04 - Drawings - General.pdf

PDF 45 MB Posted

Attached to
Y1LZ--TIERED SET-ASIDE - Parking Ramp Expansion Minor Construction - Buffalo VAMC 528-375
Solicitation number
36C77626R0046
Issued by

About this file

This is a set of architectural and general construction drawings for a parking ramp expansion project at Buffalo VA Medical Center. The project (528-375) involves the addition of two new parking levels (approximately 53,000 gross square feet each) to the top of the existing three-story parking structure, a new stair tower with two elevators spanning the full combined height, screening and signage throughout the garage, a new roadway to the east, reconfigured accessible parking and drop-off lanes, restored pedestrian crossings, structural restoration work on existing levels, and repainting of parking striping. The drawings establish comprehensive contractor requirements including basis-of-design (BOD) compliance protocols for equivalent substitutions requiring government approval, detailed protection protocols for occupied areas using fire-retardant poly sheeting and hardboard panels during work, and strict adherence to infection control procedures with sample Infection Control Risk Assessment (ICRA) and Interim Life Safety Measures (ILSM) forms provided.

The phased sequencing plan divides work into three sequences: Sequence A (stair/elevator tower construction, east roadway reconfiguration, lower-level sitework), Sequence B (existing garage restoration, upper-level additions with both workday and after-hours phases), and Sequence C (traffic island construction and site restoration). Critical operational requirements include maintaining egress pathways throughout construction, preserving emergency services access, performing noise-generating activities during off-hours (6 PM to 12 AM weekdays; weekends as authorized), closing Parking Lot A (89 spaces) for contractor staging with approximately 28 spaces for contractor parking, and maintaining the thru-lane traffic pattern within the existing parking structure. Nine deduct alternates are specified covering site work deletions, vinyl graphics substitution, photovoltaic canopy deletion, exterior screen and signage removal, structural restoration work deletions, infill screen system removal, single elevator deletion, glass guardrail substitution, and aluminum curtainwall substitution for precast concrete. All work must comply with 2021 applicable codes including NFPA 101 Life Safety Code, IBC 2021, NEC 2020, and OSHA standards.

View the file

Other files

File Type Posted
36C77626R0046 0006.pdf PDF
36C77626R0046 0005.pdf PDF
0005 - Responses to Tech Questions - 5-21-26.pdf PDF
0005 - DBA Wages - Erie County - 05-18-2026.pdf PDF
36C77626R0046 0004.pdf PDF
0004 - Responses to Tech Questions - 5-19-26.pdf PDF
0004 - SCA Wages - Erie County - 05-13-2026.pdf PDF
36C77626R0046 0003.pdf PDF
36C77626R0046 0002.pdf PDF
0002 - Responses to Tech Questions - 5-14-26.pdf PDF
0001 - 15A - SCA Wages - Erie County - 04-29-2026.pdf PDF
0001 - Subsurface Exploration Report - Question 58.pdf PDF
0001 - Site Visit Sign-in Sheet 4-22-26.pdf PDF
0001 - 36C77625R0023 Technical Questions - FINAL - Buffalo - 3-13-25 - UPDATED 5-1-26.pdf PDF
0001 - 1947 Soil Borings - Question 58.pdf PDF
0001 - Electrical Redesign - Questions 11 and 70.pdf PDF
36C77626R0046 0001.pdf PDF
02 - Specs Vol 2 of 2.pdf PDF
05 - Drawings - Civil.pdf PDF
08 - Drawings - Fire Protection.pdf PDF
15 - DBA Wages - Erie County - 01-02-2026.pdf PDF
01 - Specs Vol 1 of 2.pdf PDF
10 - Drawings - Mechanical.pdf PDF
12 - Drawings - Technology.pdf PDF
16 - Limitations on Subcontracting.pdf PDF
19 - Subcontracting Plan Template.docx DOCX document
03 - Summary of Qualification Requirements.pdf PDF
06 - Drawings - Structural.pdf PDF
09 - Drawings - Plumbing.pdf PDF
13 - Hazmat Report.pdf PDF
14 - PCRA.pdf PDF
17 - Division Cost Breakdown.xlsx XLSX spreadsheet
18 - Site Visit Instructions.pdf PDF
RFP 36C77626R0046 - 4-7-26.pdf PDF
07 - Drawings - Architectural.pdf PDF
11 - Drawings - Electrical.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BLDG 29

BA

ILE

Y

AV

E

LE

BR

UN

A

VE

BUFFALO VAMC

BLDG 1

BDGL 29

BDGL 1

A WING

B WING C WING

D WING

BA

ILE

Y

AV

EN

UE

LE

BR

UN

A

VE

NU

E

AREA OF WORK

BUFFALO

AREA OF

WORK

NEW YORK

CITY

NEW YORK

V U.S. Department of Veterans AffairsA

PROJECT LOCATION:

PROJECT TITLE:

BUILDING NUMBER:

ARCHITECTS + ENGINEERS:

BANCROFT ARCHITECTS +

ENGINEERS

CONTRACT NUMBER:

STATION PROJECT NUMBER:

BANCROFT-AE PROJECT NUMBER:

PROJECT NUMBERS:

PARKING RAMP EXPANSION

528-18-375 36C24222C0022

21-113

3495 BAILEY AVENUE, BUFFALO, NY 14215

BUFFALO VA MEDICAL CENTER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

K:

\C

C G

_P R

O

JE

C

TS

\2

1\

-1

Pa rk in g R am p

(B uf fa lo

, N Y)

\4

- D es

D oc s\

2- D ra w in gs

\W O

R

KI

N G

\2 1-

3_

G

1.

dw g 6/

/2

:3

9:

P M

ISSUE FOR BIDOffice of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

PARKING RAMP EXPANSION

3495 BAILEY AVE., BUFFALO, NY 14215

528-18-375

Project Director

Revisions: Date:

www. bancroft-ae.com

3300 Dundee Rd.

Northbrook, IL 60062

T: 847.952.9362

08-09-2024

ISSUE FOR BID 08-09-2024

STRUCTURAL ENGINEERING AND PARKING CONSULTANT:

20 NORTH CLARK ST.

SUITE 300

CHICAGO, IL 60602

T: 312.263.8400 www.desman.com

DESMAN DESIGN MANAGEMENT

3300 DUNDEE RD.

NORTHBROOK, IL 60062

T: 847.952.9362 F:847.952.9403 www.bancroft-ae.com

August 9, 2024

ISSUE FOR BID

CIVIL ENGINEERING:

1533 CRESCENT ROAD

CLIFTON PARK, NY 12065

T: 518.371.0799 www.mjels.com

MJ ENGINEERING, ARCHITECTURE, LANDSCAPE

ARCHITECTURE, AND LAND SURVEYING, P.C.

70 7 4 5 1

L

IC

E N

SE

D

PROFESSI ONAL

EN

G

I N E

E R

M

IC

H A

EL D . P AN I C

H

E L

LI

ST

ATE OF NE WYORK

Registration Expires 10.31.2026 cverdu Image cverdu Image cverdu Image cverdu Image cverdu Image cverdu Image cverdu Image

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

K:

\C

C G

_P R

O

JE

C

TS

\2

1\

-1

Pa rk in g R am p

(B uf fa lo

, N Y)

\4

- D es

D oc s\

2- D ra w in gs

\W O

R

KI

N G

\2 1-

3_

G

2.

dw g 6/

/2

:3

9:

P M

ISSUE FOR BIDOffice of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

PARKING RAMP EXPANSION

3495 BAILEY AVE., BUFFALO, NY 14215

528-18-375

Project Director

Revisions: Date:

www. bancroft-ae.com

3300 Dundee Rd.

Northbrook, IL 60062

T: 847.952.9362

08-09-2024

ISSUE FOR BID 08-09-2024

AutoCAD SHX Text

AutoCAD SHX Text 1/15/2004

AutoCAD SHX Text 21-113_G002.dwg

AutoCAD SHX Text

GENERAL - SHEET INDEX

AutoCAD SHX Text

CZ

AutoCAD SHX Text

II

AutoCAD SHX Text G002

1. ALL WORK SHALL BE COMPLETED IN ACCORDANCE WITH ALL PUBLISHED APPLICABLE LOCAL / STATE / FEDERAL / NATIONAL CODES, ORDINANCES AND REGULATIONS ALONG WITH ALL RELATED VA

DIRECTIVES, DESIGN GUIDES AND MANUALS, SPECIFICATIONS AND STANDARDS PLUS ALL VA

REQUIREMENTS (FEDERAL AND LOCAL) THAT ARE PROJECT SPECIFIC TO THE DOCUMENTED SCOPE OF

WORK ON THIS SITE.

2. EACH CONTRACTOR SHALL HAVE PUBLIC LIABILITY, PROPERTY DAMAGE AND WORKMAN'S

COMPENSATION INSURANCE AS REQUIRED BY THE VA IN THE BIDDING DOCUMENTATION. CONTACT THE VA/CO DURING THE BIDDING PHASE WITH ANY QUESTIONS, VERIFICATIONS, AND DOCUMENTATION

NECESSARY CONCERNING ALL REQUIREMENTS FOR PROJECT INSURANCE COVERAGE.

3. EACH CONTRACTOR PRIOR TO THE COMMENCEMENT OF WORK SHALL FULLY COORDINATE AND

VERIFY WITH ALL OTHER CONTRACTORS, OTHER TRADES AND THE VA/COR CONCERNING ALL SPACE REQUIREMENTS FOR THIS PROJECT. THE GENERAL/PRIME CONTRACTOR SHALL BE RESPONSIBLE FOR COMMUNICATING, DOCUMENTING AND COORDINATING ALL SPACE REQUIREMENTS WITH THE VA/COR TO

AVOID CONFLICTS AND MISCOMMUNICATION.

4. BEFORE SUBMITTING A BID, ALL CONTRACTORS WILL CAREFULLY EXAMINE THE DRAWINGS AND SPECIFICATIONS SO AS TO BE THOROUGHLY FAMILIAR WITH ALL THE CONTRACT REQUIREMENTS. EACH BIDDER SHOULD THEN VISIT THE SITE OF THE WORK TO BECOME ACQUAINTED WITH ALL VISIBLE FIELD CONDITIONS AFFECTING THE CONTRACT, SUCH AS OBSTACLES WHICH MAY BE ENCOUNTERED AND ALL OTHER CONDITIONS RELATIVE TO WHAT COULD AFFECT/IMPACT THE WORK OR BE AFFECTED BY THE

PERFORMANCE OF THE WORK.

