05 - Drawings - Civil.pdf
PDF 39 MB Posted
- Attached to
- Y1LZ--TIERED SET-ASIDE - Parking Ramp Expansion Minor Construction - Buffalo VAMC 528-375
- Solicitation number
- 36C77626R0046
About this file
Summary of Civil Drawings for Parking Ramp Expansion Project
This document is a set of civil design drawings (marked "ISSUE FOR BID" dated 08-09-2024) for Project 528-375, a Parking Ramp Expansion Minor Construction project at the VA Medical Center located at 3495 Bailey Avenue, Buffalo, NY 14215. The drawings were prepared by Bancroft Architecture & Engineering (www.bancroft-ae.com) and include general notes, existing conditions, removals plans, materials and signage specifications, layout plans, utility and erosion control plans, grading plans, landscape plans, utility profiles, and detailed construction specifications.
The project encompasses extensive site work including asphalt and concrete pavement installation, sidewalk and curb ramp construction (with specific ADA accessibility tolerances defined), parking stall striping and markings, storm sewer and water line work, erosion and sediment control measures, and landscape restoration. Key requirements include utility location services (QL-B and QL-A soft-dig verification), temporary construction facilities (water, electricity, sanitary facilities, and lighting), demolition and removal of existing structures and utilities, and implementation of a Stormwater Pollution Prevention Plan (SWPPP) per New York State standards. The drawings specify design element tolerances for sidewalk slopes (cross slope 1.5% maximum design, 2% maximum acceptance; running slope 4.5% maximum design, 5% maximum acceptance) and curb ramps (7.5% maximum design grade, 8.3% maximum acceptance grade). Geotechnical requirements include proof-rolling of subgrade soils, maximum allowable bearing pressure of 3,000 PSF, and minimum frost protection depth of 4 feet for exterior foundations. The contractor is responsible for documenting all field layout with a licensed New York surveyor, providing marked-up as-built plans, and coordinating all utility work with the Contracting Officer's Representative (COR).
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN ELEMENT TOLERANCES
CIVIL-GENERAL NOTES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
1- G
EN
ER
AL
N
O
TE
S.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C001
ELEMENT
SIDEWALK CROSS SLOPE
SIDEWALK GRADE - RUNNING SLOPE
CURB RAMP GRADE - RUNNING SLOPE7.5% MAX 8.3% MAX
5.0% MAX
2.0% MAX1.5% MAX
4.5% MAX
DESIGN AND FIELD
LAYOUT LIMIT
LIMIT FOR WORK
ACCEPTANCE
TEMPORARY UTILITY NOTES:
1. TEMPORARY WATER WILL BE AVAILABLE FOR USE DURING
CONSTRUCTION AT VARIOUS LOCATIONS THROUGHOUT THE FACILITY
BASED UPON AVAILABLE SYSTEM CAPACITY. COORDINATE WITH AND
OBTAIN APPROVAL FROM THE COR FOR LOCATIONS TO DRAW WATER
FROM THE EXISTING FACILITY WATER DISTRIBUTION SYSTEM. THE
CONTRACTOR IS RESPONSIBLE FOR SUPPLYING, INSTALLING AND
MAINTAINING ANY REQUIRED CROSS CONNECTION CONTROLS AT
POINTS OF CONNECTION TO THE EXISTING FACILITY WATER SUPPLY.
2. TEMPORARY ELECTRICITY WILL BE AVAILABLE FOR USE DURING
CONSTRUCTION AT VARIOUS LOCATIONS THROUGHOUT THE FACILITY
BASED UPON AVAILABLE SYSTEM CAPACITY. COORDINATE WITH AND
OBTAIN APPROVAL FROM THE COR FOR LOCATIONS TO CONNECT TO
THE EXISTING FACILITY ELECTRICAL DISTRIBUTION SYSTEM.
3. PROVIDE TEMPORARY SANITARY FACILITIES FOR USING DURING
CONSTRUCTION.
4. THE CONTRACTOR IS RESPONSIBLE FOR AND SHALL INCLUDE IN
THEIR BID PRICE ANY TEMPORARY CONSTRUCTION LIGHTING THAT
MAY BE NECESSARY TO COMPLETE THE WORK ASSOCIATED WITH
THIS PROJECT. THIS MAY INCLUDE, BUT IS NOT LIMITED TO
TEMPORARY CONSTRUCTION LIGHTING DURING POTENTIAL SHIFTS
OUTSIDE FIRST SHIFT, THAT TYPICALLY COVERS 7AM TO 3PM. WHEN
IT IS DETERMINED THAT TEMPORARY LIGHTING IS REQUIRED TO
COMPLETE THE WORK, THE CONTRACTOR SHALL COORDINATE WITH
AND OBTAIN APPROVAL FROM THE COR FOR LOCATIONS OF AND
DURATION OF USE OF TEMPORARY LIGHTING AT A MINIMUM OF 48
HOURS IN ADVANCE OF IMPLEMENTING TEMPORARY LIGHTING
FACILITIES. ALL TEMPORARY LIGHTING PROVIDED SHALL INCLUDE ITS
OWN POWER SUPPLY AND SHALL NOT CONNECT TO THE FACILITY
ELECTRICAL SYSTEM UNLESS PRIOR APPROVAL GRANTED BY THE
COR.
5. SEE ALSO SPECIFICATION SECTION 015000 FOR ADDITIONAL
INFORMATION REGARDING CONSTRUCTION FACILITIES AND
TEMPORARY CONTROLS.
EXISTING CONDITION MAP NOTES:
1. THE HORIZONTAL DATUM IS REFERENCED TO THE NORTH AMERICAN
DATUM OF 1983, NEW YORK STATE PLANE WEST ZONE 3103.
2. THE VERTICAL DATUM IS REFERENCED TO THE NATIONAL GEODETIC
VERTICAL DATUM OF 1929 (NGVD29). ELEVATIONS WERE ESTABLISHED
ONSITE VIA DIFFERENTIAL LEVELING HOLDING SEVERAL RECORD
FINISHED FLOOR ELEVATIONS AND UTILITY IRON ELEVATIONS.
ELEVATIONS ARE 0.42' HIGHER THAN NAVD88 ELEVATIONS DERIVED
FROM GPS OBSERVATIONS ONSITE.
3. UNDERGROUND UTILITIES SHOWN HEREON ARE BASED ON SURFACE
EVIDENCE AND PROVIDED RECORD MAPPING. THIS MAPPING DOES NOT
PURPORT TO SHOW ALL UNDERGROUND UTILITIES ON SITE AND IS
SUBJECT TO FIELD VERIFICATION. CONTRACTOR SHALL PROVIDE QL-B
UTILITY LOCATION SERVICES FOR ENTIRE PROJECT SITE AND UP TO 2
DAYS OF QL-A UTILITY LOCATION USING SOFT-DIG EQUIPMENT TO
VERIFY LOCATION OF UTILITIES.
4. INFORMATION SHOWN HEREON IS FROM A FIELD SURVEY COMPLETED
BY M.J. ENGINEERING AND LAND SURVEYING, P.C. BETWEEN AUGUST 22
AND AUGUST 25, 2022.
5. CONTOUR INTERVAL = 1'.
6. UNAUTHORIZED ALTERATIONS OR ADDITION TO THIS SURVEY MAP IS A
VIOLATION OF SECTION 7209 OF THE NEW YORK STATE EDUCATION
LAW. COPIES OF THIS SURVEY MAP NOT BEARING THE LAND
SURVEYORS SEAL AND SIGNED WITH INK SHALL NOT BE CONSIDERED
TO BE VALID COPIES.
REMOVAL NOTES:
1. CONFORM TO APPLICABLE CODE FOR DEMOLITION OF STRUCTURES,
SAFETY OF ADJACENT STRUCTURES, DUST CONTROL, RUNOFF
CONTROL, AND HAULING, DISPOSAL AND STORAGE OF DEBRIS.
2. PROVIDE, ERECT, AND MAINTAIN TEMPORARY BARRIERS AND SECURITY
DEVICES.
3. MAINTAIN EXISTING UTILITIES TO REMAIN IN SERVICE AND PROTECT
THEM AGAINST DAMAGE DURING SELECTIVE DEMOLITION OPERATIONS.
DO NOT INTERRUPT EXISTING UTILITIES SERVING OPERATING
FACILITIES, EXCEPT WHEN AUTHORIZED IN WRITING BY THE COR.
4. PREVENT MOVEMENT OR SETTLEMENT OF ADJACENT STRUCTURES.
PROVIDE BRACING AND SHORING.
5. LOCATE AND IDENTIFY ALL EXISTING UTILITIES WITHIN THE
CONSTRUCTION AREA AS REQUIRED BY SPECIFICATION SECTION
023313. DISCONNECT AND SEAL OR CAP OFF UTILITY SERVICES THAT
WILL BE AFFECTED BY THIS PROJECT. NOTIFY THE COR AT A MINIMUM
OF 72 HOURS BEFORE STARTING WORK AND WITH THEIR
REQUIREMENTS. VERIFY THAT UTILITIES HAVE BEEN DISCONNECTED
AND CAPPED.
6. REMOVE COMPONENTS IN AN ORDERLY AND CAREFUL MANNER.
7. PROTECT EXISTING FEATURES THAT ARE NOT TO BE REMOVED.
8. CONDUCT OPERATIONS WITH MINIMUM INTERFERENCE TO PUBLIC OR
PRIVATE ACCESSES.
9. MAINTAIN EGRESS AND ACCESS AT ALL TIMES. DO NOT CLOSE OR
OBSTRUCT ROADWAYS, OR SIDEWALKS WITHOUT THE COR'S
PERMISSION.
