This document is a State of Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Division 0 Specification for a construction project titled "Milliken Nature Center, Agency No. 751, File No. 751.21042.TAP". The work includes the construction of a new Nature Center and Restrooms to be located at the Mackinac Island State Park - Arch Rock Plaza. The bid deadline is November 9, 2022 at 2:00 PM ET. A mandatory pre-bid conference will be held on September 23, 2022 at 10:00 AM ET via Zoom, and a site tour will be held on September 27, 2022 from 12:30 PM to 2:30 PM ET. Bids must remain open for 60 calendar days after the bid opening. The contract times and associated liquidated damages are specified in the agreement.

The bid documents provide detailed technical specifications for the project, including the required materials, equipment, and subcontractors. Bidders must submit bid security in the form of a certified check, cashier's check, or bid bond in the amount of 5% of the base bid. The apparent low bidder will be required to submit additional qualification submittals within 5 calendar days of the request. The owner reserves the right to reject any or all bids and to waive any irregularities.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This is a Cover Sheet to the State’s Owner and Contractor Standard Construction Contract, known as the MICHSPEC Division 0

Specifications. The MICHSPEC Division 0 Specifications have been developed from the FORMSPEC Michigan Model, 1997 Edition. Although the State’s 2008 Version of the Division 0 Specifications are written as simply as practical, it is nonetheless advisable to consult with companion Guide to Specifiers when preparing specifications for a specific project. These Division 0 Specifications were developed by incorporating provisions and requirements furnished by the State into the FORMSPEC Michigan Model. These Division 0 Specifications have undergone detailed technical reviews by Department of Technology, Management and Budget, State Facilities Administration representatives and detailed legal reviews by the Department of the Attorney General for the State of Michigan. Specifiers are encouraged to consult with a Division 0 specifications specialist or an attorney knowledgeable in public contracts when preparing specifications for a specific project.

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

MICHSPEC 2008 VERSION, OWNER AND CONTRACTOR

STANDARD CONTRACT FORMS AND CONDITIONS OF THE CONTRACT

MICHSPEC No. 97.0820 − 00020 THROUGH 97.0820 − 00440

RELEASED ON NOVEMBER 1, 1997.

Developed from

Contract Forms and Conditions of the Contract

FORMSPEC Michigan Model and suggested for use with

Bidding Requirements

751/21042.TAP

DNR

Natural Resources Milliken Nature Center – Arch Rock Plaza

Mackinac Island State Park

August 22, 2022

1997 Edition/Rev 02/22 Version

STATE OF MICHIGAN (OWNER & CONTRACTOR) TABLE OF CONTENTS

MICHSPEC DTMB 00010 − 1 (Rev. 02/22)

SECTION 00010 TABLE OF CONTENTS

SECTION/PAGE NO.

SUBJECT INDEX

SECTION 00020 GLOSSARY ............................................................................................................................................. 00020 - 1

SECTION 00030 ADVERTISEMENT .................................................................................................................................. 00030 - 1

SECTION 00100 INSTRUCTIONS TO BIDDERS ............................................................................................................... 00100 - 1

ARTICLE 1 BIDDING DOCUMENT INTERPRETATIONS .................................................................................................. 00100 - 1

ARTICLE 2 QUALIFICATIONS OF BIDDERS ..................................................................................................................... 00100 - 1

ARTICLE 3 BIDDING DOCUMENTS; SITE CONDITIONS; SAFETY REQUIREMENTS; LAWS ....................................... 00100 - 2

ARTICLE 4 INTERPRETATIONS; ADDENDA .................................................................................................................... 00100 - 3

ARTICLE 5 BID SECURITY ................................................................................................................................................ 00100 - 3

ARTICLE 6 CONTRACT TIME; LIQUIDATED DAMAGES .................................................................................................. 00100 - 4

ARTICLE 7 MATERIALS AND EQUIPMENT ...................................................................................................................... 00100 - 4

ARTICLE 8 SUBCONTRACTORS ...................................................................................................................................... 00100 - 5

ARTICLE 9 BID FORM AND BID FORM ATTACHMENTS ................................................................................................. 00100 - 5

ARTICLE 10 PREPARATION AND SUBMISSION OF BIDS.................................................................................................. 00100 - 6

ARTICLE 11 BID WITHDRAWAL; BID MODIFICATION ........................................................................................................ 00100 - 6

ARTICLE 12 BID OPENING; OBJECTION TO THE AWARD ................................................................................................ 00100 - 7

ARTICLE 13 BIDS TO REMAIN OPEN .................................................................................................................................. 00100 - 7

ARTICLE 14 AWARD OF THE CONTRACT .......................................................................................................................... 00100 - 7