5. IF AWARDED THE CONTRACT, THE CONTRACTORS SHALL NOT BE ALLOWED ANY EXTRA

COMPENSATION BY REASON OF ANY UNFORESEEN DIFFICULTIES OR OBSTACLES WHICH THE BIDDER COULD HAVE REASONABLY ANTICIPATED PRIOR TO BIDDING. SHOULD ANY DISCREPANCIES, ERRORS, CONFLICT OR ITEMS NEEDING CLARIFICATION BE DISCOVERED IN THE PLANS AND/OR SPECIFICATIONS, THE CONTRACTOR SHALL NOTIFY THE VA/CO PRIOR TO SUBMITTING A BID AND THE VA/COR BEFORE

STARTING ANY OF THE WORK.

6. CONTRACTORS SHALL REFERENCE ALL DRAWINGS IN ALL SECTIONS OF WORK FOR FULLY

DEFINING THEIR SCOPE OF WORK RESPONSIBILITIES AND COORDINATE SAME WITH THE GENERAL/PRIME CONTRACTOR. SUBCONTRACTORS AND SUPPLIERS FOR EACH TRADE ARE ADVISED THAT INFORMATION PERTINENT TO THEIR SCOPE OF WORK ALSO OCCURS IN OTHER SECTIONS OF THE DRAWINGS AND THE

COMPLETE SET OF CONTRACT DOCUMENTS.

7. DO NOT SCALE THE DRAWINGS. USE THE GIVEN DIMENSIONS. COORDINATE SHOP DRAWING

REQUIREMENTS WITH ALL TRADES.

8. ALL ENGINEERING SYSTEMS WORK INCLUDED IN THE CONTRACT DRAWINGS SHALL BE TAKEN IN A SENSE AS A DIAGRAMMATIC REPRESENTATION OF ITS INTENDED PLACEMENT AND DISTRIBUTION WITHIN THE GENERAL PROXIMITY WHERE SHOWN. THE SIZE & MEANS OF RUNNING DISTRIBUTION SYSTEMS ARE SHOWN BUT IT IS NOT INTENDED TO SHOW EVERY CONNECTION, FITTING, OFFSET, SUPPORT ELEMENT, NOR EVERY STRUCTURAL DIFFICULTY THAT CAN BE ENCOUNTERED DURING THE INSTALLATION OF THE

WORK.

9. PROJECT LIMIT LINES ARE SHOWN ON THE DRAWINGS FOR ORIENTATION PURPOSES ONLY AND SHOULD NOT BE CONSTRUED TO INDICATE THE FULL EXTENT OR LIMITS OF THE AREA(S) OF WORK.

10. ALL EXISTING BUILDING UTILITIES AND INFRASTRUCTURE SERVICES SYSTEMS THAT FEED OTHER SPACES OUTSIDE THE PROJECT AREA AND THAT ARE LOCATED WITHIN THE AREA OF WORK, THEREBY INTERFERING WITH THE NEW CONSTRUCTION, SHALL BE REROUTED AND RELOCATED AS REQUIRED TO

MAINTAIN FULL SERVICE TO THE AFFECTED AREAS.

11. ALL FINISHED AREAS ADJACENT TO OR INCLUDED WITHIN THE AREA(S) OF CONSTRUCTION ALONG WITH ALL PUBLIC PROJECT ACCESS ROUTES SHALL BE PROTECTED FROM DUST AND DIRT THROUGH THE USE OF VA/COR APPROVED DUSTPROOF PROTECTION. SEE THE OCCUPIED AREA PROTECTION PROTOCOLS PROVIDED IN THE “GENERAL” DRAWINGS SECTION AND COORDINATE ALL SITE-SPECIFIC

CONDITIONS IMPACTS ENCOUNTERED WITH THE VA/COR.

12. EACH CONTRACTOR SHALL MAINTAIN A COMPETENT OSHA-30 FOREMAN OR DIRECT

REPRESENTATIVE ON THE JOB AT ALL TIMES. THE CONTRACTOR SHALL COOPERATE WITH AND

COORDINATE WITH THE SUPERINTENDENT AND FOREMAN OF OTHER TRADES IN ORDER THAT THERE BE NO DELAYS IN THE EXECUTION AND COMPLETION OF THE WORK. BEFORE CONSTRUCTION BEGINS, ALL

WORKERS MUST HAVE 0SHA-10 TRAINING.

13. DURING CONSTRUCTION EACH CONTRACTOR SHALL KEEP ON SITE ACCURATE FIELD RECORDS OF ALL CONCEALED WORK THAT DIFFERS FROM THE CONTRACT DRAWINGS. THESE AS-BUILT MARKED-UP RECORD DRAWINGS WILL BE KEPT UP TO DATE BY THE GENERAL/PRIME CONTRACTOR AND PROVIDED TO THE VA/COR FOR DISTRIBUTION AT THE COMPLETION OF THE PROJECT. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE AOR / VA PRIOR TO STARTING ANY WORK THAT DIFFERS FROM THE APPROVED

CONTRACT DOCUMENTS.

14. IT SHALL BE THE RESPONSIBILITY OF EACH CONTRACTOR TO ADEQUATELY PROTECT EXISTING CONSTRUCTION AND FINISHES TO REMAIN IN PLACE DURING BOTH DEMOLITION AND CONSTRUCTION SEQUENCES OF THE WORK. ANY DAMAGE TO SUCH AREAS SHALL BE RESTORED AND REFINISHED TO A "LIKE-NEW" CONDITION PRIOR TO THE VA/COR'S ACCEPTANCE OF THAT WORK. WORK INDICATED IN THIS

NOTES SECTION SHALL BE COMPLETED AT NO ADDITIONAL COST TO THE VA.

15. THE GENERAL/PRIME CONTRACTOR IS RESPONSIBLE FOR THE PATCH, REPAIR, REFINISHING AND/OR REPLACEMENT OF ALL CONSTRUCTION, MATERIALS, ASSEMBLIES, EQUIPMENT, SIGNAGE AND FINISHES DAMAGED BY THE PROJECT DEMOLITION, TEMPORARY CONSTRUCTION, NEW CONSTRUCTION OR THE MOVEMENT OF PERSONNEL, TOOLS, EQUIPMENT, MATERIALS, ETC. BOTH INSIDE AND OUTSIDE OF THE DESIGNATED AREAS OF WORK. WORK INDICATED IN THIS NOTES SECTION SHALL BE COMPLETED

AT NO ADDITIONAL COST TO THE VA.

16. PROVIDE THE CUTTING AND PATCHING FOR ALL DEMOLITION WORK AND ALL NEW CONSTRUCTION

WORK BEING PERFORMED OUTSIDE OF THE PROJECT LIMIT LINES AS REQUIRED TO PROPERLY

COMPLETE THE PROJECT SCOPE OF WORK.

17. ALL CUTTING, CORING AND DRILLING OF EXISTING CONCRETE AND MASONRY CONSTRUCTION

SHALL NOT DAMAGE EXISTING REINFORCING STEEL, PIPING, CONDUITS OR OTHER CONCEALED

CONSTRUCTION WITHIN. PRIOR TO CORING, DRILLING, CUTTING OR PERFORMING ANY BREAKING EFFORTS, PROVIDE PENETRATING FIELD X-RAYING OF THE INTENDED AREAS AND DOCUMENT THE EXACT SIZE AND LOCATIONS OF ALL SUCH INTERFERENCES. COORDINATE WITH AND OBTAIN VA/COR

APPROVAL BEFORE PROCEEDING WITH ANY SUCH REQUIRED PENETRATIONS WORK.

18. RELOCATIONS OF ANY INFRASTRUCTURE DISTRIBUTION SYSTEMS OR EQUIPMENT, WHICH MAY ALTER THE ARCHITECTURAL OR STRUCTURAL CONSTRUCTION, MUST BE APPROVED FIRST BY THE

VA/COR PRIOR TO STARTING ITS RELOCATION.

19. THE GENERAL/PRIME CONTRACTOR IS RESPONSIBLE TO PROVIDE THE REMOVAL OF ALL

CONSTRUCTION DEMOLITION DEBRIS, SPOIL AND MATERIALS FROM THE PROJECT SITE ON A DAILY BASIS UNLESS SPECIFICALLY REFERENCED OTHERWISE IN THE PROJECT SPECIFIC LOGISTICAL SEQUENCING REQUIREMENTS. ANY DEMOLITION DEBRIS TRANSPORTED THROUGH HOSPITAL MUST BE IN A COVERED

RECEPTACLE.

20. CONTRACTORS TO ENSURE ALL FIRE RESISTIVE RATINGS ARE MAINTAINED PER LOCATIONS SHOWN ON THE DRAWINGS. ALL PENETRATIONS ARE TO BE SEALED BY AN APPROVED UL FIRESTOPPING SYSTEM. SEAL ALL EXISTING PENETRATIONS EXPOSED DURING CONSTRUCTION AS PER THE APPROVED UL FIRESTOPPING SYSTEM INSTALLATION REQUIREMENTS. FOLLOW THE MANUFACTURER'S DESIGN RECOMMENDATIONS FOR THE PROPER FIRE STOPPING MATERIAL TO BE USED IN EACH SPECIFIC

APPLICATION.

21. ALL FIRESTOPS SHALL MATCH THE FIRE RATING OF THE CONSTRUCTION BEING PENETRATED, SUCH AS WALLS, FLOORS, CEILINGS, PARTITIONS ETC. AND SHALL COMPLY WITH ALL CODE

REQUIREMENTS. USE ONLY A SINGLE (FMRC) APPROVED MANUFACTURER'S LINE OF PRODUCTS FOR

ALL PROJECT FIRESTOPPING. THE BOD FOR ALL FIRE STOPPING WILL BE ALL PRODUCTS AS

MANUFACTURED BY THE 3M COMPANY.

22. PROVIDE AN HOURLY RATED FIRESTOP AT ALL PENETRATIONS OF RATED CONSTRUCTION AND/OR ASSEMBLIES, WHETHER NEW OR EXISTING, AND/OR AS A DIRECT RESULT OF THE PROJECT DEMOLITION

WORK OR NEW CONSTRUCTION. WHERE COMBUSTIBLE PENETRANTS OCCUR USE A FIRE RATED

INTUMESCENT MATERIAL AND WHERE NONCOMBUSTIBLE PENETRANTS OCCUR USE A FIRE RATED

ENDOTHERMIC MATERIAL. ALL FIRESTOPPING WORK MUST BE APPROVED BY THE VA/COR BEFORE

CONCEALED BY CONSTRUCTION.

24. EACH CONTRACTOR SHALL BE VETTED BY VA SECURITY AND EACH WORKER WILL HAVE THEIR ID

ISSUED BY VA. ISSUED ID MUST BE WORN AT ALL TIMES.

SPECIAL SAFETY NOTES

1. ALL CONTRACTORS, SUBCONTRACTORS AND THEIR REPRESENTATIVES WORKING ON THIS

PROJECT SHALL AT ALL TIMES PRIOR TO AND DURING THE COURSE OF THEIR ACTIVITY BE RESPONSIBLE FOR THE SAFETY OF THEIR EMPLOYEES, ALL OTHERS AND ARE TO BE IN CARE OF THE PROPERTY.