10. CEASE OPERATIONS IMMEDIATELY IF ADJACENT STRUCTURES APPEAR
TO BE IN DANGER.
11. ROUGH GRADE AND COMPACT AREAS AFFECTED BY DEMOLITION TO
MAINTAIN SITE GRADES AND CONTOURS.
12. FIELD VERIFY EXISTING CONDITIONS AND CORRELATE WITH
REQUIREMENTS INDICATED ON DEMOLITION PLAN TO DETERMINE
EXTENT OF SELECTIVE DEMOLITION REQUIRED.
13. CONDUCT DEMOLITION OPERATIONS AND REMOVE DEBRIS TO ENSURE
MINIMUM INTERFERENCE WITH SELECTIVE DEMOLITION OPERATIONS.
14. CONDUCT DEMOLITION OPERATIONS TO PREVENT INJURY TO PEOPLE
AND
DAMAGE TO ADJACENT BUILDINGS AND FACILITIES TO REMAIN. ENSURE
SAFE PASSAGE OF PEOPLE AROUND SELECTIVE DEMOLITION
AREA.
15. REMOVE AND TRANSPORT DEBRIS IN A MANNER THAT WILL PREVENT
SPILLAGE ON ADJACENT SURFACES AND AREAS. TRANSPORT ALL
EXCESS MATERIALS OFF SITE AND LEGALLY DISPOSED OF.
16. CLEAN ADJACENT STRUCTURES AND IMPROVEMENTS OF DUST, DIRT
AND
DEBRIS CAUSED BY SELECTIVE DEMOLITION OPERATIONS. RETURN
ADJACENT AREAS TO CONDITION EXISTING BEFORE START OF
SELECTIVE DEMOLITION.
17. LEGALLY DISPOSE OF DEMOLISHED MATERIALS. DISPOSE OF ALL
DEBRIS RESULTING FROM DEMOLITION ACTIVITIES OFF-SITE AT A
FACILITY LEGALLY APPROVED TO RECEIVE THE DEBRIS. DO NOT ALLOW
DEMOLISHED MATERIALS TO ACCUMULATE ON-SITE. DO NOT BURN
DEMOLISHED MATERIALS ON-SITE.
CONTRACTOR PARKING, STAGING AND STORAGE
NOTES:
1. CONTRACTOR STAGING OR STORAGE AREAS ARE PROVIDED AS NOTED
IN THESE PLANS.
2. SEE ALSO DIVISION 1 SECTIONS OF THE PROJECT SPECIFICATIONS FOR
ADDITIONAL INFORMATION.
EROSION CONTROL NOTES:
1. CONSTRUCTION PHASING PLAN
THIS PROJECT WILL BE CONSTRUCTED AS A SINGLE PHASE.
2. EROSION AND SEDIMENT CONTROL PRACTICES
REFER TO DRAWING AND THE DETAILS AND THE PROJECT MANUAL FOR
LOCATION, SIZES AND SPECIFICATIONS OF EROSION AND SEDIMENT
CONTROL DEVICES.
A. TEMPORARY SEDIMENT CONTROL - SILT FENCE
SILT FENCE REDUCES RUNOFF VELOCITY AND CAUSES SETTLING OF
SEDIMENT. INSTALL SILT FENCE WHERE SHOWN. INSTALL AROUND
ANY STOCKPILED SOIL MATERIALS.
B. WETLAND PROTECTION FENCE (IF REQUIRED)
ORANGE CONSTRUCTION FENCE POSTED WITH "SENSITIVE AREA,
STAY OUT" PROTECTS THE ON-SITE WETLANDS FROM UNAUTHORIZED
DISTURBANCE.
C. TEMPORARY SEEDING
TEMPORARY SEEDING REDUCES EROSION AND SEDIMENT LOSS
FROM BARE GROUND. PROVIDE TEMPORARY SEEDING TO PROVIDE
TEMPORARY COVER FOR DISTURBED EARTH OR SOIL STOCKPILES.
PROVIDE TEMPORARY SEEDING PER THE DRAWINGS OR AT A MINIMUM
ON DISTURBED AREAS OR SOIL STOCKPILES HELD FOR LONGER THAN
7 DAYS, TEMPORARY SHUT DOWN OF CONSTRUCTION OR WAITING
FOR OPTIMAL PLANTING TIME. IN SPRING, SUMMER OR EARLY FALL
APPLY RYE GRASS AT AT A RATE OF 1 LB/ 1000 SQ. FT. IN LATE FALL OR
EARLY SPRING, APPLY CERTIFIED AROOSTOOK RYE AT 2.5 LBS. / 1000
SQ. FT. APPLY STRAW AT 2 BALES / 1000 SQ. FT OR WOOD FIBER
HYDROMULCH AT MANUFACTURER'S RECOMMENDED RATE. ANCHOR
STRAW.
D. CONCRETE WASHOUT
CONCRETE WASHOUT IS TO BE DONE OFF SITE OR AT A MAINTAINED
WASHOUT CONTAINER AS SHOWN IN THE PLAN(S). ALL WASTE WATER
AND SEDIMENT FROM THE UNIT IS TO BE DISPOSED OF OFF SITE IN
ACCORDANCE WITH STATE, LOCAL, AND FEDERAL REQUIREMENTS.
FINAL LOCATION OF THE UNIT IS TO BE DETERMINED BY THE COR.
E. DUST CONTROL
DUST CONTROLS PREVENT SURFACE AND AIR MOVEMENT OF DUST
FROM DISTURBED AREAS THAT MAY CAUSE OFF SITE DAMAGE,
HEALTH HAZARDS AND TRAFFIC SAFETY PROBLEMS. PROVIDE DUST
CONTROL THRU SUCH MEASURES AS SPRINKLING, CHEMICAL SOIL
TREATMENTS AND TEMPORARY AND PERMANENT STABILIZATION
MEASURES, SUCH AS SEEDING, MULCHING AND INSTALLING EROSION
CONTROL BLANKETS. THESE MEASURES WILL PREVENT DUST FROM
BLOWING OFF SITE. INSTALL TEMPORARY AND PERMANENT
STABILIZATION MEASURES PER THE DRAWINGS, AS SOON AS FINAL
GRADES ARE REACHED AND ON SOIL STOCKPILES AND DISTURBED
AREAS TO BE LEFT FOR LONGER THAN 7 DAYS. USE SPRINKLING,
CHEMICAL SOIL TREATMENTS AND OTHER METHODS AS REQUIRED TO
PREVENT BLOWING DUST.
F. STORM DRAIN INLET PROTECTION
INLET PROTECTION IS A TEMPORARY, SOMEWHAT PERMEABLE
BARRIER INSTALLED AROUND A STORM WATER INLET THAT PREVENTS
SEDIMENT LADEN WATER FROM ENTERING THE SYSTEM BY FILTERING
AND/OUR CAUSING SEDIMENT TO SETTLE. INSTALL INLET PROTECTION
IMMEDIATELY UPON INSTALLATION OF A STORM DRAIN INLET. USE
STONE AND BLOCK PROTECTION AROUND INLETS IN PAVED/GRAVEL
AREAS. USE FABRIC PROTECTION AROUND INLETS INSTALLED IN
LANDSCAPED AREAS. REMOVE PROTECTION UPON FINAL
STABILIZATION OF THE SITE.
G. PERMANENT SEEDING
PERMANENT SEEDING PREVENTS SOIL EROSION FROM BARE SOIL.
ONCE FINAL GRADING OF AN AREA HAS BEEN COMPLETED, PROVIDE
PERMANENT SEEDING AND MULCHING PER SPECIFICATION SECTION
329219.
3. POLLUTION PREVENTION MEASURES
IN ADDITION TO THE EROSION AND SEDIMENT CONTROL MEASURES
IMPLEMENTED AT THE SITE, IMPLEMENT THE FOLLOWING MEASURES TO
PREVENT LITTER, CHEMICALS AND DEBRIS FROM ENTERING THE STORM
DRAINS AND DISCHARGES FROM THE SITE OR INTO SENSITIVE AREAS.
A. PROPERLY INSTALL AND MAINTAIN EROSION AND SEDIMENT CONTROL
DEVICES AS OUTLINED IN THE PROJECT DOCUMENTS AND IN
COMPLIANCE WITH THE LATEST EDITION OF THE NEW YORK STATE
STANDARDS AND SPECIFICATIONS FOR EROSION AND SEDIMENT
CONTROL.
B. PROPERLY CONTAIN AND DISPOSE OF ALL MATERIALS USED ON SITE.
C. CLEAN UP SPILLS IMMEDIATELY TO MINIMIZE SAFETY HAZARD AND
PREVENT SPREADING.
D. ROUTINELY INSPECT AND CLEAN OUT STORM CATCH BASINS AND
CONVEYANCES.
E. CONTROL LITTER BY SWEEPING AND PICKING IT UP DAILY.
EROSION CONTROL NOTES (CON'T)
· STONE AND BLOCK INLET PROTECTION: CHECK FOR DAMAGED
MATERIALS AND ACCUMULATED SEDIMENT. REPAIR OR REPLACE
MATERIALS OF CONSTRUCTION AS NEEDED. REMOVE ANY
ACCUMULATED SEDIMENT.
· FOREBAYS: CHECK SIDE SLOPES FOR SCOUR, DAMAGE FROM
RODENTS AND SEEPAGE. CONTINUOUSLY MONITOR THE FOREBAYS
AND DETENTION PONDS FOR SEDIMENT ACCUMULATION. ONCE
SEDIMENT ACCUMULATION HAS REACHED 12" IN DEPTH, REMOVE
AND DISPOSED OF THE SEDIMENT OFF SITE. CHECK OUTLETS FOR
SIGNS OF SCOUR AND OBSTRUCTIONS AND MAKE REPAIRS AS
NECESSARY.