ARTICLE 15 EXECUTION OF THE AGREEMENT ................................................................................................................ 00100 - 9

ARTICLE 16 MOBILIZATION PAY ITEM ............................................................................................................................. 00100 -10 ARTICLE 17 SOIL EROSION AND SEDIMENTATION CONTROL–FINE FOR NON-COMPLIANCE .................................. 00100 -10 ATTACHMENT A TO SECTION 00100: BIDDER'S CHECK LIST........................................................................................ 00110 - 1

SECTION 00120 SUPPLEMENTARY INSTRUCTIONS ..................................................................................................... 00120 - 1

SECTION 00210 INFORMATION FOR BIDDERS .............................................................................................................. 00210 - 1

SECTION 00300 BID SUMMARY ...................................................................................................................... 00300 - SUMMARY

SECTION 00300 BID FORM ............................................................................................................................................... 00300 - 1

ARTICLE 1 THIS BID IS SUBMITTED TO THE STATE OF MICHIGAN ("THE OWNER"). ................................................. 00300 - 1

ARTICLE 2 THE BIDDER'S REPRESENTATIONS ............................................................................................................... 00300 - 1

ARTICLE 3 TIME OF COMPLETION ..................................................................................................................................... 00300 - 2

ARTICLE 4 ATTACHMENTS INCLUDED WITH THIS BID .................................................................................................... 00300 - 2

ARTICLE 5 DEFINED TERMS ............................................................................................................................................... 00300 - 2

ARTICLE 6 BID SCHEDULE .................................................................................................................................................. 00300 - 3

ARTICLE 7 SCHEDULE OF CHANGE ORDER PRICES ...................................................................................................... 00300 - 5

ARTICLE 8 BID SUBMITTED ON ......................................................................................................................................... 00300 - 6

SECTION 00310 BID BOND ............................................................................................................................................... 00310 - 1

SECTION 00320 NONCOLLUSION AFFIDAVIT ................................................................................................................ 00320 - 1

SECTION 00410 BID BREAKDOWN ................................................................................................................................. 00410 - 1

SECTION 00420 QUESTIONNAIRE ................................................................................................................................... 00420 - 1

ARTICLE 1 ORGANIZATION ............................................................................................................................................... 00420 - 1

ARTICLE 2 SPECIALTY CONTRACTOR LICENSES .......................................................................................................... 00420 - 1

ARTICLE 3 EXPERIENCE ................................................................................................................................................... 00420 - 1

ARTICLE 4 ADDITIONAL QUALIFICATIONS ...................................................................................................................... 00420 - 2

ARTICLE 5 REFERENCES .................................................................................................................................................. 00420 - 2 REFERENCES ATTACHMENT ......................................................................................................................... 00420 - 3

SECTION 00430 LIST OF SUBCONTRACTORS ............................................................................................................... 00430 - 1

SECTION 00440 SCHEDULE OF MATERIALS AND EQUIPMENT .................................................................................. 00440 - 1

ARTICLE 1 BID MATERIALS AND EQUIPMENT −LISTED (NAMED OR SPECIFIED) ITEMS ........................................... 00440 - 1

ARTICLE 2 BID MATERIALS AND EQUIPMENT − OPEN SPECIFICATIONS .................................................................... 00440 - 3

SECTION 00500 AGREEMENT .......................................................................................................................................... 00500 - 1

ARTICLE 1 THE CONTRACT; THE PROJECT; THE WORK .............................................................................................. 00500 - 1

ARTICLE 2 CONTRACT DOCUMENTS .............................................................................................................................. 00500 - 1

ARTICLE 3 CONTRACT PRICE ........................................................................................................................................... 00500 - 2

ARTICLE 4 CONTRACT TIME; LIQUIDATED DAMAGES ................................................................................................... 00500 - 2

ARTICLE 5 PAYMENTS TO CONTRACTOR ...................................................................................................................... 00500 - 3

MICHSPEC DTMB 00010 − 2 (Rev. 02/22)

ARTICLE 6 THE PROFESSIONAL SERVICES CONTRACTOR ......................................................................................... 00500 - 3

ARTICLE 7 CONTRACTOR'S REPRESENTATIONS .......................................................................................................... 00500 - 3

ARTICLE 8 MISCELLANEOUS ............................................................................................................................................ 00500 - 3

ARTICLE 9 NOTICE AND SERVICE .................................................................................................................................... 00500 - 4

SECTION 00520 ATTACHMENT “A” TO AGREEMENT ................................................................................................... 00520 - 1

SECTION 00610 PERFORMANCE BOND ........................................................................................................................ 00610 - 1

SECTION 00620 PAYMENT BOND ................................................................................................................................... 00620 - 1