SUBMIT SAFETY PLAN TO VA COR PRIOR TO START OF CONSTRUCTION.

2. EACH CONTRACTOR OR SUBCONTRACTOR, AS REPRESENTATIVES OF THEIR EMPLOYEES, SHALL

ASCERTAIN THAT THE CONDITIONS UNDER WHICH THEY WILL BE REQUIRED TO ACCOMPLISH

THEIR WORK ARE SAFE AND MEET ALL APPLICABLE REQUIREMENTS OF THE OCCUPATIONAL SAFETY

AND HAZARD ACT, ALONG WITH ALL OTHER APPLICABLE GOVERNING REGULATIONS AND VA

REQUIREMENTS.

3. THE BEGINNING OF WORK ON SITE BY A CONTRACTOR OR SUBCONTRACTOR SHALL INDICATE

HIS/HER SATISFACTION AND FULL ACCEPTANCE OF THE CURRENT SITE CONDITIONS REGARDING SAFETY AND THE NECESSARY COMPLIANCE WITH ALL CONTRACT REQUIREMENTS REGARDING SAME.

THE CONTRACTOR ACCEPTS FULL RESPONSIBILITY FOR ANY ACCIDENTS, INJURIES, AND/OR DAMAGES

INCURRED AS A RESULT OF ANY VISIBLE OR KNOWN UNSAFE CONDITIONS THAT EXIST.

4. IF UNSATISFIED WITH THE CURRENT SITE SAFETY CONDITIONS AND/OR THE NECESSARY

COMPLIANCE, THE CONTRACTOR OR SUBCONTRACTOR SHALL INDICATE THE ACTIONS AND/OR DEVICES NECESSARY TO RENDER THE JOB-SITE SAFE. IF THE WORK OF OTHER PARTIES, UPON INSPECTION, IS FOUND AT ANY TIME TO BE UNSAFE THE CONTRACTOR OR SUBCONTRACTOR SHALL IMMEDIATELY STOP ALL WORK AND NOTIFY THE GENERAL/PRIME CONTRACTOR AND THE VA/COR. THE SUBMISSION OF A BID FOR ANY PORTION OF WORK INCLUDED IN THIS CONTRACT SHALL ALSO INDICATE ACKNOWLEDGMENT

AND ACCEPTANCE OF THESE REQUIREMENTS.

INTENT:

1. TO ORGANIZE AND IDENTIFY THE "EQUIVALENCY SUBSTITUTION PROCESS" IN ORDER TO FORMALIZE THE PROCESS, CLARIFY RESPONSIBILITIES, PROACTIVELY MANAGE THE PROCESS AND MINIMIZE

COSTLY DELAYS IN THE EXECUTION OF THE WORK.

2. THERE ARE NO INTENDED RESTRICTIONS LIMITING COMPETITION ON THE EQUIVALENT

SUBSTITUTION OF MATERIALS, EQUIPMENT, HARDWARE, FINISHES, CONTROLS, SYSTEMS AND THEIR

INCLUSIVE PARTS, DETAILED ASSEMBLIES, RELATED DESIGN ELEMENTS AND PERFORMANCE

CHARACTERISTICS, UNLESS AS IDENTIFIED IN THE BID SOLICITATION.

SUMMARY DESCRIPTION::

1. THE BASIS OF DESIGN (BOD) INCORPORATES THE DESIGN INTENT AND PERFORMANCE BASED CHARACTERISTICS FOR ALL MATERIALS, SYSTEMS AND WORKMANSHIP THAT IS INCLUDED IN THE

CONSTRUCTION DOCUMENTS AND REFERENCED BY SAME.

2. THE BOD COMPLIANCE PROTOCOLS ARE TO BE FOLLOWED FOR ALL PROPOSED EQUIVALENT

SUBSTITUTIONS, DEPARTURES OR ADJUSTMENTS FROM THE CONSTRUCTION DOCUMENT DRAWINGS, DETAILING, AND SPECIFICATIONS, PROVIDED THE SUBSTITUTIONS, DEPARTURES OR ADJUSTMENTS MEET THE DESIGN INTENT, SCOPE OF WORK (SOW) CRITERIA REQUIREMENTS, AND PERFORMANCE

BASED CHARACTERISTICS.

3. NO SUCH EQUIVALENT SUBSTITUTION, DEPARTURES OR ADJUSTMENTS WILL BE ALLOWED WITHOUT

FIRST GOING THROUGH THE BOD COMPLIANCE PROTOCOLS PROCESS AND OBTAINING THE

GOVERNMENT'S APPROVAL FROM THE CONTRACTING OFFICER (CO).

BOD COMPLIANCE PROTOCOLS:

1. THE BOD COMPLIANCE PROTOCOLS APPLY TO ALL MATERIALS, EQUIPMENT, HARDWARE, FINISHES, CONTROLS, ENGINEERING SYSTEMS AND THEIR INCLUSIVE PARTS, DETAILED ASSEMBLIES, IMPACTED ELEMENTS OF WORK PLUS ALL RELATED DESIGN CRITERIA ELEMENTS AND SPECIFIED PARAMETERS THAT ARE CONTAINED WITHIN THE BID/ISSUED FOR CONSTRUCTION DRAWINGS AND SPECIFICATIONS

DOCUMENTATION, OR AS SPECIFICALLY REFERENCED BY SAME.

2. SPECIFIC DESIGN INTENT AND PERFORMANCE CHARACTERISTICS REQUIRING BOD COMPLIANCE ANALYSIS WILL VARY WITH EACH SPECIFIC ITEM BEING PROPOSED AS AN EQUIVALENT SUBSTITUTION

AND WILL NEED TO BE FULLY COMPARED AND ANALYZED TO ESTABLISH BOD EQUIVALENCY

COMPLIANCE.

3. CRITICAL DESIGN CHARACTERISTICS AND ELEMENTS ARE SPECIFIC TO EACH ITEM NEEDING CONSIDERATION AND COULD CONSIST OF, BUT NOT LIMITED TO, CRITERIA SUCH AS DIMENSIONAL

LOGISTICS, PERFORMANCE CHARACTERISTICS, CAPACITY, DUTY REQUIREMENTS, OPERATIONAL

EFFICIENCIES, ACOUSTICAL REQUIREMENTS, UTILITIES IMPACTS, CONNECTION VARIANCES, DETAILING DEVIATIONS, FRAMING MODIFICATIONS, ROUGH IN REQUIREMENTS, WEIGHT INCREASES AND/OR DISTRIBUTIONS, STRUCTURAL IMPACTS, ATTACHMENTS, SUPPORTS, FINISHES, AVAILABILITY, COMPATIBILITY, CONSTRUCTABILITY, WARRANTIES, SERVICE LIFE, MAINTENANCE REQUIREMENTS, ENVIRONMENTAL CONSIDERATIONS, LEED RELATED DESIGN CONSIDERATIONS, ETC.

4. A VERY CRITICALLY IMPORTANT DESIGN CHARACTERISTIC OF ALL BOD ITEMS NEEDING TO BE FULLY

EVALUATED AND PROPERLY COORDINATED WOULD BE THE DESIGN AND LAYOUT OF DIMENSIONAL

LOGISTICS REQUIREMENTS. THOSE CRITICAL PARAMETERS COULD CONSIST OF, BUT NOT LIMITED TO, ALL DIMENSIONAL ELEMENTS THAT AFFECT SIZE, HEIGHT, WIDTH, DEPTH, THICKNESS, PLACEMENT, SPACING, CLEARANCES, ACCESS, MOUNTING, CONNECTIONS AND LOCATION REQUIREMENTS, INSTALLATION TOLERANCES, OPERABLE ELEMENT CLEARANCES, ETC., ALL OF WHICH COULD IMPACT OTHER AREAS OF CONSTRUCTION OR COMPONENTS OF WORK REQUIRING ADJUSTMENTS IN ORDER TO

COMPLY WITH THE DESIGN INTENT.

5. CONTRACTORS WILL BE RESPONSIBLE TO FULLY IDENTIFY ALL PROPOSED EQUIVALENT

SUBSTITUTIONS, DEPARTURES, IMPACTS ALTERATIONS AND ADJUSTMENTS FROM THE "BASIS OF DESIGN" INTENT TO THE GENERAL/PRIME CONTRACTOR DURING THE BIDDING PROCESS AND OBTAIN

THEIR APPROVAL BEFORE COMPLETING THEIR PRICING AND SUBMITTING A BID TO SAME.

6. IF A PROPOSED EQUIVALENT SUBSTITUTION ITEM WILL REQUIRE THAT ALTERATIONS AND/OR ADJUSTMENTS NEED TO BE MADE, TO THE WORK OF THE PROVIDING CONTRACTOR, THE WORK OF OTHER CONTRACTORS OR THE WORK OF THE VA, THE SUBMITTING CONTRACTOR SHALL BE FULLY RESPONSIBLE TO INFORM AND ADVISE THE GENERAL/PRIME CONTRACTOR OF ANY AND ALL SUCH NECESSARY IMPACTS REQUIRED AS A PART OF THEIR BIDDING AND FUTURE CONTRACTUAL SCOPE OF

WORK RESPONSIBILITIES.

7. THE CONTRACTOR PROPOSING THE EQUIVALENT SUBSTITUTION SHALL BE RESPONSIBLE FOR ALL RELATED WORK AND SHALL IDENTIFY, VERIFY, COORDINATE AND PROVIDE ENGINEERED SOLUTIONS FOR ALL IMPACT ISSUES AFFECTING INFRASTRUCTURE SYSTEMS, UTILITIES SERVICES, BUILDING

STRUCTURE, SURROUNDING ELEMENTS, AND SYSTEMS AFFECTED FROM WEIGHT DIFFERENTIALS,

REVISED LOADING CHARACTERISTICS, CONNECTION AND MOUNTING VARIANCES, INSTALLATION

CONFLICTS AND DETAILING ALTERATIONS OR ADJUSTMENTS, ETC. CAUSED BY THE EQUIVALENT

SUBSTITUTION REQUIREMENTS.

8. SPECIAL ATTENTION NEEDS TO BE PAID TO ANY SYSTEMS EQUIPMENT AND MATERIAL

PERFORMANCE CHARACTERISTICS INCLUDING ALL ASPECTS OF THEIR DIMENSIONAL LOGISTICS

FEATURES AND REQUIREMENTS ALONG WITH ANY STRUCTURAL AND UTILITIES IMPACTS.

9. EACH EQUIVALENT SUBSTITUTION REQUEST ALONG WITH ANY AND ALL IMPACTS, VARIANCES, ALTERATIONS OR ADJUSTMENTS REQUIRED TO OTHER ELEMENTS OF WORK WILL ALSO REQUIRE VA/CO

APPROVAL(S) BEFORE ANY SUCH REQUEST IS DEEMED APPROPRIATE BY THE GOVERNMENT AND

ALLOWED TO PROCEED INTO THE NORMAL SHOP DRAWING PREPARATION, SUBMITTAL AND REVIEW

PROCESS.