· RIP RAP OUTLETS: CHECK FOR OBSTRUCTIONS AND SCOUR AND
REMOVE AND REPAIR AS NECESSARY.
· CATCH BASINS AND PIPING: CHECK FOR OBSTRUCTIONS AND
SEDIMENT ACCUMULATION AND CLEAN AS NECESSARY.
6. SWPPP IMPLEMENTATION
THE CONTRACTOR AND SUB CONTRACTOR(S) ARE RESPONSIBLE FOR
COMPLYING WITH AND IMPLEMENTING THE SWPPP. REFER TO
SPECIFICATION "REGULATORY REQUIREMENTS" AND THE CONTRACTOR'S
CERTIFICATION STATEMENT IN THE SWPPP.
THE ENGINEER OF RECORD IS RESPONSIBLE FOR PERFORMING AND
DOCUMENTING THE INITIAL SITE ASSESSMENT AND PERFORMING THE
WEEKLY SITE INSPECTING AS REQUIRED BY THE SPDES PERMIT.
7. CONSTRUCTION COMPLETION
UPON CONSTRUCTI0N COMPLETION:
A. INSPECT THE CATCH BASINS, STORM WATER MANHOLES AND STORM
WATER CONVEYANCE SYSTEM FOR OBSTRUCTIONS OR SEDIMENT.
REMOVE OBSTRUCTIONS AND CLEAN STRUCTURES AND PIPING AS
NECESSARY.
B. FOREBAYS: INSPECT WEIRS FOR STRUCTURAL INTEGRITY AND
OBSTRUCTIONS. CHECK EMBANKMENTS FOR SCOUR, SEEPAGE,
DAMAGE FROM RODENTS OR UNWANTED PLANT GROWTH. MAKE
REPAIRS AS NECESSARY. CHECK OUTLET PROTECTION FOR
OBSTRUCTIONS AND SCOURING. MAKE ANY REPAIRS. SURVEY
FOREBAYS, REMOVE ALL ACCUMULATED SEDIMENT, RETURN TO
GRADES SHOWN ON THE GRADING PLAN.
UPON SITE STABILIZATION:
C. REMOVE ANY REMAINING TEMPORARY EROSION AND SEDIMENT
CONTROL MEASURES. STABILIZE AREA.
8. WINTER OPERATIONS/WINTER SHUT DOWN
A. FOR WINTER OPERATIONS
· PLOW SNOW AND PILE ON PAVED AREAS. DO NOT PLOW SNOW
ONTO GRASSED AREAS OR INTO WETLAND AREAS.
· CHECK DRAINAGE STRUCTURES WEEKLY AND AFTER SNOW EVENTS
FOR CLOGGING OR FREEZING TO ENSURE STRUCTURES DRAIN
FREELY.
· INSTALL AND MAINTAIN EROSION AND SEDIMENT CONTROL DEVICES
PER THE CONTRACT DOCUMENTS.
· STABILIZE ALL BARE SOILS BY ESTABLISHING VEGETATION OR
PROVIDING STRAW, MATTING, ROCK OR EROSION CONTROL
PRODUCTS.
· PLACE EROSION AND SEDIMENT CONTROL DEVICES AT ALL
SENSITIVE AREAS AND ALONG THE PERIMETER. THIS INCLUDES BUT
IS NOT LIMITED TO SILT FENCE, STORM DRAIN INLET PROTECTION,
CHECK DAMS AND PIPE OUTLET PROTECTION.
· PROTECT SOIL STOCKPILES WITH SILT FENCE PROTECTION AROUND
THE PERIMETER AND STABILIZE WITH ESTABLISHED VEGETATION,
STRAW, ROLLED EROSION CONTROL PRODUCT OR DURABLE
COVERING.
· MAINTAIN CONSTRUCTION ENTRANCE DURING WINTER SHUTDOWN.
· PLOW SNOW TO ALLOW FOR ENTRANCE TO THE SITE ON A MONTHLY
BASIS. PLOW SNOW AND STOCKPILE ONTO PAVED SURFACES. SNOW
PLOWING AND STOCKPILING ONTO GRASSED OR INTO SENSITIVE
AREAS WILL NOT BE ALLOWED.
· STABILIZATION MEASURES MUST BE IN PLACE, INCLUDING
STABILIZED VEGETATION, WITHIN SEVEN (7) DAYS FROM THE DATE
SOIL DISTURBING ACTIVITIES CEASE.
EROSION CONTROL NOTES (CON'T)
F. IF POSSIBLE, DO NOT STORE FUEL OR PETROLEUM PRODUCTS
ON-SITE. IF FUEL/PRETROLEUM PRODUCTS ARE STORED ON SITE:
· USE SECONDARY CONTAINMENT MEASURES.
· HAVE EQUIPMENT AND MATERIALS ON SITE TO CONTAIN AND CLEAN
UP SPILLS IN FUEL STORAGE AREAS OR ON BOARD MAINTENANCE
AND FUELING VEHICLES.
· CONTAIN AND CLEAN UP SPILLS IMMEDIATELY.
· PRACTICE PREVENTIVE MAINTENANCE FOR ON-SITE EQUIPMENT.
· OVERSEE ALL FILLING OPERATIONS.
G. PRACTICE GOOD HOUSEKEEPING AND EDUCATE EMPLOYEES ON
POLLUTION PREVENTION MEASURES.
· STORE ON SITE MATERIALS AND CHEMICALS IN A NEAT AND
ORDERLY MANNER AND IN AREAS DESIGNATED FOR SUCH
STORAGE.
· DISPOSE OF GARBAGE, RUBBISH, CONSTRUCTION AND SANITARY
WASTE ROUTINELY.
· IMMEDIATELY CLEAN UP ANY SPILLS.
· IMMEDIATELY CLEAN UP ANY SEDIMENTS OR WASTE TRACKED ONTO
PUBLIC HIGHWAYS OR TRANSPORTED ONTO ADJACENT
PROPERTIES.
· USE DUST CONTROL METHODS.
H. FOR CONSTRUCTION WASTE:
· DESIGNATE A WASTE COLLECTION AREA.
· PROVIDE AN ADEQUATE NUMBER OF CONTAINERS WITH LIDS OR
COVERS THAT CAN BE PLACED OVER CONTAINERS PRIOR TO
RAINFALL.
· ARRANGE FOR WASTE COLLECTION ON A ROUTINE BASIS AND PRIOR
TO CONTAINER OVERFLOW.
· IF A CONTAINER DOES SPILL, CLEAN UP IMMEDIATELY.
· COLLECT, REMOVE AND DISPOSE OF CONSTRUCTION WASTE IN
APPROVED DISPOSAL AREAS.
· FOLLOW APPLICABLE FEDERAL, STATE AND LOCAL REQUIREMENTS
FOR ALL DISPOSAL METHODS.
THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND MAINTAINING
TEMPORARY SANITARY FACILITIES. CONTRACT DOMESTIC WASTE
HAULERS TO REGULARLY REMOVE THE SANITARY WASTE AND TO
MAINTAIN THE FACILITIES IN GOOD WORKING ORDER.
I. IF FERTILIZERS ARE USED ON SITE:
· LIMIT THE APPLICATION OF FERTILIZERS TO THE MINIMUM AREA
REQUIRED AND USE THE MINIMUM RECOMMENDED AMOUNTS.
· REDUCE THE EXPOSURE OF FERTILIZERS TO STORM WATER RUN
OFF BY WORKING THE FERTILIZER INTO THE SOIL.
· APPLY FERTILIZER MORE FREQUENTLY BUT AT A LOWER
APPLICATION RATE.
4. EROSION AND SEDIMENT CONTROL PRACTICES AND IMPLEMENTATION
SCHEDULE
5. EROSION AND SEDIMENT CONTROL INSPECTION AND MAINTENANCE
SCHEDULE
A. INSPECT THE SILT FENCE AND CONSTRUCTION FENCE SURROUNDING
SENSITIVE AREAS (WETLANDS) ON A NIGHTLY BASIS DURING
CONSTRUCTION. COMPLETE REQUIRED MAINTENANCE, REPAIR OR
REPLACEMENT IMMEDIATELY.
B. INSPECT ALL REMAINING EROSION AND SEDIMENT CONTROL DEVICES
AFTER EACH RAIN EVENT AND ON A WEEKLY BASIS. COMPLETED
REQUIRED MAINTENANCE, REPAIR OR REPLACEMENT IMMEDIATELY
OR AS DIRECTED BY THE COR.
· SILT FENCE: INSPECT FOR TEARS, BULGING AND FOR AREAS WHERE
IT HAS FALLEN DOWN. REPAIR OR REPLACE AS NECESSARY.
· EROSION CONTROL BLANKETS: CHECK FOR PROPER/MISSING
ANCHORING, PLACEMENT DENSITY, DAMAGE DUE TO VANDALISM OR
CONSTRUCTION ACTIVITIES. REPAIR OR REPLACE AS NECESSARY.
· STABILIZED CONSTRUCTION ENTRANCE: MAINTAIN SO THAT
TRACKING OF SEDIMENT ONTO PUBLIC HIGHWAYS DOES NOT
OCCUR. TOP DRESS AS REQUIRED.
· FABRIC INLET PROTECTION: CHECK FOR DAMAGED MATERIALS AND
SEDIMENT ACCUMULATION. REPAIR OR REPLACE ANY DAMAGED
FABRIC. REMOVE ACCUMULATED SEDIMENT.