SECTION 00700 GENERAL CONDITIONS ........................................................................................................................ 00700 - 1

ARTICLE 1 INTERPRETATIONS ........................................................................................................................................... 00700 - 1

1.1 Section 00020 Glossary:............................................................................................................................................... 00700 - 1

1.2 Intent of the Contract Documents: ................................................................................................................................ 00700 - 1

1.3 Priority of the Contract Documents: .............................................................................................................................. 00700 - 2

1.4 Interpretation of Indemnification Provisions: ................................................................................................................. 00700 - 2

1.5 Additional Interpretations: ............................................................................................................................................. 00700 - 2

1.6 Ownership and Use of the Contract Documents: ......................................................................................................... 00700 - 3.

1.7 Copies of the Contract Documents: ............................................................................................................................... 00700 - 3

ARTICLE 2 THE OWNER−GENERAL PROVISIONS .......................................................................................................... 00700 - 3

2.1 Availability of Lands, Areas, Properties and Facilities: ................................................................................................. 00700 - 3

2.2 Reference Points; Base Lines and Benchmarks: .......................................................................................................... 00700 - 3

2.3 Stop Work Order: ......................................................................................................................................................... 00700 - 3.

2.4 Limitations on the Owner’s Responsibilities: ................................................................................................................ 00700 - 4

2.5 Additional General Provisions: ...................................................................................................................................... 00700 - 4

2.6 Partnering Charter: ...................................................................................................................................................... 00700 - 4.

ARTICLE 3 THE PROFESSIONAL − GENERAL PROVISIONS .......................................................................................... 00700 - 4

3.1 Owner’s Representative: ............................................................................................................................................. 00700 - 4

3.2 Clarifications and Interpretations: ................................................................................................................................. 00700 - 4

3.3 Minor Variations and No-Cost Changes; Minor Delays:................................................................................................ 00700 - 5

3.4 Determinations by the Professional: ........................................................................................................................... 00700 - 5

3.5 Limitations on the Professional’s Responsibilities: ....................................................................................................... 00700 - 5

ARTICLE 4 CONTROL OF WORK − GENERAL PROVISIONS ........................................................................................... 00700 - 5

4.1 Review of the Contract Documents: ............................................................................................................................. 00700 - 5

4.2 Management, Supervision, and Personnel: .................................................................................................................. 00700 - 5

4.3 Materials and Equipment: ............................................................................................................................................. 00700 - 6

4.4 Concerning Control of Work: ....................................................................................................................................... 00700 - 6.

4.5 Patent Fees and Royalties: ........................................................................................................................................... 00700 - 7

4.6 Use of Premises: .......................................................................................................................................................... 00700 - 7

4.7 Record Documents: ...................................................................................................................................................... 00700 - 7

4.8 Emergencies: ................................................................................................................................................................ 00700 - 8

4.9 Indemnification: ............................................................................................................................................................ 00700 - 8

ARTICLE 5 SUBCONTRACTORS AND SUPPLIERS .......................................................................................................... 00700 - 8

5.1 Employment of Subcontractors: .................................................................................................................................... 00700 - 8

5.2 "Or Equal" and Substitute Materials and Equipment:.................................................................................................... 00700 - 9

5.3 The Contractor’s Continuing Responsibilities: ............................................................................................................ 00700 - 9

ARTICLE 6 SUBMITTALS .................................................................................................................................................... 00700 - 9

6.1 Shop Drawing, Sample and Other Technical Submittals: ............................................................................................. 00700 - 9

6.2 Review and Return of Technical Submittals: ............................................................................................................. 00700 - 10.

6.3 Progress Schedule Submittals: ................................................................................................................................... 00700 - 10

6.4 Review and Return of Progress Schedule Submittals: .............................................................................................. 00700 - 10.

6.5 Additional Provisions Concerning Submittals: ........................................................................................................... 00700 - 10.

ARTICLE 7 LEGAL REQUIREMENTS; INSURANCE ........................................................................................................ 00700 - 11

7.1 Laws; Permits (Which Include Approvals and Licenses): .......................................................................................... 00700 - 11.

7.2 Sales and Use Tax and Other Similar Taxes: ............................................................................................................ 00700 - 12.

7.3 Safety and Protection: ................................................................................................................................................ 00700 - 12

7.4 Bonds and Insurance - General Requirements: .......................................................................................................... 00700 - 12

7.5 The Contractor’s Liability Insurance:......................................................................................................................... 00700 - 12

7.6 Pollution Liability Insurance: ....................................................................................................................................... 00700 - 13

7.7 Property Insurance (Builder's All Risk Insurance): ...................................................................................................... 00700 - 13

7.8 Waiver of Rights: ........................................................................................................................................................ 00700 - 13

7.9 Receipt and Application of Proceeds: ......................................................................................................................... 00700 - 13

MICHSPEC DTMB 00010 − 3 (Rev. 02/22)

7.10 Unfair Labor Practice: ................................................................................................................................................. 00700 - 13

7.11 Michigan Right-To-Know Law: ................................................................................................................................... 00700 - 13.