10. NO REQUEST FOR AN EQUIVALENT SUBSTITUTION REVIEW IS ALLOWED TO BE MADE VIA A SHOP DRAWING SUBMISSION. ANY SUCH SUBMISSION WILL NOT BE REVIEWED AND WILL BE REJECTED AS NON-CONFORMING WITH THE DESIGN INTENT AND NOTED THAT THE CONTRACTOR IS TO FOLLOW THE

STANDARD BOD COMPLIANCE PROTOCOLS.

11. ANY UNDOCUMENTED OR UNFORESEEN IMPACT, VARIANCES, ALTERATIONS OR ADJUSTMENTS

REQUIRED TO ELEMENTS OF WORK AS A RESULT OF AN EQUIVALENCY SUBSTITUTION THAT SURFACE DURING THE CONSTRUCTION PHASE SHALL IMMEDIATELY BE MADE KNOWN TO THE GENERAL/PRIME CONTRACTOR WHO WILL IN TURN NOTIFY THE VA/COR. ALL SUCH UNDOCUMENTED OR UNFORESEEN CONDITIONS WILL BE FULLY IDENTIFIED, DOCUMENTED AND SUBMITTED TO THE VA/COR FOR REVIEW, EVALUATION AND DIRECTION(S) ON HOW TO PROCEED.

12. ANY NON-COMPLIANT EQUIVALENT SUBSTITUTIONS WORK FOUND TO BE IN PLACE DURING THE CONSTRUCTION PHASE THAT HAD NOT GONE THROUGH THE BOD COMPLIANCE PROTOCOLS APPROVAL PROCESS AND THAT DOESN'T HAVE THE VA/CO'S APPROVAL WILL BE SUBJECT TO POSSIBLE REJECTION

AND REMOVAL AS DETERMINED BY THE GOVERNMENT. CONTRACTOR IS RESPONSIBLE FOR THE

REMOVAL / REPLACEMENT OR REJECTED WORKS AT NO ADDITIONAL COST TO THE VA.

13. THE FINAL INSTALLATION OF ANY EQUIVALENT SUBSTITUTION AND ITS IMPACTS SHALL NOT COMPROMISE ANY OF THE BOD PERFORMANCE CHARACTERISTICS NOR SHALL IT ENCUMBER ANY OF

THE ASSOCIATED DESIGN INTENT LAYOUT AND DIMENSIONAL LOGISTICS REQUIREMENTS.

14. ALL EQUIVALENT SUBSTITUTION INSTALLATIONS AND THEIR IMPACTS TO OTHER SOW ELEMENTS SHALL COMPLY WITH ALL APPLICABLE BUILDING CODES, REGULATIONS AND VA REQUIREMENTS, PLUS

ALLOW ANY SYSTEMS, EQUIPMENT AND/OR MATERIALS TO FUNCTION PROPERLY AND SAFELY.

BOD EQUIVALENT SUBSTITUTIONS PROCESS SEQUENCE:

(STEP 01) BIDDING PHASE:

1. ALL BOD PROPOSED EQUIVALENT SUBSTITUTIONS AND THEIR ASSOCIATED IMPACTS ON OTHER SOW ELEMENTS, SHALL BE FULLY IDENTIFIED AND COORDINATED WITH THE GENERAL/PRIME CONTRACTOR(S) SUCH THAT THE COST OF ALL ASSOCIATED SCOPE OF WORK IMPACTS DIRECTLY AFFECTING OTHER

TRADES SHALL BE INCLUDED IN THE BASE BIDS OF ALL AFFECTED CONTRACTORS.

(STEP 02) CONTRACTORS IDENTIFY PROPOSED EQUIVALENT SUBSTITUTION(S):

1. ALL CONTRACTORS, BEFORE SUBMITTING THEIR REQUEST FOR EQUIVALENT SUBSTITUTION

CONSIDERATION SHALL BE RESPONSIBLE TO HAVE FULLY VERIFIED AND CERTIFIED IN WRITING THAT THE DESIGN CHARACTERISTICS OF THE ITEMS THEY WILL BE SUBMITTING FOR BOD COMPLIANCE REVIEW MEETS OR EXCEEDS THE DESIGN INTENT AND PERFORMANCE REQUIEMENTS AS DESIGNED, DETAILED AND SPECIFIED.

(STEP 03) CONTRACTORS PREPARE DETAILED COMPARISONS:

1. THE REQUESTING CONTRACTOR SHALL PREPARE AND PROVIDE TO THE GENERAL/PRIME

CONTRACTOR A FULL LINE ITEM, SIDE-BY-SIDE COMPARISON LISTING SPREAD SHEET OF ALL BOD

DESIGN AND MANUFACTURED CHARACTERISTICS VERSUS THE SAME FOR THE EQUIVALENT

SUBSTITUTION BEING PROPOSED.

2. ALL EQUIPMENT, MATERIALS OR ASSEMBLY EQUIVALENT SUBSTITUTIONS SHALL BE PROVIDED ON A CONTACTOR PREPARED ITEMIZED LISTING PER EACH REQUESTED SUBSTITUTION WITH A FULL AND DETAILED COMPARATIVE DESCRIPTION OF ALL SPECIFICATIONS, PERFORMANCE CHARACTERISTICS, CAPACITIES, WEIGHT, DIMENSIONAL LOGISTICS AND KNOWN IMPACTS, DEPARTURES, ALTERATIONS OR

ADJUSTMENTS FROM THE ORIGINAL BOD.

3. CONTRACTOR SHALL UTILIZE THE ORIGINAL MANUFACTURER'S PUBLISHED SPECIFICATIONS AND

PRODUCT DATA SHEETS ALONG WITH ANY ADDITIONAL CHARACTERISTICS AND PERFORMANCE

CRITERIA REQUIRED AND SPECIFIED IN THE CONSTRUCTION DOCUMENTS AS THE BASIS FOR THE

DEVELOPMENT OF THE LINE BY LINE COMPARISON CRITERIA SPREAD SHEET.

(STEP 04) CONTRACTORS IDENTIFY RELATED IMPACTS:

1. THE REQUESTING CONTRACTOR SHALL BE RESPONSIBLE TO FULLY IDENTIFY AND DOCUMENT ALL

PROPOSED EQUIVALENT SUBSTITUTION CAUSED IMPACTS, DEPARTURES, ALTERATIONS OR

ADJUSTMENTS REQUIRED FROM THE ORIGINAL BOD REQUIREMENTS WITH THE GENERAL/PRIME

CONTRACTOR AS WELL AS ALL AFFECTED CONTRACTORS.

2. SEE THE DETAILED BOD PROTOCOL REQUIREMENTS FOR THE EXTENT OF RESPONSIBILITIES AND

DOCUMENTATION REQUIRED FOR THIS CRITICAL ITEM.

(STEP 05) CONTRACTOR'S DOCUMENTATION TO GENERAL/PRIME CONTRACTOR:

1. CONTRACTORS SHALL COORDINATE WITH THE GENERAL/PRIME CONTRACTOR AS TO THE SPECIFIC

DATE THAT EACH IS REQUIRED FOR THE COMPLETION OF THEIR EQUIVALENT SUBSTITUTION

SUBMISSION REQUEST DOCUMENTATION AND DELIVERY OF THE COMPLETED PACKAGE(S) TO THEM.

2. CONTRACTORS SHALL FULLY COORDINATE THEIR PREPARATION OF ALL REQUIRED DOCUMENTATION AND EQUIVALENCY SUBSTITUTION REQUIREMENTS WITH THE GENERAL/PRIME CONTRACTOR IN ORDER TO ADDRESS ANY AND ALL IMPACTS ON THE PROJECT SCHEDULE AS WELL AS PERFORMING THEIR

REQUIRED FORMALIZED REQUEST FOR EQUIVALENCY SUBSTITUTION SUBMISSION.

3. ALL EQUIVALENT SUBSTITUTION REQUESTS ALONG WITH THEIR REQUIRED SUBMISSION REQUEST DOCUMENTATION SHALL BE DELIVERED TO THE GENERAL/PRIME CONTRACTOR AS REQUIRED BY SAME IN TIME FOR THE GC'S FIRST SUBMISSION OF THE PROPOSED PROJECT CONSTRUCTION SCHEDULE

BEING SUBMITTED TO THE GOVERNMENT FOR REVIEW.

(STEP 06) GENERAL/PRIME CONTACTOR RESPONSIBLE FOR COORDINATION:

1. THE GENERAL/PRIME CONTRACTOR SHALL BE RESPONSIBLE TO FULLY IDENTIFY, DOCUMENT, MAKE SUBMISSIONS, TRACK, COORDINATE, OBTAIN CONTRACTING OFFICER (CO) APPROVALS AND INCLUDE THE COST OF ALL SUCH EQUIVALENT SUBSTITUTIONS, WORK IN THEIR COST OF CONSTRUCTION AS

WELL AS ALLOWED FOR WITHIN THEIR PROJECT SCHEDULE.

2. THE GENERAL/PRIME CONTRACTOR HAVING BEEN MADE FULLY AWARE OF POTENTIAL EQUIVALENCY SUBSTITUTIONS AND IMPACTS DURING THE BIDDING PROCESS SHALL INCLUDE AND DOCUMENT THIS BOD PROCESS IN THEIR DETAILED PROJECT SCHEDULE ALLOWING A SEPARATE TASK ITEM TIMELINE

FOR EACH WITH CRITICAL DATES AND PERFORMANCE TARGETS IDENTIFIED AND TRACKED.

3. THE GENERAL/PRIME CONTRACTOR SHORTLY AFTER CONTRACT AWARD AND EXECUTION SHALL

NOTIFY AND COORDINATE WITH THE VA/COR, ALL SUCH KNOWN EQUIVALENT SUBSTITUTION REQUESTS ALONG WITH ALL POSSIBLE IMPACTS FROM THE SPECIFIC BOD REQUIREMENTS PROVIDED IN THE

DRAWINGS AND SPECIFICATIONS.

4. ALL SUCH IMPACTS, DEPARTURES, ALTERATIONS OR ADJUSTMENTS REQUIRED TO ELEMENTS OF WORK WILL BE FULLY IDENTIFIED, DOCUMENTED AND SUBMITTED TO THE VA/COR FOR REVIEW, EVALUATION AND DIRECTION(S) ON HOW TO PROCEED.

5. THE GENERAL/PRIME CONTRACTOR WILL ALSO BE RESPONSIBLE TO FULLY IDENTIFY AND

COORDINATE ALL EQUIVALENCY SUBSTITUTION IMPACTS WITH ALL AFFECTED CONTRACTORS AND

TRADES TO BE SURE THAT ALL SUCH WORK IS INCLUDED IN THE SCOPE OF WORK.