GEOTECHNICAL EARTHWORK NOTES:
GEOTECHNICAL ENGINEERING REPORT PREPARED BY QUALITY GEO
ENGINEERING, P.C. DATED SEPTEMBER 15 AND 26, 2022 PROVIDES THE
FOLLOWING DIRECTION:
1. EVALUATE THE EXPOSED SUBGRADE BY PROOF-ROLLING, AFTER
EXCAVATION TO THE DESIGN SOIL SUBGRADE ELEVATION, USING A
LARGE SMOOTH DRUM ROLLER OPERATED IN THE STATIC MODE. A
GEOTECHNICAL ENGINEER MUST BE PRESENT DURING THESE
EFFORTS TO GUIDANCE AND OBSERVATION.
2. UNDERCUT ANY AREAS WHICH APPEAR WET, LOOSE, SOFT,
UNSTABLE, OR OTHERWISE UNSUITABLE, AS DIRECTED BY THE
GEOTECHNICAL ENGINEER. BACKFILL UNDERCUT EXCAVATIONS WITH
IMPORTED STRUCTURAL FILL.
3. THE NEW BARN STRUCTURES CAN BE SUPPORTED USING SPREAD
FOUNDATIONS, WHICH MAY BEAR ON UNDISTURBED INDIGENOUS
CLAY SOILS, OR ON DRAINAGE STONE. IF GROUNDWATER
CONDITIONS ARE ENCOUNTERED IN THE SPREAD FOUNDATION
EXCAVATIONS, OR IF THE EXPOSED FOUNDATION BEARING GRADES
WILL BE EXPOSED TO WET WEATHER CONDITIONS BETWEEN THE
TIME OF EXCAVATION AND THE TIME THE FOOTINGS ARE POURED,
PROTECT THE EXPOSED BEARING GRADES WITH A 6-INCH THICK
LAYER OF DRAINAGE STONE.
4. CONTINUOUS WALL FOUNDATIONS MUST BE AT LEAST 1.5 FEET IN
WIDTH AND ISOLATED COLUMN FOUNDATIONS MUST BE AT LEAST 2.5
SQUARE FEET. EXTERIOR FOUNDATIONS MUST BE EMBEDDED A
MINIMUM OF 4.0 FEET BELOW FINISHED EXTERIOR GRADES FOR
FROST PROTECTION.
5. SIZE SPREAD FOUNDATIONS USING A MAXIMUM ALLOWABLE SOIL
BEARING PRESSURE OF 3,000 POUNDS PER SQUARE FOOT.
6. BASED ON SOILS CONDITIONS ENCOUNTERED IN THE TEST BORINGS,
THE SITE CAN BE CLASSIFIED AS SEISMIC SITE CLASS "D".
UDIG NY: CALL 811 BEFORE YOU DIG:
CALL BEFORE YOU DIG: IF YOU PLAN TO DIG OR DO ANY TYPE OF
EXCAVATION WORK, NEW YORK STATE LAW REQUIRES YOU CALL DIG
SAFELY NEW YORK PRIOR TO DOING SO.
2. WAIT THE REQUIRED TIME: YOU NEED TO PROVIDE TWO FULL WORKING
DAYS NOTICE PRIOR TO STARTING YOUR WORK, NOT COUNTING THE
DAY OF YOUR CALL, WEEKENDS OR HOLIDAYS. THIS PROVIDES TIME
FOR THE UTILITIES TO LOCATE YOUR PROPOSED DIG SITE.
3. CONFIRM UTILITY RESPONSE: DIG SAFELY NEW YORK WILL NOTIFY ALL
MEMBER UTILITIES OF THE PENDING EXCAVATION SO THAT THAT THEY
CAN COME OUT AND MARK THE LOCATION OF THEIR UNDERGROUND
LINES. BEFORE DIGGING ON YOUR STATED COMMENCEMENT DATE
CONFIRM THAT ALL UTILITIES HAVE RESPONDED TO YOU INDICATING
THEY HAVE MARKED YOUR PROPERTY OR THEY HAVE NO FACILITIES
PRESENT.
4. RESPECT THE MARKS: BEFORE YOU BEGIN YOUR EXCAVATION, WALK
THROUGH THE SITE TO FAMILIARIZE YOURSELF WITH THE MARKINGS
AND THE LOCATIONS OF BURIED FACILITIES.
5. DIG WITH CARE: IT IS IMPORTANT EXCAVATORS TAKE A PROACTIVE
APPROACH TO SAFETY NOT ONLY FOR THEMSELVES BUT FOR THE
PUBLIC BY INITIATING THE ONE CALL PROCESS AND ADHERING TO THE
FIVE STEPS OF A SAFE EXCAVATION.
ACCESSIBLE SIDEWALKS AND CURB RAMP NOTES:
DIMENSIONS SHOWN IN THE DETAILS AS MINIMUMS AND
MAXIMUMS ARE THE LIMITS FOR DESIGN AND FIELD LAYOUT.
FACILITIES SHALL NOT BE CONSTRUCTED WITH VALUES
OUTSIDE THE LIMITS FOR WORK ACCEPTANCE. SEE TABLE
"DESIGN ELEMENT TOLERANCES" BELOW.
2. TO CHECK FIELD LAYOUT AND TO VERIFY WORK ACCEPTANCE,
ALL SLOPES AND GRADES WILL BE MEASURED WITH A 4' LONG
DIGITAL LEVEL USING AT LEAST TWO READINGS. WHERE THE
READINGS VARY, THE MEASUREMENTS WILL BE AVERAGED.
GRADE (RUNNING SLOPE) WILL BE MEASURED ALONG THE
CENTERLINE AND OFFSET 12" TO 18" FROM THE CENTERLINE.
CROSS SLOPES WILL BE MEASURES PERPENDICULAR TO
CENTERLINE AT 5' TO 10' INTERVALS.
3. GRADES (RUNNING SLOPES) ARE MEASURED IN THE DIRECTION
OF PEDESTRIAN TRAVEL. CROSS SLOPES ARE MEASURED
PERPENDICULAR TO THE DIRECTION OF PEDESTRIAN TRAVEL.
4. JOINTS BETWEEN SIDEWALKS, CURB RAMPS, TURNING SPACES
AND ROADWAYS SHALL BE FLUSH AND FREE FROM ABRUPT
VERTICAL CHANGES GREATER THAN 1
4". VERTICAL SURFACE
DISCONTINUITIES BETWEEN 1
4" TO 1
2" SHALL BE BEVELED WITH A
SLOPE NOT STEEPER THAN 1:2. THE BEVEL SHALL BE APPLIED
ACROSS THE ENTIRE JOINT.
5. THE CROSS SLOPE OF PEDESTRIAN ACCESS ROUTES SHALL BE
1.5% MAXIMUM FOR DESIGN AND LAYOUT, AND 2% MAXIMUM FOR
WORK ACCEPTANCE.
6. THE RUNNING SLOPE OF PEDESTRIAN ACCESS ROUTES SHALL BE
4.5% MAXIMUM FOR DESIGN AND LAYOUT, AND 5% MAXIMUM FOR
WORK ACCEPTANCE.
7. THE MINIMUM WIDTH OF A CURB RAMP SHALL BE 4'.
8. THE GRADE (RUNNING SLOPE) OF A CURB RAMP SHALL BE A
MINIMUM OF 5%. THE GRADE FOR DESIGN AND LAYOUT SHALL BE
A MAXIMUM OF 7.5%, THE GRADE FOR ADA ACCESSIBILITY AND
WORK ACCEPTANCE SHALL BE A MAXIMUM OF 8.3%. THE
MAXIMUM VERTICAL RISE OVER THE LENGTH OF THE CURB RAMP
FOR ACCEPTANCE SHALL BE 6".
9. THE CROSS SLOPE OF THE CURB RAMP SHALL BE AS FLAT AS
POSSIBLE AND STILL PROVIDE POSITIVE DRAINAGE. THE CROSS
SLOPE OF A CURB RAMP SHALL BE 1.5% MAXIMUM FOR DESIGN
AND LAYOUT, AND 2% MAXIMUM FOR WORK ACCEPTANCE.
10. WHERE A PEDESTRIAN CIRCULATION PATH CROSSES A CURB
RAMP, FLARED SIDES SHALL BE INSTALLED WITH A MAXIMUM
SLOPE OF 9.5% FOR DESIGN AND LAYOUT, AND 10% MAXIMUM
FOR WORK ACCEPTANCE. THE SLOPE OF THE FLARED SIDES IS
MEASURED PARALLEL TO THE CURB LINE.