7.12 Nondiscrimination: ...................................................................................................................................................... 00700 - 14

7.13 Michigan Residency for Employees: ........................................................................................................................... 00700 - 14

ARTICLE 8 PROSECUTION; SUBSTANTIAL COMPLETION ........................................................................................... 00700 - 15

8.1 Starting the Work: ...................................................................................................................................................... 00700 - 15.

8.2 Revision 0 (Rev. 0) Schedule and Cost Submittals: ................................................................................................... 00700 - 15

8.3 Compliance with Contract Time Requirements: .......................................................................................................... 00700 - 15

8.4 Substantial Completion: .............................................................................................................................................. 00700 - 15

8.5 Partial Use: ................................................................................................................................................................. 00700 - 16

8.6 Division of Responsibilities: ........................................................................................................................................ 00700 - 16

8.7 Suspension of Work: .................................................................................................................................................. 00700 - 16

8.8 Sharing of Total Float on Non-Critical Paths: .............................................................................................................. 00700 - 16

ARTICLE 9 WARRANTY; TESTS, INSPECTIONS, AND

APPROVALS; CORRECTION OF WORK ....................................................................................................... 00700 - 17

9.1 Warranty: ................................................................................................................................................................... 00700 - 17

9.2 Tests, Inspections and Approvals: ............................................................................................................................. 00700 - 17

9.3 Uncovering Work: ...................................................................................................................................................... 00700 - 17

9.4 Correction of Work: .................................................................................................................................................... 00700 - 17

9.5 Special Correction Period Requirements: .................................................................................................................. 00700 - 18

9.6 Special Maintenance Requirements: ......................................................................................................................... 00700 - 18

ARTICLE 10 CHANGES ..................................................................................................................................................... 00700 - 19

10.1 Changes in the Work: ................................................................................................................................................ 00700 - 19

10.2 Differing Subsurface or Physical Site Conditions: ..................................................................................................... 00700 - 19.

10.3 Responsibilities for Underground Utilities: ................................................................................................................. 00700 - 20

10.4 Hazardous Material Conditions: ................................................................................................................................. 00700 - 20

10.5 Incidents with Archaeological Features: .................................................................................................................... 00700 - 20

10.6 Unit Price Work: ......................................................................................................................................................... 00700 - 21

10.7 Cash Allowances; Provisionary Allowances: ............................................................................................................. 00700 - 21

10.8 Change Orders; Change Authorizations: ................................................................................................................... 00700 - 21

ARTICLE 11 CHANGES IN CONTRACT PRICE; CHANGES IN

CONTRACT TIME ......................................................................................................................................... 00700 - 22

11.1 General Provisions: ................................................................................................................................................... 00700 - 22

11.2 Changes in Contract Time: ........................................................................................................................................ 00700 - 22

11.3 Methods for Making Adjustments in Contract Price: ................................................................................................. 00700 - 22.

11.4 Labor, Subcontract and Material/Equipment Costs: .................................................................................................. 00700 - 23

11.5 Construction Equipment Costs: ................................................................................................................................. 00700 - 23

11.6 Rented or Leased Construction Equipment: .............................................................................................................. 00700 - 23

11.7 Owned Construction Equipment: ............................................................................................................................... 00700 - 24

11.8 General Conditions Costs: ......................................................................................................................................... 00700 - 24

11.9 Limitations on Allowable Costs: ................................................................................................................................. 00700 - 24

11.10 Costs Covered by the Fee for the Work Involved (and not Allowable as Cost of the Work Involved): ....................... 00700 - 24.

11.11 Limits on the Fee for the Work Involved: ................................................................................................................... 00700 - 25.

11.12 Fee for Unabsorbed Home Office Overhead: ............................................................................................................. 00700 - 25

11.13 Changes in Contract Time for Early Completion: ........................................................................................................ 00700 - 25

11.14 Access to Records: ..................................................................................................................................................... 00700 - 26

11.15 Price Reduction for Defective Cost and Pricing Data: ................................................................................................ 00700 - 26

ARTICLE 12 PROGRESS PAYMENTS; FINAL PAYMENT ............................................................................................... 00700 - 26

12.1. Schedule of Values: ................................................................................................................................................... 00700 - 26

12.2 Requests for Payment: .............................................................................................................................................. 00700 - 27

12.3 Review of Request for Payment; Intent of Review: .................................................................................................... 00700 - 27

12.4 Refusal to Make or to Recommend Payment: .......................................................................................................... 00700 - 27.