(STEP 07) TRACKING LIST OF PROPOSED EQUIVALENT SUBSTITUTIONS:

1. THE SUCCESSFUL GENERAL/PRIME CONTRACTOR SHALL PREPARE A COMPLETE MASTER LISTING, BY

SPECIFICATION AND/OR DRAWING SECTIONS, OF ALL PROPOSED EQUIVALENT SUBSTITUTION

REQUESTS.

2. THIS MASTER LISTING WILL CONSIST OF A SUMMARY DESCRIPTION OF EACH REQUEST ALONG WITH A BULLET POINT LISTING OF THE MAJOR IMPACTS, DEPARTURES, ALTERATIONS AND ADJUSTMENTS

REQUIRED RESULTING FROM IT.

3. THIS DOCUMENT WILL BE PREPARED AS A SPREAD SHEET AND UTILIZED AS A TRACKING TOOL FOR DOCUMENTING ALL SIGNIFICANT ASSOCIATED DATES, ACTION ITEMS, CURRENT STATUS, REJECTIONS, RESUBMISSIONS, APPROVALS AND ADDITIONAL PERTINENT ISSUES AND ITEMS TO BE RECORDED AND

TRACKED AS REQUIRED BY THE VA/COR.

(STEP 08) EQUIVALENCY REQUEST(S) SUBMITTED TO VA

1. THE SUCCESSFUL GENERAL/PRIME CONTRACTOR SHALL SUBMIT TO THE VA/COR FOR PRELIMINARY REVIEW A MASTER SUMMARY LISTING OF ALL EQUIVALENT SUBSTITUTION REQUESTS WITH ANY/ALL

IMPACTS IDENTIFIED A MINIMUM OF TWO WEEKS PRIOR TO THE FIRST SUBMISSION OF THEIR

PROJECTED PROJECT SCHEDULE.

2. A SEPARATE FULLY DETAILED SUBMISSION DOCUMENTATION PACKAGE SHALL BE PREPARED FOR EACH SUBSTITUTION REQUEST AND WILL CONSIST OF STEPS NUMBER 2, 3, 4, & 5 ALONG WITH ANY ADDITIONAL PERTINENT INFORMATION DEEMED NECESSARY SUCH AS SKETCHES, DETAILED DRAWINGS, ENGINEERING DESIGN AND CALCULATIONS, MORE DETAILED DESCRIPTIONS, ETC. THIS SUBMISSION DOCUMENTATION PACKAGE SHALL BE SUBMITTED WITH THE FIRST SUBMISSION OF THEIR PROJECTED

PROJECT SCHEDULE TO THE VA/COR.

(STEP 09) VA REVIEW AND ACTION NOTIFICATION:

1. THE VA/COR SHALL REVIEW EACH SUBSTITUTION REQUEST PACKAGE AND TAKE SUCH ACTION AS

DEEMED NECESSARY ON EACH. SUCH ACTION COULD CONSIST OF REJECTION, APPROVAL OR

DIRECTION ON PROVIDING MORE DETAILED INFORMATION AND/OR CLARIFICATION(S) ON EACH

SUBMISSION AND/OR EACH IMPACT.

2. AS PART OF THE VA'S REVIEW PROCESS THE AE WILL ALSO BE INCLUDED IN A SIMILAR FASHION TO

THE SHOP DRAWING REVIEW PROCESS AND SHALL CONSULT WITH THE VA/COR AND PROVIDE A

RECOMMENDATION FOR THE VA'S CONSIDERATION.

3. THE A/E WILL REJECT IMMEDIATELY WITHOUT REVIEWING ANY SUBMITTAL THAT IS DEEMED

INCOMPLETE AND NOT IN COMPLIANCE WITH THE BOD PROTOCOLS COMPLIANCE REQUIREMENTS.

4. IT SHOULD BE NOTED THAT IT IS NOT THE VA'S OR THE A/E'S RESPONSIBILITY TO RESEARCH, DOCUMENT AND PROVE EQUIVALENCY, THAT IS THE REQUESTING/SUBMITTING CONTRACTOR'S

RESPONSIBILITY AS PER THESE PROTOCOLS. THE AE'S RESPONSIBILITY IS TO REVIEW AND ANALYZE THE DETAILED COMPARATIVE DOCUMENTATION AS PROVIDED AND ADVISE THE VA/COR ON WHAT WAS

SUBMITTED.

(STEP 10) VA APPROVAL ALLOWS SHOP DRAWING PROCESS TO BEGIN:

1. PRIOR TO THE CONTRACTOR(S) BEING ALLOWED TO PROCEED WITH SHOP DRAWING PREPARATION AND THE OFFICIAL SHOP DRAWING SUBMISSION(S) PROCESS, THEY WILL FIRST NEED TO OBTAIN THE VA/CO APPROVAL(S) ON EACH EQUIVALENT SUBSTITUTION REQUEST THAT WILL AFFECT THE SHOP

DRAWING PROCESS FOR THAT SPECIFIC ITEM AND AREA OF WORK.

(STEP 11) IMPLEMENTATION OF SUBSTITUTION(S) AND IMPACT(S):

1. ONCE APPROVED BY THE VA/CO THE CONTRACTORS SHALL PERFORM THEIR FINAL COORDINATION EFFORTS AND BEGIN THE NORMAL SHOP DRAWING PREPARATION AND SUBMITTAL PROCESS INCLUDING PROVIDING ANY ADDITIONAL ENGINEERING WORK NECESSITATED BY THE EQUIVALENT SUBSTITUTION.

2. THE GENERAL/PRIME COTACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL WORK ASSOCIATED WITH AND IMPACTED BY ANY EQUIVALENT SUBSTITUTION ALONG WITH THE COMPLETE COORDINATION

AND MANAGEMENT OF THE WORK WITHOUT ADDITIONAL COST TO THE GOVERNMENT.

GENERAL NOTES FOR CONTRACTORS BASIS OF DESIGN (BOD) COMPLIANCE PROTOCOLS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

K:

\C

C G

_P R

O

JE

C

TS

\2

1\

-1

Pa rk in g R am p

(B uf fa lo

, N Y)

\4

- D es

D oc s\

2- D ra w in gs

\W O

R

KI

N G

\2 1-

3_

G I0

.d w g

6/

/2

:3 9:

P

M

ISSUE FOR BIDOffice of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

PARKING RAMP EXPANSION

3495 BAILEY AVE., BUFFALO, NY 14215

528-18-375

Project Director

Revisions: Date:

www. bancroft-ae.com

3300 Dundee Rd.

Northbrook, IL 60062

T: 847.952.9362

08-09-2024

ISSUE FOR BID 08-09-2024

AutoCAD SHX Text

AutoCAD SHX Text 1/15/2004

AutoCAD SHX Text 21-113_GI001.dwg

AutoCAD SHX Text

GENERAL - CONTRACTOR AND BASIS-OF-DESIGN PROTOCOL NOTES

AutoCAD SHX Text

CZ

AutoCAD SHX Text

RB

AutoCAD SHX Text

GI001

DN

DN

UP

9'- 7"

15'-3 1/2"

SUBSTITUTE WEST

CURTAINWALL WITH

PRECAST CONCRETE

CONSTRUCTION

NORTH CURTAINWALL TO

REMAIN AS DESIGNED

STEEL COLUMNS AND

BEAMS ELIMINATED FROM

WEST SIDE

STEEL COLUMNS AND BEAMS

ELIMINATED FROM EAST SIDE

MEDICAL CENTER

LOBBY

M01

LEVEL 2 LOBBY

SUBSTITUTE EAST

CURTAINWALL WITH

PRECAST CONCRETE

CONSTRUCTION

DELETE SOUTH WINDOW (NO OPENING IN

PRECAST CONCRETE WALL)

THE SCOPE OF WORK FOR THIS PROJECT INCLUDES AN ADDITION OF TWO NEW PARKING LEVELS TO THE TOP OF THE EXISTING THREE-LEVEL PARKING STRUCTURE. A NEW STAIR TOWER WITH TWO ELEVATORS WILL BE CONSTRUCTED FOR THE WHOLE COMBINED HEIGHT OF THE GARAGE. ADJACENT PARKING, DROP OFF, AND ROADWAY WORK WILL BE

RECONFIGURED AS INDICATED IN THE DOCUMENTS.

1. ADDITION OF TWO NEW PARKING LEVELS OF APPROXIMATELY 53,000 GSF EACH TO THE TOP OF THE EXISTING

THREE-STORY PARKING STRUCTURE.

2. ADDITION OF NEW STAIR TOWER WITH FOOTPRINT OF APPROXIMATELY 1,500 GSF TO INCLUDE NEW STAIRS

AND TWO NEW ELEVATORS SPANNING THE FULL HEIGHT OF THE COMBINED GARAGE LEVELS.

3. ADDITION OF SCREENING AND SIGNAGE THROUGHOUT THE GARAGE FOR SAFETY AND WAYFINDING.

4. NEW ROADWAY TO THE EAST OF THE GARAGE FOR BETTER TRAFFIC FLOW AND FUTURE PARKING GARAGE

EXPANSION.

5. RECONFIGURED ACCESSIBLE PARKING AND DROP-OFF LANE AT THE NORTH SIDE OF THE PARKING GARAGE.

6. RECONFIGURED PEDESTRIAN CROSSINGS FROM THE PARKING GARAGE TO THE MEDICAL CENTER ENTRANCE.

7. RESTORATION WORK ON EXISTING PARKING STRUCTURE LEVELS.

8. REPAINTING OF PARKING STRIPING AS SHOWN AND REQUIRED.

VERIFY AND COORDINATE ALL PROTECTION REQUIREMENTS TO BE PROVIDED FOR EACH SPECIFIC AREA OR LOCATION OF SCHEDULED WORK WITH THE VA/COR BEFORE BEGINNING ANY WORK. WHEN PERFORMING WORK (DEMOLITION OR NEW) IN OCCUPIED SPACES, THE FOLLOWING PROTECTION PROTOCOLS WILL BE FOLLOWED ON A DAILY BASIS UNLESS

MODIFIED IN WRITING BY THE COR ON A CASE BY CASE BASIS:

1. CAREFULLY MOVE/RELOCATE ANY SIGNAGE, WALL HUNG ITEMS, BLINDS, CURTAINS, ETC. THAT ARE IN THE AREA/ZONE WHERE THE WORK IS TO BE ACCOMPLISHED AND IN DANGER OF BEING DAMAGED BY THE PERFORMANCE OF THE WORK, INCLUDING DAMAGE THAT CAN BE CAUSED BY FALLING OBJECTS, DUST OR MOISTURE. NOTE: THIS ALSO APPLIES TO THE DIRECT ACCESS ROUTE THRU THE OCCUPIED AREA TO AND FROM THE ACTUAL WORK AREA/ZONE. NOTE: THE VA WILL BE RESPONSIBLE TO MOVE/RELOCATE ANY FURNITURE, EQUIPMENT, BOXES, FILES, USER BELONGINGS, ETC. THAT WOULD BE IN THE AREA OF WORK AND OBSTRUCT/INTERFERE WITH THE PERFORMANCE OF THE CONTRACTOR'S WORK. COORDINATE ALL REQUIRED VA

RELOCATIONS WITH VA/COR.