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
ST
ATE OF NE WYORK
010' 20'20'
CIVIL-EXISTING CONDITIONS PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0-
EX
IS
TI
N G
C O
N D
IT
IO
N S.
dw g
6/
/2
:3 9:
P
M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C100
EXISTING LEGEND
BENCHMARK
CONTROL BASELINE
CONTROL BASELINE TIE
CONTROL BASELINE SPUR
SPIKE POINT
STAKE POINT
NAIL POINT
RAILROAD SPIKE POINT
CONTROL SURVEY MARKER
HORIZ. PHOTOGRAMMETRY POINT
VERT. PHOTOGRAMMETRY POINT
MONUMENT POINT
MISC MONUMENT POINT
CROSS CUT POINT
DRILL HOLE POINT
FENCE LOCATION POINT
CAPPED IRON PIPE
IRON PIPE
SANITARY MANHOLE
CATCH BASIN
CATCH BASIN - ROUND
CURB INLET
STORM MANHOLE
WATER MANHOLE
ELECTRIC MANHOLE
COMMUNICATION MANHOLE
GAS MANHOLE
STEAM MANHOLE
TELEPHONE MANHOLE
UNKNOWN MANHOLE
DRYWELL
YARD DRAIN
SEWER WETWELL
WATER WELL
UNKNOWN WELL
FIRE HYDRANT
FIRE HOSE CONNECTION
SPIGOT
GATE VALVE
POST INDICATOR VALVE
WATER METER
ELECTRIC METER
TELEPHONE BOX
UTILITY POLE
DECIDUOUS TREE
CONIFEROUS TREE
DECIDUOUS SHRUB
CONIFEROUS SHRUB
TREE STUMP
TREE WITH WIRE
SINGLE POST SIGN
DOUBLE POST SIGN
DELINEATORS
PARKING METER
WOOD POST
BOLLARD
GUY WIRE
GUIDE POST
GUIDE ANCHOR
BORE HOLE
MONITORING WELL
GAS VALVE
UNKNOWN VALVE
UNKNOWN VENT
UNKNOWN FILL CAP
TOP OF HOOD
ELECTRICAL JUNCTION BOX
JUNCTION BOX
FIRE ALARM
UNKNOWN UTILITY BOX
WETLAND FLAG
CLEANOUT
DRAINAGE INVERT
CURB STOP
ROOF DRAIN
BENCH
AC UNIT
GENERATOR
ADA PAD
FLAG POLE
PAPER BOX
MAILBOXPARKING METER
ROCK
REFERENCE MARKER SIGN
GAS VENT
FUEL PUMP
TELEPHONE LINE MARKER
FIBER OPTIC MARKER
OIL LINE MARKER
GAS METER
GAS MARKER
UTILITY MARKOUT POINT
DEAD UTILITY POLE
LIGHT POLE
SINGLE LIGHT
DOUBLE LIGHT
UTILITY POLE WITH LIGHT
PEDESTRIAN POLE
TRAFFIC CONTROL SIGNAL POLE
TRAFFIC CONTROL BOX JUNCTION
TRAFFIC CONTROL BOX PULL
LIGHT POST
FLOODLIGHT
SECURITY LIGHT
ELECTRIC TRANSMISSION POLE
GROUND ROD
OUTLET
BUILDING LINE
SPOT ELEVATION
MINOR CONTOUR
MAJOR CONTOUR
WOODS LINE
PLANTING BED
CULVERT
STORM LINE
SANITARY LINE
COMBINED SEWER
OVERHEAD SANITARY LINE
SANITARY FORCEMAIN LINE
OVERHEAD SAN. FORCEMAIN
OVERHEAD POWER LINE
ELECTRIC LINE
ELECTRIC AND COMM. LINE
WATER LINE
IRRIGATION WATER LINE
COMMUNICATION LINE
OVERHEAD COMM. LINE
TELEPHONE LINE
OVERHEAD TEL. LINE
FIBER OPTIC LINE
OVERHEAD FIBER OPTIC LINE
GAS LINE
OVERHEAD GAS LINE
FUEL LINE
OVERHEAD FUEL LINE
OVERHEAD WIRES
CABLE TV
OVERHEAD CABLE TV
OVERHEAD ELECTRIC, TELEPHONE,
CABLE
TRAFFIC LINE
OVERHEAD TRAFFIC LINE
STEAM LINE
UNIDENTIFIED PIPE
UNIDENTIFIED CABLE
UNID. UNDERGROUND LINE DITCH
WETLAND LIMITS
SILT FENCE
CHAIN LINK FENCE
WOOD FENCE
WIRE FENCE
STONE FENCE
GUIDERAIL
RAILING
EDGE OF WATER
ACCESS EASEMENT
RIGHT-OF-WAY EASEMENT
STORM LINE
UTILITY LINE
PROPERTY LINE
ADJOINING PROPERTY LINE
SUBDIVISION LINE
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
4"x4"x4" DOUBLE WYE
INV.678.83
45° BEND
INV.678.83
18 18
24242424 18
20 20 20
20 20 20 20 20
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
DEDUCT ALTERNATE NO. 1
REMOVALS NOTES:
1 REFER TO ELECTRICAL PLANS FOR ELECTRICAL REMOVALS.
2 PROTECT EXISTING BUILDING FACADES. REPAIR ANY DAMAGE DURING
CONSTRUCTION AT NO ADDITIONAL COST TO THE OWNER, INCLUDING
DAMAGE TO EXISTING ASPHALT TO REMAIN.
3 THE CONTRACTOR, AT THEIR OWN RISK, MAY RECYCLE ON-SITE
MATERIALS FOR USE ON THE PROJECT SITE IF THE INSTALLED MATERIAL
MEETS THE SPECIFICATIONS FOR THAT MATERIAL. THE BID PRICE SHALL
BE BASED UPON THE REMOVAL AND DISPOSAL OF THE UNCLASSIFIED
EXCAVATION MATERIALS FOR PLACEMENT OF NEW PAVEMENT AND
SIDEWALK SECTIONS, INCLUSIVE OF SUBBASE MATERIALS.
REMOVAL KEY NOTES:
1 REMOVE SIGN, STORE FOR REUSE
2 REMOVE SIGN, RETURN TO VA
3 REMOVE SIGN, BASE AND POSTS TO REMAIN
4 SIGN TO REMAIN, PROTECT DURING ENTIRE CONSTRUCTION PROCESS
5 REMOVE CONCRETE CURBING TO EXTENTS SHOWN
6 SAWCUT PAVEMENT
7 STORM SEWER STRUCTURE TO REMAIN, ADJUST FRAME & GRATE/COVER
TO MATCH PROPOSED GRADE, SEE SHEET C140
8 REMOVE CATCH BASIN IN ITS ENTIRETY
9 REMOVE STORM SEWER PIPE
10 ELECTRIC MANHOLE TO REMAIN, PROTECT DURING ENTIRE
CONSTRUCTION PROCESS
11 STORM SEWER MANHOLE TO REMAIN, PROTECT DURING ENTIRE
CONSTRUCTION PROCESS
12 REMOVE CONCRETE STAIRS AND FOUNDATION
13 REMOVE LIGHT POLE AND FOUNDATION, REFER TO ELECTRICAL PLANS
14 REMOVE TREE, INCLUDING STUMP
15 FIRE HYDRANT TO REMAIN, MAINTAIN ACCESS DURING ENTIRE
CONSTRUCTION PROCESS
16 REMOVE BUILDING AND STORE, COORDINATE NEW LOCATION WITH COR
17 CONCRETE CURB TO REMAIN, PROTECT DURING ENTIRE CONSTRUCTION
PROCESS
18 REMOVE EXISTING STRIPING
19 REMOVE BOLLARD AND FOOTING
20 PROTECT COLUMN DURING ENTIRE CONSTRUCTION PROCESS
21 CATCH BASIN TO REMAIN, PROTECT DURING ENTIRE CONSTRUCTION
PROCESS
22 BRICK AND MORTAR PIPE PENETRATION INTO STRUCTURE. MORTAR
BOTH INSIDE AND OUTSIDE OF STRUCTURE.
23 REMOVE SHRUBS
24 REMOVE METAL GUIDERAIL AND FOOTING
25 REMOVE OVERHEAD ELECTRICAL AND POWER POLE, REFER TO
ELECTRICAL PLANS
26 REMOVE NATURAL GAS LINE TO EXTENTS SHOWN
27 REMOVE WHEELCHAIR SHELTER, TURN OVER TO VA
28 TREE TO REMAIN, PROTECT DURING ENTIRE CONSTRUCTION PROCESS
29 REMOVE ELECTICAL CONDUIT TO EXTENTS SHOWN
010' 20'20'
CIVIL-REMOVALS PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- R
EM
O
VA
LS
.d w g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C110
LINEAR OBJECT REMOVAL
ASPHALT MILLING
ASPHALT REMOVAL, DRIVES
CONCRETE REMOVAL
BUILDING REMOVAL
KEY NOTE
REMOVALS LEGEND
PAVEMENT SANDBLASTING
OBJECT REMOVAL
TEMPORARY TREE PROTECTION
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
LOADING ZONE LOADING ZONE AMBULANCE PARKING ONLY
CONCRETE CURB,
SEE DETAIL 13/C500
PARKING STALL STRIPING, TYP.,
SEE DETAIL 7/C502
CURB RAMP,
SEE DETAIL
8/C501
CONCRETE CURB,
SEE DETAIL 12/C500
CONCRETE CURB, TYP.,
SEE DETAIL 12/C500
REINSTALL WHEELCHAIR SHELTER,
REPLACE DAMAGED PARTS IN KIND.
FLUSH CURB
W/TACTILE WARNING, TYP.,
SEE DETAIL 9/C501
CROSSWALK,
SEE DETAIL 5/C502
TACTILE WARNING, TYP.
SEE DETAIL 10/C501
6" BOLLARD, TYP.
