This document appears to be a set of civil engineering construction plans for the Milliken Nature Center at Arch Rock on Mackinac Island, Michigan. The project is being managed by the State of Michigan Department of Technology, Management, and Budget, State Facilities Administration. The plans detail site demolition, site layout, site grading, and storm water management for this nature center project. Key details include the approximate 35,700 square foot limit of construction/disturbance, the requirement to remove an existing septic system, and the addition of an alternate bid item for a new concrete sidewalk. The project is located within the Mackinac Island State Park and is scheduled to be bid out on August 12, 2022.
The plans indicate that the soils on site consist of topsoil over Mackinac Brecchia, which is a mixture of sand, gravel, and limestone rocks. The project specifies general earthwork requirements and a storm structure schedule. Temporary topsoil stockpile areas are also identified. Erosion and sedimentation control requirements are provided, along with a maintenance schedule for the storm system.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCH
ROCK
ROAD
RIFLE RANGE ROAD
APPROXIMATE LIMIT OF TREE REMOVALS
REMOVE EXISTING SEPTIC SYSTEM
CARRIAGE
STAGING AREA
ARCH ROCK
BICYCLE TRAIL
APPROXIMATE LIMIT OF
CONSTRUCTION / DISTURBANCE
ADD ALTERNATE #3: SAW CUT AND
REMOVE EXISTING ASPHALT,
PROVIDE NEW CONCRETE WALK
(CROSS-HATCHED AREA)
SITE DEMOLITION KEY
BARRIER-FREE NOTES
GENERAL NOTES
F
IL
E N
U M
B E
R
S T
A T
E I N
D E
X N
U M
B E
R S
C o n st ru ct io n
F in a l R e co rd
Is su e d f o r
P re lim in a ry
D a te
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
R O
B E
R T
C H
A L L
R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
E a s t
K a la m a z o o A v e n u e
S u it e
K a la m a z o o
M ic h ig a n
-5
.3
.6
P
H O
N E
.3
.6
F A
X
T O
W E
R P
IN
K
S T
E R
.C O
M
A L L R
IG
H
T S
R E
S E
R V
E D
E a s t
F u lt o n S tr e e t, S u it e
G ra n d
R a p id s M ic h ig a n
.4
.9
P
H O
N E
.4
.5
F A
X
S H
E E
T T
IT
L
E
S H
E E
T N
U M
B E
R
O W
N E
R P
R O
J E
C T
T
IT
L E
D A
T E
-1
.0
A U
G U
S T
M
IL
L
IK
E N
N A
T U
R E
C E
N T
E R
A T
A R
C H
R O
C K
M a c k in a c I s la n d
M ic h ig a n
S T
A T
E O
F M
IC
H
IG
A
N
/2
.T
A P
A U
G U
S T
ISSUED FOR BIDS AUGUST 12, 2022
S
IT
E
D E
M O
L
IT
IO
N
P L A
N
C .0
ARCH
ROCK
ROAD
RIFLE RANGE ROAD
NATURE
CENTER
CARRIAGE
STAGING AREA
DECK
RESTROOMS
ARCH ROCK
BICYCLE TRAIL
APPROXIMATE LIMIT OF
CONSTRUCTION / DISTURBANCE
SEE ENLARGED PLAN
BELOW LEFT
ADD ALTERNATE #3: SAW CUT AND
REMOVE EXISTING ASPHALT,
PROVIDE NEW CONCRETE WALK
(CROSS-HATCHED AREA)
BARRIER-FREE NOTES
GENERAL NOTES
PROPOSED FEATURES LEGEND:
F
IL
E N
U M
B E
R
S T
A T
E I N
D E
X N
U M
B E
R S
C o n st ru ct io n
F in a l R e co rd
Is su e d f o r
P re lim in a ry
D a te
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
R O
B E
R T
C H
A L L
R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
E a s t
K a la m a z o o A v e n u e
S u it e
K a la m a z o o
M ic h ig
-5
.3
.6
P
H O
.3
.6
F A
X
T O
W E
R P
IN
K
S T
E R
.C O
M
A L L R
IG
H
T S
R E
S E
R V
E D
E a s t
F u lt o n S tr e e t, S u it e
G ra n d
R a p id s M ic h ig a n
.4
.9
P
H O
N E
.4
.5
F A
X
S H
E E
T T
IT
L
E
S H
E E
T N
U M
B E
R
O W
N E
R P
R O
J E
C T
T
IT
L E
D A
T E
-1
.0
A U
G U
S T
M
IL
L
IK
E N
N A
T U
R E
C E
N T
E R
A T
A R
C H
R O
C K
M a c k in a c I s la n d
M ic h ig a n
S T
A T
E O
F M
IC
H
IG
A
N
/2
.T
A P
A U
G U
S T
ISSUED FOR BIDS AUGUST 12, 2022
S
IT
E
L A
Y O
U T
P L A
N
C
.0ENLARGED PLAN
AT STEPS
RIFLE RANGE ROAD
CARRIAGE
STAGING AREA
FFE 708.00
FFE 708.00
SEE 7 / C6.0 FOR
CLEANOUT DETAILS
FIELD VERIFY EXISTING PICNIC
AREAS AND CLOSELY
COORDINATE NEW WORK,
REPORT ANY DISCREPANCIES
TO ARCHITECT PRIOR TO
STARTING CONSTRUCTION
SEE NEXT SHEET FOR AREAS WHERE
MULCH BLANKETS ARE REQUIRED.