2. CAREFULLY PROVIDE FULL PROTECTIVE DUST, MOISTURE AND DAMAGE PREVENTION BARRIERS/COVERS FOR ALL SUCH ITEMS ADDRESSED ABOVE INCLUDING THE ADDITIONAL PROTECTION OF ALL WALL SURFACES/FINISHES, WINDOWS/GLAZING, DOORS, FRAMES, HARDWARE, CARPETING, FLOOR COVERINGS, WALL BASE, CEILING

CONSTRUCTION, TILE, GRID, WALL ANGLES, LIGHT FIXTURES, DIFFUSERS, GRILLES, ETC.

3. FLOOR FINISHES SHALL BE PROTECTED THROUGHOUT THE AREA WITH A 6 MIL HEAVY DUTY REINFORCED, FIRE-RETARDANT, POLY SHEETING (VISQUEEN) TEMPORARY TARPAULIN(S)/DROP CLOTH(S) AS A MINIMUM FOR

DUST, MOISTURE AND VERY LIGHT FOOT TRAFFIC PROTECTION

4. ALL MAIN TRAFFIC AREAS TO AND FROM , ALONG WITH INSIDE THE WORK ZONE/AREAS, SHALL HAVE ADDITIONAL PROTECTION PROVIDED OVER THE 6 MIL HEAVY DUTY REINFORCED, FIRE-RETARDANT, POLY SHEETING (VISQUEEN), IN THE FORM OF FULL SHEETS OF 3/16“ TEMPERED HARDBOARD (MASONITE) 4'X8' PANELS. ALL PANELS SHALL BE FIRMLY HELD TOGETHER AND SECURED IN PLACE VIA THE USE OF AN INDUSTRY APPROVED 2” HEAVY DUTY CONSTRUCTION ADHESIVE TAPE, INTENDED FOR THIS APPLICATION NOTE: ALL BOARD TO BOARD JOINTS WILL BE FULLY TAPED THE LENGTH OF THE JOINT AND ALL BOARD TO VISQUEEN JOINTS WILL BE TAPED AT 4' ON CENTER WITH A MINIMUM 8” LENGTH OF TAPE. PAINTERS TAPE AND/OR MASKING TAPE ARE NOT CONSIDERED EQUIVALENTS

TO THE HD CONSTRUCTION ADHESIVE TAPE BEING SPECIFIED.

5. CONSTRUCT A TEMPORARY FULL HEIGHT, FULLY SEALED, CONTAINMENT ENCLOSURE AROUND ALL CONSTRUCTION AREAS/ZONES IN ORDER TO CONTAIN AS MUCH DUST AND DEBRIS AS POSSIBLE DURING THE PERFORMANCE OF

ANY DEMOLITION, CONSTRUCTION AND CLEAN-UP WORK.

6. THE TEMPORARY FULL HEIGHT CONTAINMENT ENCLOSURES SHOULD BE CONSTRUCTED OF A MINIMUM 6 MIL HEAVY DUTY REINFORCED, FIRE-RETARDANT POLY SHEETING (VISQUEEN) WITH THE USE OF THE APPROPRIATE TELESCOPICALLY ADJUSTABLE ALUMINUM OR METAL VERTICAL SPRING LOADED SUPPORT STUDS/POLES FOR 24 HOURS WHILE BUILDING 1-HR. FIRE-RATED DOUBLE-WALLED SHEETROCK TO FACILITATE A CONSTRUCTION WALL TO CONTAIN AN AREA. USE FIRE-RETARDANT ZIPPER WALL FOR A SINGLE ROOM (STRUCTURAL IMPROVEMENT PURPOSES), USE 1-HR FIRE RATE DOUBLE-WALLED SHEETROCK TO FACILITATE A CONSTRUCTION WALL IN A CONSTRUCTION AREA. FULL HEIGHT FOAM PADDED RAILS, PRESSURE FIT AT ALL PERIMETER WALL/PARTITION CONNECTION CONDITIONS ARE TO BE UTILIZED IN ORDER TO MINIMIZE THE USE OF TAPE SEALS ON ALL FINISHED

WALL SURFACES.

7. WHEN ALL WORK IS COMPLETED FOR THE PREARRANGED SPECIFIC LOCATION(S), SCHEDULED TASKING AND IDENTIFIED PERIOD OF TIME THE ENTIRE AREA IS TO BE FULLY CLEANED-UP WITH HEPA FILTER USE, ALL TEMPORARY CONTAINMENT ENCLOSURES AND PROTECTION REMOVED WITH ALL FURNITURE AND EQUIPMENT RETURNED TO THEIR PRIOR FUNCTIONING POSITIONS NOTE: FULLY CLEANED-UP MEANS COMMERCIALLY VACUUM CLEANED WITH ALL SURFACES BEING FULLY WIPED DOWN AND DUST FREE AS ACCEPTED BY THE VA PRIOR TO THE CONTRACTORS

WORK.

8. ALL SPACES WILL BE RETURNED TO THE USER, BY THE CONTRACTOR, AS A COMMERCIALLY CLEAN ENVIRONMENT WITH ALL OPEN CONSTRUCTION SURFACES SEALED WITH TEMPORARY CONSTRUCTION MATERIALS INCLUDING THE USE OF 6 MIL HEAVY DUTY REINFORCED, FIRE-RETARDANT POLY SHEETING (VISQUEEN), IN ORDER TO AVOID DUST PARTICLES FROM THE CONSTRUCTION AREA MIGRATING INTO THE OCCUPIED USERS AREA/SPACE/ROOM(S).

9. UNLESS DIRECTLY SPECIFIED AND CONFIRMED BY THE VA/COR, ALL TEMPORARY PROTECTION AND ENCLOSURES ARE TO BE SET-UP AND KNOCKED-DOWN ON A DAILY BASIS SUCH THAT THE USERS OF THE OCCUPIED AREAS ARE NOT TO BE INCONVENIENCED AND PREVENTED FROM FUNCTIONING WITHIN THEIR SPACE/AREA/ROOM(S) DURING THEIR

NORMAL BUSINESS HOURS OF OPERATION.

10. MINIMUM TWICE A DAY INSPECTION OF FIRE-RETARDANT POLY SHEET (VISQUEEN) TO ENSURE IT SEALS, HAS NO

HOLES, ETC. INCLUDE A LOG OF THE MAINTENANCE.

11. BEFORE WORK COMMENCES FOR EACH SPECIFIC AREA OR LOCATION OF SCHEDULED WORK, VERIFY AND

COORDINATE ALL PROTECTION REQUIREMENTS WITH INFECTION CONTROL, SAFETY AND COR.

OCCUPIED AREA

PROTECTION PROTOCOLS

NORMAL WORK SHIFT HOURS FOR THE BUFFALO VA MEDICAL CENTER ARE 7:00AM UNTIL 5:00PM DAILY, MONDAY

THROUGH FRIDAY

1. CERTAIN WORK ITEMS AND CONSTRUCTION ACTIVITIES THAT CREATE NOISE, DUST, VIBRATIONS AND THAT WOULD CREATE DISTURBANCES TO THE MEDICAL CENTER AND/OR ANY OF THE ADJACENT OCCUPIED AREAS WILL NEED TO BE PERFORMED DURING PERIODS OF AFTERHOURS/OFF-HOURS WORK. ITEMS THAT WILL REQUIRE AFTER HOURS ACTIVITIES SHALL BE FULLY COORDINATED WITH VA COR PRIOR TO START OF

CONSTRUCTION.

2. AFTERHOURS/OFF-HOURS OF OPERATION SHALL BE SCHEDULED FOR THE FOLLOWING DAYS AND TIMES AS

COORDINATED, SCHEDULED AND AUTHORIZED BY THE COR:

a. MONDAY THROUGH FRIDAY - 5 PM UNTIL 12 AM

b. WEEKENDS (AS ALLOWED) - TIMES TO BE DETERMINED WITH THE COR

c. CONTRACTOR SHALL COORDINATE ALL AFTER HOURS AND WEEKEND WORK WITH NOISE ORDINANCE

REQUIREMENTS FOR THE CITY OF BUFFALO AND SURROUNDING JURISDICTIONS.

4. THE FOLLOWING CONSTRUCTION ACTIVITIES SHALL BE CONSIDERED AFTER HOURS/OFF-HOURS OPERATIONS:

a. THE MOVING OF CONSTRUCTION MATERIALS, EQUIPMENT, TOOLS AND/OR DEMOLITION MATERIALS

TO/FROM THE EXTERIOR TO INTERNAL AREAS OF WORK

b. ALL WORK IN THE ADJACENT OCCUPIED SPACES TO THE CURRENT STAGE/AREA OF WORK

c. ALL WORK THAT WILL REQUIRE SYSTEM SHUTDOWNS

d. ALL CONCRETE OR METAL DECKING CORING, CUTTING OR DRILLING

e. THE APPROVED USE OF POWER ACTUATED FASTENERS

f. ALL WORK (DEMOLITION OR NEW) THAT WILL CAUSE IMPACT NOISE AND VIBRATIONS THAT CAN BE

HEARD OR FELT IN THE SURROUNDING ADJACENT OCCUPIED SPACES/AREAS

g. CONTRACTOR MUST PARK WITHIN APPROVED CONSTRUCTION AREA OR AT DESIGNATED AREAS AT FAR PORTIONS OF EXISTING CAMPUS PARKING LOTS. CAMPUS PARKING IS LIMITED AND PRIORITY IS GIVEN

TO PATIENTS AND STAFF.

WEEKEND AND HOLIDAY HOURS SHALL BE AS ALLOWED AND COORDINATED WITH THE VA COR.

MISCELLANEOUS

1. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND ELEVATIONS IN THE FIELD PRIOR TO

COMMENCING WORK.

2. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF DIMENSIONS SHOWN ON THE

DRAWINGS. NOTIFY THE VA/COR OF ANY DISCREPANCY BEFORE STARTING WORK.

3. A SUCCESSFUL REVIEW OF SHOP DRAWINGS AND SUBMITTALS BY THE ARCHITECT/ENGINEER

DOES NOT RELIEVE CONTRACTOR OF THE RESPONSIBILITY TO REVIEW AND CHECK SHOP

DRAWINGS BEFORE SUBMITTAL TO VA/COR. THE CONTRACTOR REMAINS SOLELY RESPONSIBLE

FOR ERRORS AND OMISSIONS ASSOCIATED WITH THE PREPARATION OF SHOP DRAWINGS AS

THEY PERTAIN TO DETAILS AND GIVEN DIMENSIONS IN THE CONTRACT DOCUMENTS AND FULL

COMPLIANCE WITH THE BASIS-OF-DESIGN CRITERIA.