SEE DETAIL 2/C501
LIGHT POLE, TYP.,
SITE LIGHTING NOTE 1
PAVEMENT STRIPING,
SEE DETAIL 2/C502
CROSSWALK,
SEE DETAIL 5/C502
CURB RAMP,
SEE DETAIL 9/C501
CONCRETE SIDEWALK
SEE DETAIL 1/C501
DIRECTIONAL ARROWS, TYP.,
SEE DETAIL 3/C502
444 4 4 4
STOP BAR AND LETTERING, TYP.,
SEE DETAIL 4/C502
CURB RAMP, SEE
DETAIL 8/C501
WALL
MOUNTED
10 10 4 10 10 1010 3 3 3 3
3 3
CONCRETE RETAINING WALL,
SEE STRUCTURAL PLANS
RAISED ASPHALT CROSSWALK,
SEE DETAIL 11/C501
CROSSWALK,
SEE DETAIL 5/C502
LOADING ZONE
PAVEMENT STRIPING,
SEE DETAILS 2&8/C502
AMBULANCE PARKING
PAVEMENT STRIPING,
SEE DETAILS 2&9/C502
SEGMENTED CONCRETE
RETAINING WALL, SEE DETAIL 7/C501
1212121212121212121212
(4)6" BOLLARDS
SEE DETAIL 2/C501
(2)6" BOLLARD,
SEE DETAIL 2/C501
(3)6" BOLLARD,
SEE DETAIL 2/C501
TACTILE WARNING, TYP
SEE DETAIL 10/C501
℄ PAVEMENT STRIPE,
SITE DETAIL 2/C502
ELECTRICAL HANDHOLE
PARKING STALL STRIPING, TYP.,
SEE DETAIL 1/C502
CROSSWALK,
SEE DETAIL 5/C502
WALL
MOUNTED
WALL
MOUNTED
WALL
MOUNTED (13)LIGHTED BOLLARD, TYP.
SEE DETAIL 17/C502
CONCRETE STAIRS, CONCRETE
CHEEKWALL AND RAILINGS,
SEE DETAILS 1,2&3/C503
(19)TUBULAR SIGN
POSTS, SEE DETAIL
3/C501
(8)6" BOLLARD,
SEE DETAIL 2/C501
CONCRETE CURB,
SEE DETAIL 13/C500
CONCRETE CURB,
SEE DETAIL 12/C500
CONCRETE SIDEWALK
W/GUARDRAIL, SEE DETAILS
1&5/C501
CONCRETE SIDEWALK
SEE DETAIL 1/C501
PARKING STALL STRIPING, TYP.,
SEE DETAIL 1/C502
PARKING STALL STRIPING, TYP.,
SEE DETAIL 1/C502
WAYFINDING SIGN C1
SEE 1/AW604
WAYFINDING SIGN C2
SEE 2/AW604
WAYFINDING SIGN C6
SEE 5/AW604
WAYFINDING SIGN C5
SEE 4/AW604
WAYFINDING SIGN C3
SEE 3/AW604
GUARDRAIL, SEE
DETAIL 5/C501
NOTE:
DEDUCT ALTERNATE NO. 1 TO
INCLUDE ALL PARKING LOT 1
010' 20'20'
CIVIL-MATERIALS, SIGNAGE
AND STRIPING PLAN
STANDARD SIGNAGE SCHEDULE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- M
AT
ER
IA
LS
.d w g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C120
SITE LIGHTING NOTES:
1. SITE LIGHTING SHOWN FOR REFERENCE ONLY.
REFER TO E-SERIES DRAWINGS FOR DESIGN
INFORMATION.
MATERIAL PLAN NOTES:
1. SUBBASE MATERIAL AND THE VARIOUS
ASPHALT CONCRETE MATERIALS CALLED FOR IN
THESE DRAWINGS SHALL CONFORM WITH THE
REFERENCED SECTION OF THE NEW YORK
STATE DEPARTMENT OF TRANSPORTATION
STANDARD SPECIFICATIONS FOR
CONSTRUCTION AND MATERIALS, LATEST
EDITION. CONSTRUCTION SHALL BE AS
FURTHER SET FORTH IN THOSE
SPECIFICATIONS AND AS OTHERWISE PROVIDED
FOR IN THESE DRAWINGS.
2. PLACE ASPHALT CONCRETE MIXTURE ON
PREPARED SURFACE, SPREAD AND STRIKE-OFF
USING A SELF-PROPELLED PAVING MACHINE,
WITH VIBRATING SCREED. PLACEMENT IN
INACCESSIBLE AND SMALL AREAS MAY BE BY
HAND.
3. PROVIDE JOINTS BETWEEN OLD AND NEW
PAVEMENTS OR BETWEEN SUCCESSIVE DAY'S
WORK.
4. INSTALL TACK COAT AS SPECIFIED.
5. AFTER COMPLETION OF PAVING AND
SURFACING OPERATIONS, MAINTAIN CLEAN
SURFACES FROM EXCESS OR SPILLED ASPHALT,
GRAVEL, STONE MATERIALS AND DEBRIS.
6. PROVIDE TOPSOIL AND HYDROSEED IN AREAS
OF EXISTING LAWN DISTURBED OR NEW LAWN
CREATED. REFER TO LANDSCAPE PLAN.
P Government Vehicles Only
ASPHALT PAVEMENT MILL
AND FILL, SEE DETAIL 10/C500
ASPHALT PAVEMENT, FULL
DEPTH, SEE DETAIL 9/C500
CONCRETE PAVEMENT
SEE DETAIL 1/C501
MATERIAL LEGEND:
■ ■ ■ ■ ■ ■ ■ ■ ■ ■ HAND RAIL
PEDESTRIAN CROSSWALK
SIGN
6" BOLLARD
MOTORCYCLE
PARKING
ONLY
DO NOT
ENTER
VAN
ACCESSIBLE
RESERVED
PARKING
STOP
NO
PARKING
ANY
TIME
NO
PARKING
ANY
TIME
HEAVY-DUTY CONCRETE PAVEMENT
SEE DETAIL 6/C501
CONCRETE CURB
7'-0"
VAN
ACCESSIBLE
RESERVED
PARKING
LIGHTED BOLLARD
FIRE HYDRANT
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
5.0'
5.0'
R4.5'
R4.5'
R4.5'8.6'9.0'
TYP.
9.0'
TYP.
.8'
TY
P.
8.4'
R4 .5'
LOADING ZONE LOADING ZONE AMBULANCE PARKING ONLY
R10.0'
R4.5'
7.0'
24.0'
24.0'
8.0'TYP.
8.0'TYP.
18.5' 9.0'
26.
1'
TYP.
18.0' TYP.
R3.0
R53.0'
R220.0'
R22.0'
R3.0'
R1 1.0
R10.
0' R5.0'
.5'
TY
P.
R196.0'
R13.0'
102.1'
8.5'
TYP.
5.0'
8.0'
R4.5'
R4.5'
R4.5'
R4.5'
R4.5
R4.5'
R4.5
R4.5'
R4.5
R4.5'
R4.5
R4.5'
R3 .0'R5.0
8.5
TY
P.
R3.0'
R3.0
6.5'
6.3 ' 5.0'
18.6'
4.0 ' T
YP
R29.0'
R50.0'
135°
45°
5.0'
R10.0'
18.7'11.3'
TYP.
R3 0.0
R4.5' R4.5'
R4.5'
5.0'
TYP.
5,0'
TYP.
R4.5'
R10.
0'
8.5' TYP.
.5'
TY
P.
24.3'
24.8'
24.6'
25.6'
24.0'
.0'
R5.0' R2.0'
R46.0'
5.0
6.0'
6.0
5.0'
5.0'
010' 20'20'
CIVIL-LAYOUT PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0-
LA
YO
U
T.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C130
LAYOUT PLAN NOTES:
1. THE CONTRACTOR SHALL BE RESPONSIBLE FOR DOCUMENTING
ALL FIELD LAYOUT. THE CONTRACTOR SHALL TAKE TIES TO ALL
UTILITY CONNECTIONS AND PROVIDE MARKED-UP AS BUILT
PLANS FOR ALL UTILITIES SHOWING TIES TO CONNECTIONS,
BENDS, VALVES, LENGTHS OF LINES AND INVERTS.
2. CONTRACTOR SHALL UTILIZE A LICENSED NYS SURVEYOR TO
PROVIDE STAKING AND ASSIST THE CONTRACTOR WITH
PROPER LAYOUT AND COLLECTIVE AS-BUILT INFORMATION.
3. AS-BUILT PLANS SHALL BE REVIEWED BY THE VA AND THE AOR.
THE CONTRACTOR SHALL PROVIDE ANY CORRECTION OR
ADDITIONS TO THE SATISFACTION OF THE VA AND THE AOR
BEFORE UTILITIES WILL BE ACCEPTED.
WHEELCHAIR HUT
ACCESS AREA
SEE INSET THIS SHEET
INSET 05' 10'10'
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
LOADING ZONE LOADING ZONE AMBULANCE PARKING ONLY
DS 4
NEW TF:687.64
DSM2
NEW TF:685.14
CB101
TF:685.43
INV. IN:681.19
INV. IN:681.19
INV. OUT:681.19
CB102
TF:685.72
INV. OUT:682.12
68LF-12" CLASS III RCP
@ 1.4%
8LF-4" HPDE WALL
DRAIN @ 1.0%
NEW INV:682.26
CB100
TF:686.14
INV. IN:681.92
INV. OUT:681.92
76LF-12"
CLASS III RCP
@ 1.0%
DSM13
NEW TF:692.50
NEW INV IN(12"):685.30
NEW INV IN(4"):677.73CB103
TF:690.06
INV. OUT:686.20
92LF-12" CLASS III RCP
@ 1.0%
NEW INV:
680.36
51LF-12" CLASS III RCP
@ 1.6%
4" PERF. HDPE
FOUNDATION DRAIN @0.0%
INV:678.83
110LF-4" HDPE
@ 1.0%
4" PERF. HDPE
FOUNDATION DRAIN @0.0%
INV:678.83
FIRE HYDRANT, 6" GATE VALVE,
AND 6" TAPPING SLEEVE
(CUT-IN CONNECTION NOT PERMITTED)
SEE DETAIL 4/C503
6" DIP WATER LINE
SEE DETAIL 6/C500
AND 4/C503
4"x4"x4" DOUBLE WYE
INV.678.83
45° BEND
INV.678.83
IN-PAVEMENT INLET FILTER, TYP,
SEE DETAIL 5/C-500
CATCH BASIN, TYP.,
SEE DETAIL 7/C-500
ADJUST FRAME AND GRATE
OF EX. CATCH BASIN,
SEE DETAIL 8/C-500
ADJUST FRAME AND GRATE
OF EX. STORM MANHOLE,
SEE DETAIL 7/C-500
ADJUST FRAME AND GRATE
OF EX. STORM MANHOLE,
SEE DETAIL 8/C-500
INSULATE EXISTING WATER LINES,
SEE DETAIL 6/C-500
RELOCATED GAS LINE
FUTURE TUNNEL
EXPANSION, SHOWN
FOR REFERENCE ONLY.