12.5 Final Request for Payment: ....................................................................................................................................... 00700 - 27

12.6 Final Payment and Acceptance: ................................................................................................................................ 00700 - 28

12.7 Contractor’s Continuing Obligation: ......................................................................................................................... 00700 - 28

12.8 Waiver of Claims: ...................................................................................................................................................... 00700 - 28

ARTICLE 13 OTHER WORK .............................................................................................................................................. 00700 - 28

13.1 Related Work at Site: ................................................................................................................................................. 00700 - 28

13.2 Coordination Requirements: ...................................................................................................................................... 00700 - 29

13.3 Claims Between the Contractor and Other Parties: ................................................................................................. 00700 - 29

MICHSPEC DTMB 00010 − 4 (Rev. 02/22)

ARTICLE 14 TERMINATION .............................................................................................................................................. 00700 - 29

14.1 Notice Requiring Assurance of Due Performance: ................................................................................................... 00700 - 29.

14.2 Contractor Default and Termination for Cause: ........................................................................................................ 00700 - 30

14.3 Surety Default: ........................................................................................................................................................... 00700 - 31

14.4 Termination for Convenience of the Owner: .............................................................................................................. 00700 - 31

14.5 The Contractor May Suspend Work: ...................................................................................................................... 00700 – 31.

ARTICLE 15 DISPUTES .................................................................................................................................................... 00700 - 31

15.1 Claims Under This Article: ......................................................................................................................................... 00700 - 31

15.2 Requirement for Certification of Contractor Claims: ................................................................................................. 00700 - 32

15.3 Recommendations or Decisions from the Professional:........................................................................................... 00700 - 32

15.4 Determinations by the Director-DCD: ....................................................................................................................... 00700 - 32

15.5 Supplements to AAA Arbitration: ............................................................................................................................... 00700 - 33

15.6 Interest on a Judgment; Payment of Judgment: ........................................................................................................ 00700 - 33

15.7 Venue; Flow-Through Provision: ............................................................................................................................... 00700 - 33

SECTION 00800 SUPPLEMENTARY CONDITIONS ....................................................................................................... 00800 - 1

DIVISION 01000 GENERAL REQUIREMENTS PROVIDED BY PSC

SECTION 01310 PROGRESS SCHEDULE ...................................................................................................................... 01310 - 1

DIVISION 03 — CONCRETE

03 3000 - CAST-IN-PLACE CONCRETE

03 3543 - POLISHED CONCRETE FINISHING

03 4100 - PRECAST STRUCTURAL CONCRETE

03 4500 - PRECAST ARCHITECTURAL CONCRETE sf0

03 6000 - POST INSTALLED ANCHORS

DIVISION 04 — MASONRY

04 2000 - UNIT MASONRY

04 4200 - EXTERIOR STONE CLADDING

DIVISION 05 — METALS

05 1200 - STRUCTURAL STEEL FRAMING

05 3100 - STEEL DECKING

05 4000 - COLD-FORMED METAL FRAMING sf0 05 7300 - DECORATIVE METAL RAILINGS sf0

DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES

06 1000 - ROUGH CARPENTRY sf0

06 1053 - MISCELLANEOUS CARPENTRY

06 1533 - WOOD PATIO DECKING

06 2013 - EXTERIOR FINISH CARPENTRY

06 4013 - EXTERIOR ARCHITECTURAL WOODWORK

06 4023 - INTERIOR ARCHITECTURAL WOODWORK

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

07 1900 - WATER REPELLENTS

07 2100 - THERMAL INSULATION

MICHSPEC DTMB 00010 − 5 (Rev. 02/22)