4. CONTRACTOR SHALL OBTAIN VA/COR WRITTEN APPROVAL PRIOR TO PROCEEDING WITH ANY

CHANGES OR VARIANCES FROM THE INFORMATION PROVIDED HEREIN.

P1. PROVIDE ALL PAINTING AND RELATED WORK AS SHOWN ON THE DRAWING AND/OR AS REASONABLY IMPLIED BY THE SPECIFICATIONS AND THE PROJECT REQUIREMENTS TO PROVIDE A COMPLETELY FINISHED PROJECT.

P2. ALL SCRATCHES, DENTS, CRACKS AND/OR OPENINGS ON EXISTING AND NEW WALL SURFACES ARE TO BE FILLED WITH PLASTER PATCH, SPAKLING COMPOUND OR OTHER PRESCRIBED MATERIAL IN AN INDUSTRY APPROVED MANNER AND SANDED SMOOTH TO PROVIDE A "LIKE NEW" SURFACE CONDITION BEFORE PAINTING AND FINISHING.

P3. ALL SURFACES ARE TO BE CLEANED FREE OF LOOSE DIRT, DUST, OIL, GREASE AND ALL FOREIGN MATTER JUST PRIOR

TO FINISHING.

P4. PROVIDE ALL LABOR, MATERIALS, BRUSHES, TOOLS, LADDERS AND ALL EQUIPMENT OF ANY KIND NECESSARY FOR

PROPER EXECUTION OF THE WORK.

P5. WORKMANSHIP SHALL BE FIRST CLASS IN EVERY RESPECT WITH ALL MATERIALS EVENLY SPREAD AND SMOOTH

WITHOUT RUNS, SAGS, OR DEBRIS IN THE FINISHED SURFACE.

FIRST CLASS WORKMANSHIP: AN INDUSTRY, DISCIPLINE AND SPECIFIC TRADE RECOGNIZED BEST PRACTICES FOR MATERIALS PROVIDED, INSTALLATION TECHNIQUES UTILIZED AND THE FINAL EXECUTION SUCH THAT ALL MATERIALS AND/OR EQUIPMENT IS PROPERLY INSTALLED, FUNCTIONING CORRECTLY, VISUALLY AS INTENDED AND CLEARLY REPRESENTATIVE OF THE HIGHEST QUALITY OF PROFESSIONAL INSTALLATION THAT IS WITHOUT

DEFECT.

P6. THE PRIME COAT SHALL BE TINTED TO APPROXIMATE SHADE OF FINAL COAT. ALL SECTIONS, SPOTS OR HOT SPOTS AFTER PRIMARY APPLICATION SHALL BE TOUCHED-UP BEFORE APPLYING THE SECOND COAT TO PRODUCE A SMOOTH AND LEVEL SURFACE. THE FINAL COAT SHALL NOT BE APPLIED UNTIL AFTER ALL OTHER TRADES, WHOSE OPERATIONS WOULD BE DETRIMENTAL TO FINISH PAINTING, HAVE FINISHED THEIR WORK IN THE AREAS TO BE

PAINTED.

P7. WORK NOT INCLUDED: UNLESS OTHERWISE INDICATED, SHOP PRIMING OF FERROUS METAL ITEMS AND FABRICATED COMPONENTS ARE INCLUDED UNDER THEIR RESPECTIVE TRADES. PRE-FINISHED ITEMS ARE NOT INCLUDED.

FINISHED METALS SUCH AS ANODIZED ALUMINUM, STAINLESS STEEL, BRONZE, AND SIMILAR METALS WILL NOT BE PAINTED, UNLESS OTHERWISE SPECIFIED. DO NOT PAINT ANY MOVING PARTS OF OPERATING UNITS, OR OVER ANY EQUIPMENT IDENTIFICATION, PERFORMANCE RATINGS, NAMES OR NOMENCLATURE PLATES OR CODE-REQUIRED

LABELS.

P8. PROTECT WORK OF OTHER TRADES. CORRECT ANY PAINTING RELATED DAMAGES BY CLEANING, REPAIRING OR

REPLACING, AND REFINISHING, AS DIRECTED BY THE COR.

P9. PROPERLY PREPARE ALL SURFACES TO RECEIVE FINISHES AND APPLY PRIME COATS, PAINTING AND FINISHING MATERIALS IN ACCORDANCE WITH EACH MANUFACTURER'S DIRECTIONS FOR A QUALITY APPLICATION. USE APPLICATORS AND TECHNIQUES BEST SUITED FOR MATERIALS AND SURFACES TO WHICH APPLIED.

P10. APPLY ADDITIONAL COATS WHEN UNDERCOATS, STAINS OR OTHER CONDITIONS SHOW THROUGH FINAL PAINT OR

FINISHED COAT, UNTIL THE SURFACE FILM IS OF UNIFORM FINISH COLOR AND APPEARANCE.

P11. APPLY EACH MATERIAL AT NOT LESS THAN THE MANUFACTURER'S RECOMMENDED SPREADING RATE, TO PROVIDE A TOTAL DRY FILM THICKNESS OF NOT LESS THAN 2.5 MILS FOR ENTIRE COATING SYSTEM OF (1) PRIME AND (2) FINISH COATS FOR 3 COAT WORK ON PAINTED SURFACES. COR SHALL INSPECT BETWEEN EACH PRECEDING COAT.

P12. PAINTED SURFACE PREPARATION - COMPLY WITH PAINT MANUFACTURER'S RECOMMENDATIONS FOR EACH MATERIAL TYPE AND SURFACE FINISH AS PER THEIR REFERENCE GUIDE AND SPECIFICATIONS.

P13. METAL SURFACE PREPARATION - ALL METAL SURFACES TO BE PAINTED MUST BE CLEAN AND FREE OF RUST, MILL SCALE, GREASE, OIL, DIRT AND OTHER FOREIGN MATTER. ALL ALUMINUM MUST BE CLEANED WELL IN ORDER TO REMOVE ALL SURFACE FILM AND OILS, AND SHALL BE PROPERLY PRIMED IN ACCORDANCE WITH THE PAINT

MANUFACTURER'S RECOMMENDATIONS.

P14. ANY STEEL BEAMS INSTALLED SHALL BE PRIMED, AT A MINIMUM. ALL EXISTING STRUCTURAL STEEL BEAMS ARE FIREPROOFED. ANY NEW STRUCTURAL STEEL INSTALLED IN THE EXISTING BUILDING SHALL BE FIREPROOFED.

WHEREVER THE WORK BEING PERFORMED BY THIS PROJECT REQUIRES THE REMOVAL/DEMOLITION FROM, OR THE INSTALLATION OF NEW CONDUIT, JUNCTION BOXES, CABINETS, PANELS, DEVICES, EQUIPMENT, ETC., TO FINISH PAINTED SURFACES, THE CONTRACTOR SHALL PROVIDE ALL PAINTING TO THE EXISTING WALL/CEILING SURFACES AND NEW MATERIALS BEING INSTALLED TO MATCH ALL OF THE EXISTING FINISHED CONDITIONS SO THAT WHEN THE WORK PERFORMED IS COMPLETED IT BLENDS WITH THE EXISTING FINISHING DÉCOR AND DOESN'T STAND OUT AS BEING A REPAIR, UNFINISHED OR NEW WORK THAT DOESN'T BLEND WITH THE EXISTING CONDITIONS. PAINTING/REPAINTING SHALL OCCUR IN ALL INSTANCES FROM FLOOR TO CEILING AND FROM A WALL CORNER TO A WALL CORNER CHANGE IN PLANE WITH ALL EXISTING PAINTED SURFACES RECEIVING A NEW

FINISH COAT AS A MINIMUM, SEE BELOW:

1. CENTER ALL CEILING GRIDS IN ROOMS TO MAXIMUM EXTENT POSSIBLE, UNLESS OTHERWISE NOTED. SEE CEILING PLANS FOR COMPLETE INFORMATION. COORDINATE WITH SPRINKLER, MECHANICAL, PLUMBING, ELECTRICAL, STRUCTURAL AND EQUIPMENT DRAWINGS.

2. CENTER ALL FIXTURES WITHIN CEILING TILE UNLESS OTHERWISE NOTED. COORDINATE WITH ELECTRICAL

DRAWINGS.

3. REFER TO ROOM FINISH SCHEDULES FOR CEILING HEIGHTS.

4. COORDINATE WITH MECHANICAL AND ELECTRICAL DRAWINGS FOR ADDITIONAL CEILING ACCESS POINTS WHICH

MAY BE REQUIRED AT AREAS FOR MECHANICAL AND ELECTRICAL ACCESS SERVICE WORK.

5. ALL ELECTRICAL AND SAFETY DEVICES SHALL BE CENTERED IN CEILING GRIDS AND COORDINATE WITH

REFLECTED CEILING PLANS AND ELECTRICAL DRAWINGS.

6. COORDINATE THE LOCATIONS OF MECHANICAL SUPPLY AND RETURN GRILLES WITH REFLECTED CEILING PLANS

AND MECHANICAL DRAWINGS.

7. RELOCATE EXISTING SPRINKLER HEADS AS PER NEW REFLECTED CEILING PLAN GRIDS.

8. RELOCATE EXISTING SPRINKLER HEADS WHERE SPRINKLER HEADS CONFLICT WITH LIGHTING, GRIDS OR

DEVICES.

9. COORDINATE LOCATION OF SPRINKLER HEADS WITH DIFFUSERS AND LIGHTING LAYOUT.

10. REFER TO FIRE PROTECTION DRAWINGS FOR NEW SPRINKLER LAYOUT.

1. THIS WORK ENTAILS INTERFACING WITH PROPRIETARY IT SYSTEMS: FIRE PROTECTION, ALARMING, SECURITY

AND CONTROLS.

2. INFORMATION ON THESE SYSTEMS IS CONTROLLED BY SPECIFIC SYSTEMS CONTRACTOR.

3. CONTRACTOR SHALL WORK WITH VA AND SYSTEMS CONTRACTORS TO DETERMINE WIRE ROUTING, WIRING TYPES FOR EACH SYSTEM, END POINTS OF CONTRACTOR INSTALLED WIRING AND ANY MODIFICATIONS

REQUIRED TO SYSTEMS HARDWARE.