SEE NOTE 1.
WATER STAND PIPE,
REFER TO MEP PLANS
BUILDING WALL LIGHT, TYP.
SEE ELECTRICAL PLANS
ELECTRICAL CLOSET
SEE ELECTRICAL PLANS
BUILDING WALL LIGHT, TYP.
SEE ELECTRICAL PLANS
BRANCH ELECTRICAL PLANS CIRCUIT
SEE ELECTRICAL PLANS
LIGHT POLE, TYP.
SEE ELECTRICAL PLANS
ELECTRICAL HANDHOLE, TYP.
SEE ELECTRICAL PLANS
010' 20'20'
CIVIL-UTILITIES AND EROSION
AND SEDIMENT CONTROL PLAN
AND PROFILE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- U
TI
LI
TY
A
N D
E C
.d w g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C140
LEGEND:
IN-PAVEMENT INLET FILTER
CATCH BASIN
STORM SEWER MANHOLE
GAS LINE BY OTHERS
ELECTRIC LINE BY OTHERS
LIGHT POLE
NOTES:
1. CONTRACTOR TO COORDINATE WITH
AOR ALL UTILITIES IN THIS AREA
PRIOR TO CONSTRUCTION TO AVOID
CONFLICTS IN FUTURE WORK.
2. REFER TO SHEET C-130 LAYOUT PLAN
REGARDING THE CONTRACTOR'S
RESPONSIBILITY IN DOCUMENTING
UTILITY INSTALLATION.
STORM SEWER CLEANOUT
WATER LINE
STORM SEWER UNDERDRAIN LINE
STORM SEWER LINE
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
TC/BC:
687.05
TC:687.82
BC:687.32
TC/BC:
687.32
TC:687.72
BC:687.22
TC:687.90
BC:687.40
TC/BC:
687.32
TC:687.82
BC:687.32
TC/BC:
687.00
TC:687.72
BC:687.22
TC/BC:
687.31
687.11
687.21
687.21
687.06
687.26
687.18
690689
690 691 693
1 69
685 68
LOADING ZONE LOADING ZONE AMBULANCE PARKING ONLY
ME:
TC:689.6±
BC:689.3±
ME:
689.4±
ME:
686.1±
ME:
685.4±
ME:
685.4±
ME:
685.0±
ME:
TC:684.6±
BC:684.1± TC:684.95
BC:684.45
TC:685.18
BC:684.68
TC/BC:
685.50
TC:685.69
BC:685.19
TC:693.64
BC:693.14
TC:692.67
BC:692.17
TC:693.17
BC:692.67
TC/BC:
689.84
TC:691.68
BC:691.18
TC:692.36
BC:691.86
TC:685.92
BC:685.42
692.56
TC/BC:
685.56
TC:692.38
BC:691.88
TC:686.70
BC:686.20
TC:686.70
BC:686.20
686.00
686.00
685.90
TC:692.19
BC:691.69
691.88
TC:689.04
BC:688.54 TC:694.13
BC:693.63
ME:
TC:688.3±
BC:687.8±
TC/BC:
688.43
686.00
686.00
TC:693.14
BC:692.64
TC:692.83
BC:692.33
TC:692.76
BC:692.26
TC:692.35
BC:692.14
TC:693.91
BC:693.41
TC/BC:
688.47 693.1
TC:688.49
BC:687.99
TC:688.50
BC:688.00
TC:688.13
BC:687.63
TC:684.33
BC:683.83
TC:683.63
BC:683.13
TC:689.28
BC:688.78
693.08
ME:
682.8±
683.00
687.85
688.50
ME:
TC:688.9±
BC:688.4±
TC:693.27
BC:692.77
TC:692.30
BC:691.80
692.46
TC/BC:
691.96
TC:684.65
BC:684.15
685.58
TC:693.22
BC:692.72
TC:692.58
BC:692.08
BC:693.34
TC:693.45
BC:692.95
692.88
TC:693.33
BC:692.83
TC:692.67
BC:692.17
TC:692.01
BC:691.51TC:690.92
BC:690.42
TC:691.57
BC:691.07
BC:692.67BC:691.81BC:691.37BC:690.93BC:690.50TC/BC:
690.06
TC:693.91
BC:693.41
TC:693.83
BC:693.33
TC:693.02
BC:692.52
TC:692.01
BC:691.51
TC:691.37
BC:690.87
TC:690.31
BC:689.81
TC:693.97
BC:693.47
693.06 693.21
TC:693.22
BC:692.72
692.40
TC:693.63
BC:693.13
TC/BC:
688.34
TC:690.15
BC:689.65 690.11 690.55 690.99 691.42 691.85 692.29 692.95
BC:692.24
688.71
TC:690.63
BC:690.13
688.71688.71
693.07 693.03 692.78693.07
692.67
ME:687.2±
688.18
TC:692.83
BC:692.33
TC:692.89
BC:692.39
TC:693.89
BC:692.39
692.89
692.39
692.39 692.66
TF:692.50
TF:687.64
TC:691.99
BC:691.49
ME:
683.3±
ME:
683.3±
TC:685.79
BC:685.29
ME:
685.3±
TC:686.64
BC:686.14
TC/BC:
686.47
TC/BC:
686.34
TC:686.51
BC:686.01
HP
685.89
TF:685.43
TC:686.33
BC:685.83
TC/BC:
685.75
TC/BC:
685.62
ME:
685.4±
TC:686.41
BC:685.91
689.78
686.71
687.54
686.41
686.48
686.58
686.30
TC/BC:
685.59
TC:686.23
BC:685.73
685.66
TC:686.50
BC:686.00
TC:688.77
BC:688.27
TC:688.83
BC:688.33
TC:688.75
BC:688.25
TC:688.73
BC:688.23
TC:688.05
BC:687.55
TC:684.40
BC:683.90
TC:683.35
BC:682.85
TC:685.86
BC:685.36
TC:685.20
BC:684.70
TC:685.91
BC:685.41
TC:685.00
BC:684.50
TC:686.80
BC:686.30
TC:686.43
BC:685.93
TC:686.74
BC:686.24
TC:686.29
BC:685.79
TC:687.39
BC:686.87
TC:687.17
BC:686.67
TC:687.30
BC:686.80
TC:687.04
BC:686.54
TC:687.68
BC:687.18
TC:687.53
BC:687.03
TC:687.62
BC:687.12
TC:687.41
BC:686.91
TW:691.07
BW:688.07
TW:693.07
TC:688.79
BC:688.29
686.7
TW:693.07
TW:692.07
TW:692.07
TW:691.07
TC:686.51
BC:686.01
693.07693.07
692.91
ME:
688.5±
ME:
688.2±
BS:691.90
BS:688.40
BS:692.00
BS:688.50
ME:
TC:687.7±
BC:687.2±
ME:
TC:687.8±
BC:687.3±
692.46
TC:692.54
BC:692.04
TF:685.72
TC:686.50
BC:686.00
TC:692.97
BC:692.59
TC/BC:
692.67 TC:693.13
BC:692.63
692.97
010' 20'20'
CIVIL-GRADING PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- G
R
AD
IN
G
.d w g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C150
INSET 05' 10'10'
300.00
ME:
310.2±
TC:327.70
BC:327.20
TW:350.25
BW:345.10
HP:
318.50
GRADING LEGEND:
SPOT ELEVATION
SPOT ELEVATION - MATCH
EXISTING ELEVATION
SPOT ELEVATION - TOP OF
CURB AND EDGE OF PAVEMENT
TOP OF WALL AND BOTTOM OF WALL
SPOT ELEVATION - HIGH POINT
TOPOGRAPHIC CONTOUR LINE350
FOR GRADING IN THIS AREA
SEE INSET, THIS SHEET
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
LOADING ZONE LOADING ZONE AMBULANCE PARKING ONLY
TREE PLANTING WITH BARK
MULCH, SEE DETAIL 13/C-502
SHRUB PLANTING
(TYP.) 12/C-502
PERENNIAL MASS
PLANTING (TYP.) SEE
DETAIL 15/C-502
STONE MULCH, TYP.
SEE DETAIL 10/C-502
(9) PLACED BOULDERS:
ONONDAGA LIMESTONE,
600 LBS EA.
ORNAMENTAL GRASS
PLANTING (TYP.) SEE
DETAIL 14/C-502
TOPSOIL AND TURF,
TYP.
BIKE RACKS
SEE DETAIL 11/C-502
(2) PLACED BOULDERS:
ONONDAGA LIMESTONE,
600 LBS EA.
TOPSOIL AND TURF,
TYP.
BENCHES
SEE DETAIL 10/C-502
010' 20'20'
LANDSCAPE PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0-
LA
N D
SC
AP
IN
G
.d w g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C160
PLANT SCHEDULE
Type Abbrv. Scientific Name Common Name Size/Form Spacing Remarks Grasses:
SH Sporobolis heterolepis Prairie Dropseed #1 Pot 30-36" o.c.