F
IL
E N
U M
B E
R
S T
A T
E I N
D E
X N
U M
B E
R S
C o n st ru ct io n
F in a l R e co rd
Is su e d f o r
P re lim in a ry
D a te
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
R O
B E
R T
C H
A L L
R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
E a s t
K a la m a z o o A v e n u e
S u it e
K a la m a z o o
M ic h ig
-5
.3
.6
P
H O
.3
.6
F A
X
T O
W E
R P
IN
K
S T
E R
.C O
M
A L L R
IG
H
T S
R E
S E
R V
E D
E a s t
F u lt o n S tr e e t, S u it e
G ra n d
R a p id s M ic h ig a n
.4
.9
P
H O
N E
.4
.5
F A
X
S H
E E
T T
IT
L
E
S H
E E
T N
U M
B E
R
O W
N E
R P
R O
J E
C T
T
IT
L E
D A
T E
-1
.0
A U
G U
S T
M
IL
L
IK
E N
N A
T U
R E
C E
N T
E R
A T
A R
C H
R O
C K
M a c k in a c I s la n d
M ic h ig a n
S T
A T
E O
F M
IC
H
IG
A
N
/2
.T
A P
A U
G U
S T
ISSUED FOR BIDS AUGUST 12, 2022
S
IT
E
G R
A D
IN
G
P L A
N
C .0
BARRIER-FREE NOTES
GENERAL NOTES
ENLARGEMENT AT CHANNEL DRAIN
GENERAL EARTHWORK NOTES:
STORM STRUCTURE SCHEDULENOTE: EARTHWORK IS UNCLASSIFIED AND INCLUDES
ALL WORK REQUIRED REGARDLESS OF CHARACTER
OF MATERIALS ENCOUNTERED. REFER TO
SPECIFICATIONS FOR ADDITIONAL INFORMATION.
APPROX. DISTURBED AREA:
35,700 SFT (0.82 ACRE)
TEMPORARY TOPSOIL STOCKPILE
AREA ALREADY PAVED /
NOT DISTURBED: 6400 SFT
PROJECT
AREA
LAKE
HURON
250'
M -185
F
IL
E N
U M
B E
R
S T
A T
E I N
D E
X N
U M
B E
R S
C o n st ru ct io n
F in a l R e co rd
Is su e d f o r
P re lim in a ry
D a te
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
R O
B E
R T
C H
A L L
R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
E a s t
K a la m a z o o A v e n u e
S u it e
K a la m a z o o
M ic h ig
-5
.3
.6
P
H O
.3
.6
F A
X
T O
W E
R P
IN
K
S T
E R
.C O
M
A L L R
IG
H
T S
R E
S E
R V
E D
E a s t
F u lt o n S tr e e t, S u it e
G ra n d
R a p id s M ic h ig a n
.4
.9
P
H O
N E
.4
.5
F A
X
S H
E E
T T
IT
L
E
S H
E E
T N
U M
B E
R
O W
N E
R P
R O
J E
C T
T
IT
L E
D A
T E
-1
.0
A U
G U
S T
M
IL
L
IK
E N
N A
T U
R E
C E
N T
E R
A T
A R
C H
R O
C K
M a c k in a c I s la n d
M ic h ig a n
S T
A T
E O
F M
IC
H
IG
A
N
/2
.T
A P
A U
G U
S T
ISSUED FOR BIDS AUGUST 12, 2022
S E
S C
P L A
N
C .1
VICINITY MAP
NOTE: PROJECT AREA IS PART OF MACKINAC
ISLAND STATE PARK AND DOES NOT HAVE AN
INDIVIDUAL LEGAL DESCRIPTION
SOIL TYPE: TOPSOIL OVER MACKINAC
BRECCHIA (SAND, GRAVEL, LIMESTONE ROCKS)
NOTE: SEQUENCE SHOWN ABOVE IS
PRELIMINARY, CONTRACTOR SHALL
SUBMIT DETAILED CONSTRUCTION
SEQUENCE, SESC PLAN AND COST
ITEMIZATION FOR DTMB APPROVAL
SESC REQUIREMENTS:
STORM SYSTEM MAINTENANCE SCHEDULE:
| 15 - C0.0 |
| 15 - C1.0 |
| 15 - C2.0 |
| 15 - C3.0 |
| 15 - C3.1 |
| 06 751.21042.TAP_Milliken Nature Center at Park Arch_CD Drawings - 02 Civil 1.pdf |
| 15 - C0.0 |
| 15 - C1.0 |
| 15 - C2.0 |
| 15 - C3.0 |
| 15 - C3.1 |
| 06 751.21042.TAP_Milliken Nature Center at Park Arch_CD Drawings - 02 Civil 1.pdf |
| 15 - C0.0 |
| 15 - C1.0 |
| 15 - C2.0 |
| 15 - C3.0 |
| 15 - C3.1 |
File details come from the government source that posted it. Updated .