07 2500 - WEATHER BARRIERS

07 4113.16 - STANDING-SEAM METAL ROOF PANELS

07 6200 - SHEET METAL FLASHING AND TRIM

07 7200 - ROOF ACCESSORIES

07 7253 - SNOW GUARDS

07 9200 - JOINT SEALANTS

DIVISION 08 — OPENINGS

08 1116 - ALUMINUM DOORS AND FRAMES

08 1216 - ALUMINUM FRAMES

08 1416 - FLUSH WOOD DOORS

08 1743 - RUSTIC WOOD GRAIN FRP ALUMINUM HYBRID DOOR Original

08 3113 - ACCESS DOORS AND FRAMES

08 4113 - ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS sf0

08 5113 - ALUMINUM WINDOWS

08 7100 - DOOR HARDWARE

08 8000 - GLAZING

08 8300 - MIRRORS

08 9119 - FIXED LOUVERS

DIVISION 09 — FINISHES

09 0561.13 - MOISTURE VAPOR EMISSION CONTROL

09 2216 - NON-STRUCTURAL METAL FRAMING

09 3000 - TILING

09 5000 - ACOUSTICAL METAL CEILINGS

09 5426 - SUSPENDED WOOD CEILINGS

09 9300 - STAINING AND TRANSPARENT FINISHING sf1

09 9400 - WATER & OIL REPELLENT

DIVISION 10 — SPECIALTIES

10 1419 - DIMENSIONAL LETTER SIGNAGE

10 2113.17 - PHENOLIC-CORE TOILET COMPARTMENTS sf1

10 2800 - TOILET, BATH, AND LAUNDRY ACCESSORIES

10 4416 - FIRE EXTINGUISHERS

DIVISION 12 — FURNISHINGS

12 9300 - Site Furnishings

DIVISION 22 — PLUMBING

22 0500 - COMMON WORK RESULTS FOR PLUMBING

22 0513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

22 0519 - METERS AND GAGES FOR PLUMBING PIPING

22 0523 - GENERAL DUTY VALVES FOR PLUMBING PIPING (2 and smaller)

22 0529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 0553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22 0700 - PLUMBING INSULATION

22 1116 - DOMESTIC WATER PIPING

MICHSPEC DTMB 00010 − 6 (Rev. 02/22)

22 1119 - DOMESTIC WATER PIPING SPECIALTIES

22 1123 - DOMESTIC WATER PUMPS

22 1313 - FACILITY SANITARY SEWERS

22 1316 - SANITARY WASTE AND VENT PIPING

22 1319 - SANITARY WASTE PIPING SPECIALTIES

22 1329 - SANITARY SEWERAGE PUMPS

22 1413 - FACILITY STORM DRAINAGE PIPING

22 3300 - ELECTRIC DOMESTIC WATER HEATERS

22 4000 - PLUMBING FIXTURES

DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING

23 0500 - COMMON WORK RESULTS FOR HVAC

23 0513 - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

23 0529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

23 0553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 0593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 0700 - HVAC INSULATION

23 2300 - REFRIGERANT PIPING

23 3113 - METAL DUCTS

23 3300 - AIR DUCT ACCESSORIES

23 3713 - DIFFUSERS, REGISTERS, AND GRILLES

23 7200 - AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Renewaire)

23 8143 - VARIABLE REFRIGERANT FLOW HEAT PUMPS

DIVISION 26 — ELECTRICAL

26 0500 - COMMON WORK RESULTS FOR ELECTRICAL

26 0519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 0533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 0543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

26 0544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 0800 - COMMISSIONING OF ELECTRICAL

26 0923 - LIGHTING CONTROL DEVICES

26 2416 - PANELBOARDS

26 2726 - WIRING DEVICES

26 4313 - SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

26 5100 - INTERIOR LIGHTING

26 5600 - EXTERIOR LIGHTING

DIVISION 31 — EARTHWORK

31 1000 - Site Clearing 31 2000 - Earth Moving

DIVISION 32 — EXTERIOR IMPROVEMENTS

32 1216 - Asphalt Paving 32 1313 - Concrete Paving

MICHSPEC DTMB 00010 − 7 (Rev. 02/22)

32 9200 - Turf and Grasses 32 9300 - Plants

DIVISION 33 — UTILITIES

33 4100 - Storm Drainage 33 4300 - Sanitary Sewers 33 4400 - Water Distribution Piping

DRAWINGS

MICHSPEC DTMB 00010 − 8 (Rev. 02/22)

STATE OF MICHIGAN (OWNER AND CONTRACTOR) GLOSSARY

MICHSPEC DTMB 00020 - 1 (Rev. 02/22)

SECTION 00020 GLOSSARY

1.1 Defined Terms:

1.1.1. The following terms or relative pronouns used in

Division 0 of the Specifications have these intent and meanings:

Activity− An element in the Progress Schedule establishing a requisite step, or the time and resources required, for completing the part of the Work associated with that Activity.

Addenda− Written instruments that are used by the Owner and/or Professional to incorporate interpretations or clarifications, modifications, and other information into the Bidding Documents. An Addendum issued after Bid opening to those Bidders who submitted a Bid, for the purpose of rebidding the Work without readvertising, is referred to as a post-Bid Addendum.

Agreement− The written agreement between the Owner and Contractor covering the Work to be furnished and performed.

Alternate− Refers to Work specified in the Bidding Documents for which the Bidder shall bid a Bid Price in the space provided in the Schedule of Alternates in Section 00300 Bid Form.

Apparent Low Bidder:- Those Bidders whose Base Bid, when added to those specific Alternates the Owner intends to accept, yields the three lowest sums of Base Bid and Alternates. Additional Bidders may be considered Apparent Low Bidders if their Base Bid, when added to those specific Alternates the Owner intends to accept, yields a sum within 10% of the lowest of the Apparent Low Bidder’s sum. If a qualified disabled veteran meets the requirements of the contract solicitation and with the veteran’s preference is the lowest Bidder is considered the Apparent Low Bidder.

Archaeological Feature− Any prehistoric or historic deposit of archaeological value, as determined by a representative of a State agency that is duly authorized to evaluate such findings and render such judgments. An Archaeological Feature deposit may include, but is not limited to Indian habitations, ceremonial sites, abandoned settlements, treasure trove, artifacts, or other objects with intrinsic archaeological value and that relate to the history and culture of the State of Michigan.

As-Planned Schedule− The Contractor’s Revision 0 Progress Schedule returned to the Contractor as "Resubmittal Not Required," with or without comments or objections noted.

Authorized Technical Data− Information and data contained in a report of exploration and tests of subsurface conditions that are expressly designated in paragraph 2.0 of Section 00210 Information for Bidders. Also, any physical data (dimension, location, conditions, etc.) contained in those drawings of physical conditions of existing surface and subsurface facilities identified in paragraph 3.0 of Section 00210 Information for Bidders.

Bar Chart Schedule− Activity schedule, in a bar chart format, that accounts for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.

STATE OF MICHIGAN MODEL

Developed from FORMSPEC Michigan Model.

Bid− Written offer by a Bidder for the Work, as specified, which designates the Bidder’s Base Bid and Bid Prices for all Alternates. The term Bid includes a Rebid.

Bidder− The Person acting directly, or through an authorized representative, who submits a Bid directly to the Owner.

Bidding Documents− The proposed Contract Documents as advertised, and all Addenda issued before Bid opening, and after Bid opening, if the Work is rebid without readvertising.

Bid Price− The Bidder's price for a lump sum item of Work, or the product of the Bidder's unit price for an item of Unit Price Work times the quantity given on the Bid Form for that item.

Bid Security− A security serving as a guarantee that the Bidder will conform to all conditions requisite for its return or as liquidated damages in the event of failure or refusal to conform.

Bidding Requirements− The Advertisement, Instructions to Bidders (including Attachment A), Supplementary Instructions, Information for Bidders, Bid Form, Bid Form Attachments and Qualification Submittals, as advertised and as modified by Addenda, and any other Section included within Division 0 of the Bidding Documents for the purpose of governing bidding and award of the Contract.

*AD Board− The Administrative Board of the State of Michigan.

Bonds− Section 00310 Bid Bond, Section 00610 Performance Bond and Section 00620 Payment Bond are security furnished by the Contractor, as required by the Contract Documents.

Business Day− Any Day except Saturdays, Sundays and holidays observed by the Owner.

Bulletin− A standard DTMB or other PSC form used by the PSC & Owner to describe a change in the Work under consideration by the Owner and to request the Contractor to submit a proposal for the corresponding adjustment in Contract Price and/or Contract Time, if any.

Calendar Day− Every day shown on the calendar, Saturdays, Sundays, and holidays included.

Cash Allowance− An Owner-specified sum included within the Contract Price to reimburse the Contractor for the actual purchase/furnished cost of materials and/or equipment or other designated items, as specifically provided in the Contract Documents. Although the scope (e.g., the required quantity) of any Work covered by a Cash Allowance is sufficiently

MICHSPEC DTMB 00020 - 2 (Rev. 02/22) detailed in the Contract Documents for the purposes of bidding the required labor costs, Subcontract costs, construction equipment costs and general conditions costs and Fee, it is understood that the required materials, equipment or other designated items are of uncertain purchase cost at the time of Bid or are yet to be specified in more detail by the Professional as to quality, appearance, durability, finish and such other necessary features affecting purchase price.

Change Authorization− A written order issued and signed by the Professional, which directs changes in the Work that require no adjustment in Contract Price or Contract Time, or which allows for variations in the quantities of Unit Price Work.

Change Order− A written order issued and signed by the Owner, which amends the Contract Documents for changes in the Work or an adjustment in Contract Price and/or Contract Time, or both.

Contact Person− Individual in the employ of the Professional or the Owner who is designated as the sole point of contact for prospective Bidders for requests or inquiries concerning the Work and/or the Bidding Documents.

Contract− Refer to the definition in paragraph 1.1 of Section 00500 Agreement. The term “Contract” encompasses the legal obligations of the Owner and Contractor, as defined by the Contract Documents.

Contract Award− The official action of the Board, the Director-SFA or the Director-DCD awarding the Contract to the Contractor.