Perennials:
LM Liriope muscari Lily Turf #1 Pot 12-18" o.c. Sub. L. spicata MF Monarda fistulosa Wild Bergamot #1 Pot 18-24" o.c.
Shrubs:
CA Cotoneaster apiculatus Cranberry Cotoneaster#3 Pot, 1-2' Ht./Spread3-4' o.c.
CP Comptonia peregrina Sweetfern #3 Pot, 1-2' Ht. 36-48" o.c.
IV Itea virginica 'Henry's Garnet' Virginia Sweetspire #3 Pot, 1-2' Ht./Spread30-42" o.c.
JH Juniperus horizontalis 'Blue Chip' Creeping Juniper #3 Pot 24-30" o.c. 1 Male & 1 Female
SN Spiraea nipponica 'Snowmound' Spiraea Snowmound #3 Pot, 1-2' Ht./Spread36-48" o.c.
Trees:
AG Amelanchier x grandiflora 'Robin Hill' Shadblow-White B&B, 6-8' Ht., >2" Cal.As Shown Single Stem AR Acer rubrum'October Glory' October Glory Red MapleB&B, 6-8' Ht., >2" Cal.As Shown BN Betula nigra 'Heritage' Heritage River Birch B&B, 5-6' Ht. As Shown Multi Stem JV Juniperus virginiana 'Canaertii' Canaertii Red Cedar B&B, 5-6' Ht. As Shown
LANDSCAPING LEGEND:
LANDSCAPE PLANT TAG
TOPSOIL AND TURF
STONE MULCH
PERENNIAL MASS PLANTING
SHRUB
ORNAMENTAL GRASS
EVERGREEN
SMALL TREE
TREE
BOULDERS
BIKE RACK
BENCH
PLANT SCHEDULE NOTES:
1. PLANT SUBSTITUTIONS MUST BE APPROVED BY AOR
PRIOR TO INSTALLATION.
TREE & SHRUB PLANTING NOTES:
1. REMOVE STONES 2" AND LARGER FROM EXCAVATED
PLANT PIT SOIL AND EXCAVATED PIT AREA.
2. DIG PIT DEPTH SAME AS ROOT BALL OR CONTAINER
DEPTH.
3. SET ROOT BALL (REMOVE ROOT BALL FROM
CONTAINERS) IN CENTER OF PIT SO TOP OF ROOT BALL
WHERE ROOTS FLARE OUT (ROOT FLARE/COLLAR) IS 1-2
INCHES ABOVE FINISH GRADE & VISIBLE (NOT COVERED
WITH SOIL); THE REST OF THE REMAINING TOP OF ROOT
BALL SHALL BE FLUSH WITH FINISH GRADE & COVERED
WITH PLANTING SOIL (TOPSOIL, SEE SPECS).
4. IF PLANT IS A CONTAINER: SLIGHTLY LOOSEN EDGES
AROUND ROOT BALLS: IF PLANT IS B&B: CUT OFF ALL
WIRE/ROPE ETC. AROUND ROOT BALL & DISPOSE OF
PROPERLY; FOLD BACK TOP HALF TO TWO-THIRDS OF
ROOT BALL LOOSENING ROOT FIBERS AT EXPOSED
EDGES; KEEP REMAINING BOTTOM PORTION OF ROOT
BALL IN BURLAP INTACT; APPLY ROOT ENHANCER AND
FERTILIZER TO ALL B&B AND CONTAINER TREES, CLUMPS,
AND SHRUBS.
5. SET PLANT STRAIGHT & PLUMB FROM ALL ANGLES; MAKE
SURE ROOT BALL IS NOT DRY-MOISTEN IF NEEDED;
INSTALL AS SPECIFIED; BACKFILL WITH APPROVED
TOPSOIL PARTIALLY; CHECK AGAIN TO ASSURE PLANT IS
STRAIGHT & PLUMB ADJUSTING AGAIN FOR APPROVAL;
FINISH BACKFILL WITH APPROVED TOPSOIL; SMOOTH OUT
EXCAVATION AREA AND CREATE 3"-4" HT. SAUCER FOR
WATERING ZONE.
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
.1
.3
.7
.1
.6
.5
.8
.8
.0
.0
1.
1.
.5
STORM SEWER
PROFILES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- U
TI
LI
TY
P
R O
FI
LE
S.
dw g 6/
/2
:3
9:
P M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024ISSUE FOR BID 08-09-2024 C200
CB100 - EX DS11 CB102 - CB1012
CB103 - EX DSM133
Registration Expires 10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
NOTES:
NOTES:
TEMPORARY SOIL STOCKPILE4
SILT FENCE INSTALLATION1 CONCRETE WASHOUT AREA2
SECTION
PERSPECTIVE VIEW
NOTES:
BAG DETAIL
IN-PAVEMENT INLET FILTER5
PLAN
SECTION
ASPHALT PAVEMENT SECTION9
NOTES:
NOTES
CONCRETE CURB13
PAVEMENT TRANSITION12
NOTE:
X X X X
CONCRETE SIDEWALK AT BUILDING14
NOTES:
TEMPORARY CONSTRUCTION FENCE AND GATE3
FENCE USING FOOT PLATES
STEEL PANEL STAND
SADDLE CLAMP DETAIL
CONSTRUCTION GATE
NOTES:
ALTER EXISTING DRAINAGE STRUCTURE8
PIPE CONNECTION TO DRAINAGE STRUCTURE
CEMENT GROUT SEAL JOINT11
CURB INSTALLATION AT EXISTING PAVEMENT15
SECTION
PLAN
STORM CATCH BASIN (SQUARE) - PRECAST7
WATER PIPE
TRENCH AND BEDDING6
NOTES
NOTES:
STORM SEWER
PIPE TRENCH AND BEDDING16
NOTES:
ASPHALT PAVEMENT
MILLING AND RESURFACING10
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- D
ET
AI
LS
.d w g
6/
/2
:3 9:
P
M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024 C500
CIVIL-SITE DETAILS
Registration Expires
10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
X X X
PLAN
SECTION
EXPANSION JOINT
X
X
X
X
X
CONSTRUCTION JOINT
X X
CONTROL JOINT
TOOLED EDGE
NOTES:
CONCRETE PAVEMENT1
TACTILE WARNINGS FOR RAMPS10
NOTES:
DOME SECTION
DOME SPACING PLAN
PLAN
SINGLE POST
SIGN MOUNTING DETAIL4
CURB RAMP - DROP CURB8 CURB RAMP - DROP CURB9
TUBULAR POST
SIGN MOUNTING3
CONCRETE SIDEWALK WITH GUARDRAIL5
X X X X
POST SLEEVE DETAIL
PLAN
SECTION
EXPANSION JOINT CONSTRUCTION JOINT
CONTROL JOINT TOOLED EDGE
NOTES:
HEAVY DUTY CONCRETE PAVEMENT6
PLAN VIEW
AA
B
B
RAISED ASPHALT CROSSWALK11
SECTION A-A
SECTION B-B
LONGITUDINAL TRANSITION AREA - HOT MIX ASPHALT OVERLAY SPLICE
NOTES:
SEGMENTED CONCRETE
RETAINING WALL SECTION7
A
A
6" BOLLARD2
NOTES:
SECTION A-A
NOTES:
GUARDRAIL
HANDRAIL CONNECTION
TO GUARDRAIL
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- D
ET
AI
LS
.d w g
6/
/2
:3 9:
P
M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024 C501
CIVIL-SITE DETAILS
Registration Expires
10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
90° PARKING STALL STRIPING1
NO PARKING
LOADING ZONE STRIPING2 CROSSWALK5
DIRECTIONAL
ARROW STRIPING3 STOP LINE/LETTERING4
TREE PLANTING13
45° PARKING STALL STRIPING7
NOTES:
VAN
ACCESSIBLE
RESERVED
PARKING
NO
PARKING
ANY
TIME
RESERVED
PARKING
LOADING ZONE MARKINGS8
AMBULANCE PARKING MARKINGS9 STONE MULCH10
NOTES:
PERENNIAL MASS PLANTING15
SHRUB PLANTING12
NOTES:
ORNAMENTAL GRASS PLANTING14
ADA SYMBOL MARKINGS6
BIKE RACK11
NOTES:
NOTES:
NOTES:
NOTES:
NOTES: NOTES: NOTES: NOTES: NOTES:
NOTES:
NOTES:
LIGHTED BOLLARD17
DIRECT EMBEDMENT
NOTES:
BENCH16
NOTES:
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- D
ET
AI
LS
.d w g
6/
/2
:3 9:
P
M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024 C502
CIVIL-SITE DETAILS
Registration Expires
10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
STAIR SECTION1 CHEEK WALL3
RAILING DETAIL2
POST SLEEVE DETAIL
WATER MAIN RELOCATION5
TYPICAL HYDRANT INSTALLATION WITH BOLLARDS4
PLANELEVATION
NOTES:
VEGETATION PROTECTION FENCE6
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F:
\M
J1
- B uf fa lo V
A\ M
J1
3.
_C
0- D
ET
AI
LS
.d w g
6/
/2
:3 9:
P
M
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING RAMP EXPANSION
3495 BAILEY AVE., BUFFALO, NY 14215
528-18-375
Project Director
Revisions: Date:
www. bancroft-ae.com
3300 Dundee Rd.
Northbrook, IL 60062
T: 847.952.9362
08-09-2024
ISSUE FOR BID 08-09-2024 C503
CIVIL-SITE DETAILS
Registration Expires
10.31.2026
70 7 4 5 1
L
IC
E N
SE
D
PROFESSI ONAL
EN
G
I N E
E R
M
IC
H A
EL D . P AN I C
H
E L
LI
File details come from the government source that posted it. Updated .