4. ALL WIRING ON THESE SYSTEMS IS SHOWN AS "TYPICAL" AND MAY BE REVISED BASED ON SYSTEMS

CONTRACTORS GUIDANCE.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

K:

\C

C G

_P R

O

JE

C

TS

\2

1\

-1

Pa rk in g R am p

(B uf fa lo

, N Y)

\4

- D es

D oc s\

2- D ra w in gs

\W O

R

KI

N G

\2 1-

3_

G I0

.d w g

6/

/2

:3 9:

P

M

ISSUE FOR BIDOffice of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

PARKING RAMP EXPANSION

3495 BAILEY AVE., BUFFALO, NY 14215

528-18-375

Project Director

Revisions: Date:

www. bancroft-ae.com

3300 Dundee Rd.

Northbrook, IL 60062

T: 847.952.9362

08-09-2024

ISSUE FOR BID 08-09-2024

GENERAL NOTES -

WALL AND CEILING PAINTING

GENERAL NOTES - CEILING

SECURITY, FIRE PROTECTION, AND

CONTROL SYSTEM NOTES

GENERAL NOTES - CONSTRUCTION

PERIOD STAGING OF WORK

GENERAL SCOPE OF WORK (SOW)

DESCRIPTION

DEDUCT ALTERNATE #1: DELETE ALL SITE RELATED WORK IN PARKING LOT B

- THIS DEDUCT DELETES:

-- THE NEW TRAFFIC ISLANDS ADJACENT TO PARKING LOT B

-- SIGNAGE AND STRIPING AT THE NORTH END OF PARKING LOT B

-- ADDITIONAL HANDICAP PARKING AND RELOCATION OF THE EXISTING WHEELCHAIR HUT

- PARKING LOT B WOULD REMAIN AS EXISTING WITH NO SCOPE OF WORK

- REFER TO CIVIL DRAWINGS FOR ADDITIONAL INFORMATION

DEDUCT ALTERNATE #2: SUBSTITUTE OR REMOVE VINYL WAYFINDING GRAPHICS

- THIS DEDUCT:

-- SUBSTITUTES THE USE VINYL WALL GRAPHICS ON THE SOUTH WALL OF STAIR #1 FOR SOLID COLOR

PAINT, ALL LEVELS

-- DELETES PAINTED WAYFINDING STRIPE AND ARROWS FROM THE PARKING DECK, ALL LEVELS

- THE SUBSTITUTION DOES NOT ALTER THE SCOPE AS INDICATED IN THE DRAWINGS.

- VINYL GRAPHICS WILL REMAIN ON THE GLAZED ENTRY WALL TO STAIR #1 AS INDICATED IN THE DRAWINGS.

- THE PAINTED CROSSWALK SHOWN ON THE PARKING DECK WILL REMAIN AS INDICATED IN THE DRAWINGS.

- REFER TO ARCHITECTURAL WAYFINDING SHEETS FOR ADDITIONAL INFORMATION.

DEDUCT ALTERNATE #3: DELETE PHOTOVOLTAIC CANOPY

- THIS DEDUCT:

-- DELETES ALL SOLAR PANELS, ELECTRICAL COMPONENTS, AND ASSOCIATED STRUCTURE FROM THE

UPPER LEVEL OF THE PARKING GARAGE

-- DELETES ALL LINEAR SUSPENDED LIGHT FIXTURES UNDER THE CANOPY

-- INSTALLS SALVAGED LIGHT POLES ON THE UPPER LEVEL OF THE GARAGE

- REFER TO ARCHITECTURAL PLANS, ARCHITECTURAL SECTIONS, AND ELECTRICAL LIGHTING PLANS FOR

ADDITIONAL INFORMATION

DEDUCT ALTERNATE #4: DELETE SELECT EXTERIOR SCREEN SYSTEMS AND LARGE SIGNAGE

- THIS DEDUCT DELETES:

-- PORTION OF ARCHITECTURAL SCREEN SYSTEM FROM THE EXTERIOR FACADE ON THE SOUTH

ELEVATION OF THE GARAGE

-- CURTAIN GLAZING SYSTEM ON THE EXTERIOR FACADE ON THE WEST ELEVATION OF THE GARAGE -- METAL "VA" LETTER SIGNAGE ACCOMPANYING THE GLAZING AND SCREEN SYSTEMS MENTIONED ABOVE

ON BOTH THE WEST AND SOUTH ELEVATIONS.

- REFER TO ARCHITECTURAL PLANS AND ELEVATIONS FOR ADDITIONAL INFORMATION.

DEDUCT ALTERNATE #5: DELETE PORTION OF STRUCTURAL RESTORATION WORK

- THIS DEDUCT DELETES THE FOLLOWING PORTIONS OF STRUCTURAL RESTORATION WORK WITHIN THE

EXISTING GARAGE:

-- JOINT SEALANT WORK

-- RECOAT EXISTING WATER PROOFING MEMBRANE

-- REPLACE DAMAGED WATERPROOFING MEMBRANE

-- INJECT LEAKING WALL CRACKS

-- REPLACE STAIR TOWER JOINT SEALANTS

-- PLUMBING REPAIR ALLOWANCE

-- APPLY SILANE SEALER WITH CORROSION INHIBITOR

-- WATERPROOFING MEMBRANE STRIPS TO SUPPORTED LEVELS

- REFER TO STRUCTURAL RESTORATION DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

DEDUCT ALTERNATE #6: DELETE INFILL SCREEN SYSTEMS

- THIS DEDUCT DELETES THE ARCHITECTURAL SCREEN SYSTEMS INFILLING OPENINGS AT ALL LEVELS OF THE

GARAGE

- REMOVES DEMOLITION OF EXISTING STEEL RAILING AT EXISTING LEVELS OF THE GARAGE

- ADDS STEEL RAILING AND FABRIC MESH PANELS BETWEEN TOP/BOTTOM PRECAST PANELS TO ALL OPENINGS

- REFER TO ARCHITECTURAL PLANS AND ELEVATIONS FOR ADDITIONAL INFORMATION.

BID DEDUCT ALTERNATES AND DESCRIPTIONS

DEDUCT ALTERNATE #7: DELETE ONE ELEVATOR INSTALLATION

- THIS DEDUCT DELETES THE INSTALLATION OF ONE ELEVATOR WITHIN THE NEW STAIR / ELEVATOR TOWER

- THE PRECAST STRUCTURE WILL CONTINUE TO BE CONSTRUCTED AS DESIGNED WITH BOTH ELEVATOR SHAFTS

- ONLY ONE ELEVATOR WILL BE INSTALLED ON ONE SIDE OF THE SHAFT

- DOOR OPENINGS WHERE THE SECOND ELEVATOR WOULD HAVE BEEN BUILT WILL BE FILLED IN WITH CONCRETE

MASONRY UNITS

DEDUCT ALTERNATE #8: SUBSTITUTE GLASS GUARDRAILS

- THIS DEDUCT SUBSTITUTES THE GLASS GUARDRAILS IN STAIR #1 FOR PAINTED STEEL GUARDRAILS

- PAINTED STEEL GUARDRAILS SHALL MATCH THOSE BEING CONSTRUCTED IN STAIR #2

- STAINLESS STEEL HANDRAIL SHALL REMAIN AS DESIGNED

- REFER TO ENLARGED ARCHITECTURAL PLANS FOR ADDITIONAL INFORMATION

DEDUCT ALTERNATE #9: SUBSTITUTE ALUMINUM CURTAINWALL FOR PRECAST CONCRETE PANELS

- THE DEDUCT:

-- DELETES ALUMINUM WINDOWS / OPENINGS IN SOUTH WALL OF STAIR #1

-- SUBSTITUTES A PORTION OF ALUMINUM CURTAINWALL FOR PRECAST CONCRETE CONSTRUCTION IN STAIR #1 -- SUBSTITUTION WILL ALSO ELIMINATE A PORTION OF STEEL STRUCTURAL FRAMING WITHIN STAIR #1

- REFER TO DETAIL 1 THIS SHEET FOR ADDITIONAL INFORMATION

THE FOLLOWING LIST DESCRIBES THE BID DEDUCT ALTERNATES THROUGHOUT THE PROJECT AS NUMBERED IN THE CONTRACT DOCUMENTS

1 PARTIAL FL. PLAN - DEDUCT ALT. #9

AutoCAD SHX Text

AutoCAD SHX Text 1/15/2004

AutoCAD SHX Text 21-113_GI002.dwg

AutoCAD SHX Text

GENERAL - PROTECTION PROTOCOL, SCOPE OF WORK, DEDUCT ALTERNATES

AutoCAD SHX Text

CZ

AutoCAD SHX Text

RB

AutoCAD SHX Text

GI002

AutoCAD SHX Text

AutoCAD SHX Text 2'

AutoCAD SHX Text 4'

AutoCAD SHX Text 8'

AutoCAD SHX Text 16'

AutoCAD SHX Text 1/8"=1'-0"

AutoCAD SHX Text N

GENERAL NOTES FOR CONTRACTORS: SEE ALL PROJECT GENERAL NOTES AND OTHER REQUIREMENTS INCLUDING THE LIFE SAFETY AND INFECTION CONTROL WORK LOCATED WITHIN THE GENERAL DRAWINGS SECTION. COMPLY WITH ALL REQUIREMENTS AS THEY ARE A DIRECT PART OF THIS SECTION AS IF THEY WERE

DIRECTLY INCLUDED AND PROVIDED HEREIN.

PROTECTION PROTOCOLS: VERIFY AND COORDINATE ALL PROTECTION REQUIREMENTS TO BE PROVIDED FOR EACH SPECIFIC AREA OR LOCATION OF SCHEDULED WORK WITH THE VA/COR, BEFORE BEGINNING ANY WORK.

WHEN PERFORMING DEMOLITION WORK IN ANY OCCUPIED SPACES FOLLOW THE “OCCUPIED AREAS PROTECTION

PROTOCOLS” UNLESS MODIFIED IN WRITING BY THE VA/COR ON A CASE BY CASE BASIS.

1. BEFORE BEGINNING ANY DEMOLITION WORK EACH CONTRACTOR AND DISCIPLINE SHALL PERFORM A FULL EXAMINATION OF ALL AREAS OF WORK AND FULLY VERIFY ALL EXISTING CONDITIONS ALONG WITH ALL OF THE AREAS OF WORK FOR ANY UNFORESEEN CONDITIONS OR DISCREPANCIES FROM THE DOCUMENTATION THAT WOULD AFFECT THEIR WORK AND/OR THE WORK OF OTHERS. ANY UNFORESEEN CONDITIONS OR DISCREPANCIES DISCOVERED ARE TO BE IMMEDIATELY IDENTIFIED AND COORDINATED WITH THE GENERAL/PRIME CONTRACTOR WHO SHALL IN TURN DOCUMENT AND PROMPTLY REPORT ANY SUCH CONDITIONS DIRECTLY TO THE VA/COR FOR

DIRECTION ON HOW TO PROCEED BEFORE ALLOWING ANY WORK TO BEGIN.

2. ALL REQUIRED DEMOLITION WORK IS NOT NECESSARILY LIMITED TO WHAT IS ONLY SPECIFICALLY SHOWN OR DIRECTLY CALLED OUT ON THE DEMOLITION PLANS OR THAT IS ONLY SPECIFICALLY IDENTIFIED WITHIN THE DEMOLITION NOTES DESCRIPTIONS.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .