STANDPIPE RISER |
| FP701 FIRE PROTECTION - SCHEDULES |
| FP801 FIRE PROTECTION - SITE PLAN |
File details come from the government source that posted it. Updated .