Contract Documents− Those documents itemized or designated in paragraphs 2.2 through 2.4 of Section 00500 Agreement.

Contract Float− Calendar Days between the Contractor's anticipated date for early completion of the Work, or of a specified portion of the Work, if any, and the corresponding Contract Time.

Contract Price− The Contract price for the Work, or a designated portion of the Work, as designated in Section 00500 Agreement or elsewhere in the Contract Documents, is the total compensation, including authorized adjustments, payable by the Owner to the Contractor (subject to provisions for Unit Price Work).

Contract Times− The Contract Times for the entire Work are the periods allowed, including authorized adjustments, for Substantial Completion and final completion of the Work. The Contract Times for a designated portion of the Work are the periods allowed for Substantial Completion and final completion of any such portion of the Work, as specified in the Contract Documents.

Contractor− Person named "the Contractor" in Section 00500 Agreement with whom the Owner has entered into the Contract.

Correction Period− The period during which the Contractor shall, in accordance with the Contract Documents, (a) correct or, if rejected, remove, and replace Defective Work, and (b) maintain warranties for materials and equipment in full force and effect.

Cost of the Work Involved− The sum of all costs that would be, or were, necessarily incurred by the Contractor in providing any Work Involved with the related change, less the costs that would be, or would have been, incurred by the Contractor to provide such Work without the related change.

CPM Schedule− Computerized, Activity-based Progress Schedule, using Critical Path Method (CPM) techniques, and accounting for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.

Critical Path Method (CPM)− The Critical Path Method of planning and scheduling. The term “Critical Path” denotes a sequence of Activities controlling achievement of a specified Contract Time.

Date of Commencement of the Contract Time− The date when the Contract Time starts to run.

Defective− An adjective which when referring to or when applied to the term “Work” refers to (a) Work not conforming to the Contract Documents or not meeting the requirements of any inspection, test, or approval, or (b) Work itemized in a Punch List which the Contractor fails to complete or correct within a reasonable time after issuance of the Punch List by the Professional.

Defective Work/Non-Compliance Notice – A DTMB-0499 form or equivalent issued to identify defective or non-compliant conditions requiring response and remedy by the Contractor.

Delay− Any act or omission or other event that in any manner adversely affects or alters the schedule, progress or completion of all or any part of the Work. Delay is a generic term intended to include deferral, stoppage, slow down, interruption and extended performance, and all related hindrance, rescheduling, disruption, interference, inefficiency and productivity and production losses.

*Department (DTMB)− Department of Technology, Management and Budget of the State of Michigan. Director is the Director of the Department.

Director-SFA- The Director of DTMB State Facilities Administration.

Director-DCD- The Director of DTMB State Facilities Administration, Design and Construction Division

Division− Each of the numbered, distinct parts (starting with Division 0) into which the Specifications are divided.

Drawings− Part of the Contract Documents showing the Work.

Drawings shall neither serve nor be used as Shop Drawings.

Early (Late) Dates− Early (late) times of performance for the Activities.

MICHSPEC DTMB 00020 - 3 (Rev. 02/22)

Emergency− A condition affecting the safety or protection of persons, or the Work, or property at or adjacent to the site.

Fee for the Work Involved (Fee)− A negotiated, percentage mark-up on the Cost of the Work Involved which is allowed to the Contractor for (a) reasonable administrative costs, and (b) negotiated, reasonable profit on the Cost of the Work Involved.

General Requirements− Division 1 of the Specifications.

Hazardous Material− Asbestos, ACBMs, PCBs, petroleum products, such construction materials as paint thinners, solvents, gasoline, oil, etc., and any other like material the manufacture, use, treatment, storage, transportation, or disposal of which is regulated by federal, State, or local Laws governing the protection of public health, natural resources, or the environment.

State Facilities Administration- Entity in the Department of Technology, Management and Budget responsible for design, construction, and operations and maintenance of facilities and capital renewal.

State Facilities Administration Representative- Designated DTMB-SFA Design and Construction Division Project Director (a) Responsible for directing and supervising the Professional’s services during the period allowed for completion of the Work; and/or (b) Acting as representative for the Owner and for the enforcement of the Contract Documents, approving payment to the Contractor and coordinating the activities of the State, Owner, Professional and Contractor.

Law(s)− Means federal, state, and local statutes, ordinances, orders, rules and/or regulations.

MCL− The Michigan Compiled Laws of the State of Michigan.

Means and Methods− Includes means, methods, techniques, sequences and/or procedures applicable to the Work.

Notice of Award− Written notice accepting the Bid to the lowest responsive, responsible Bidder and designating the Contract Price (and establishing the Alternates accepted…