0200000 – Management and Administration
SECTION F: DELIVERIES OR PERFORMANCE
Section F – 0200000 Management and Administration
DELIVERABLES
| Annex/ Spec Item |
| Form Attachment Number |
| Deliverable Title |
| Date (s) of Submission |
| Distribution |
| Frequency |
| Original |
| Copies (including original) |
0200000/ 2.2.1.2
| N/A |
| Request to Work Outside Government’s Regular Working Hours |
| At least seven calendar days prior to requested day. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.3.1
| N/A |
| Sign-In Sheets and Minutes |
| Within two working days. |
| KO, COR and all attendees |
| 1 |
| As required |
0200000/ 2.3.1
| N/A |
| Final Revision of Minutes |
| Within two working days. |
| KO, COR and all attendees |
| 1 |
| As required |
0200000/ 2.3.4
| N/A |
| Permits and Licenses |
| Before work commences and as requested by the KO. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.3.5
| N/A |
| Certificate of Insurance |
| At least 30 calendar days prior to start of contract performance. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.6.7.1
| N/A |
| Quality Management Plan |
| At least 30 calendar days prior to start of contract performance and within 15 calendar days prior to any changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.6.7.2
| N/A |
| QC Inspection File |
| Within five calendar days of completion/ termination of the contract. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.6.7.3
| N/A |
| Contractor Quality Inspection and Surveillance Report |
| First work day of each month. |
| KO and COR |
| 1 |
| Monthly |
0200000/ 2.6.8
| N/A |
| Property Management Plan |
| At least 30 calendar days prior to start of contract performance. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.7.1
| N/A |
| List of Key Personnel and Qualifications |
| At least 30 calendar days prior to start of contract performance. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.7.1
| N/A |
| Organizational Chart |
| At least 15 calendar days prior to start of contract performance. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.7.2.6
| N/A |
| Proof of Legal Residency |
| Prior to be admitted to site of work. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.7.3
| N/A |
| Contractor Labor Hours (eCMRA) Report |
| No later than 31 October. |
| KO and COR |
| 1 |
| Annually for labor executed during the period of performance during each Government fiscal year (FY) |
0200000/ 2.8.1
| N/A |
| Employee List |
| Upon request. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.8.8
| N/A |
| Personnel Security Investigation (PSI), Fingerprint Card (FD87), and OF-306 Declaration for Federal Employment |
| Prior to employee access to sensitive unclassified information. |
| KO, COR, and |
Security Manager
| 1 |
| As required |
0200000/ 2.9.1
| N/A |
| Accident Prevention Plan |
| At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.9.2
| N/A |
| Activity Hazard Analysis |
| Together with the Accident Prevention Plan and for changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.9.3
| N/A |
| Compliance Plans, Programs, and Procedures |
| Together with the Accident Prevention Plan and for changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.9.3.5
| N/A |
| Asbestos Abatement Plan |
| Together with the Accident Prevention Plan and for changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.9.5
| N/A |
| NAVFAC Contractor Incident Reporting System (CIRS) |
| Within five calendar days of accident. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.9.5
| N/A |
| Weight Handling Equipment Accident Report |
| Within 15 working days of accident. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.9.5
| N/A |
| Crane and Rigging Gear Near Miss Report |
| Within 15 working days of accident. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.9.7
| N/A |
| Monthly On-Site Labor Report |
| First work day of each month. |
| KO and COR |
| 1 |
| Monthly |
0200000/ 2.9.8
| N/A |
| OSHA Citations and Violations Corrective Action Report |
| Within 48 hours after receiving a citation. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.9.10
| N/A |
| Safety Certifications |
| At least 15 calendar days prior to start of contract performance and prior to expiration of certifications. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.10.1.1
| N/A |
| Water Conservation Plan |
| At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes. |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.10.2.1
| N/A |
| Written Sampling Plan |
| Prior to each sampling event |
| KO and COR |
| 1 |
| As required |
0200000/ 2.10.2.1
| N/A |
| Sampling Results |
| Within 24 hours after receipt of laboratory analysis |
| KO and COR |
| 1 |
| As required |
0200000/ 2.10.2.2
| N/A |
| Class I and II ODS Report |
| Within 24 hours following delivery of refrigerant to DLA |
| KO and COR |
| 1 |
| As required |
0200000/ 2.10.2.3
| N/A |
| Solid Waste Management Reports |
| Within three months after start of contract performance and annually by October 10th thereafter |
| KO and COR |
| 1 |
| As specified |
0200000/ 2.10.2.3
| N/A |
| Recycling Weight Ticket Receipts |
| As Specified |
| KO and COR |
| 2 |
| Quarterly |
0200000/ 2.10.2.5
| N/A |
| Waste Stream Determination |
| At least 30 calendar days prior to start of contract performance and within 14 days of identification of any new waste stream. |
| KO and COR |
| 1 |
| As required |
0200000/ 2.10.2.7
| N/A |
| Spill Report |
| Within 48 hours of spill occurrence |
| KO and COR |
| 1 |
| As required |
| 0200000/ 2.10.2.8 |
| N/A |
| Emergency Planning and Community Right-To-Know Act (EPCRA) Report |
| At least 15 calendar days prior to start of contract performance and not less than 10 working days prior to planned use of hazardous material. |
| KO and COR |
| 2 |
| As specified |
| 0200000/ 2.10.2.8 |
| J-0200000-06 |
| Contractor Hazardous Material Inventory Log |
| Within 15 calendar days after the end of each calendar year and at termination of the contract. |
| KO and COR |
| 2 |
| Annually |
0200000/ 2.10.2.12
| N/A |
| Asbestos Containing Material (ACM) |
| Written notification within 24 hours of discovery |
| KO and COR |
| 2 |
| As specified |
0200000/ 2.10.2.13
| J-0200000-07 |
| Hazardous Air Pollutant (HAP) Monthly Data |
| First work day of each month. |
| KO and COR |
| 1 |
| Monthly |
0200000/ 2.10.2.13
| J-0200000-07 |
| Hazardous Air Pollutant (HAP) Semi-annual Report |
| Semi-annually by July 10th and January 10th |
| KO and COR |
| 1 |
| Semi-Annually |
0200000/ 2.10.3
| N/A |
| Sustainable Procurement and Practices Plan |
| At least 15 calendar days prior to start of contract performance and within 15 calendar days after exercised option periods. |
| KO and COR |
| 1 |
| Annually |
0200000/ 2.10.3
| N/A |
| Sustainable Delivery of Services Report |
| Within five calendar days after each contract period. |
| KO and COR |
| 1 |
| Annually |
0200000/ 2.10.3.2
| N/A |
| Recovered Material Certification |
| As specified |
| KO and COR |
| 1 |
| When a product containing recovered materials is equal to or better than the original and could be used. |
0200000/ 2.14.1
| N/A |
| Detailed Scope of Work and Detailed Estimate |
| Within two work days |
| KO and COR |
| 2 |
| As required |
0200000/ 2.15.2.1
| N/A |
| Non-Recurring Work Proposals |
| Within two working days following receipt of request |
| KO and COR |
| 1 |
| As required |
0200000/ 2.15.1.1
| N/A |
| Non-Recurring Work Quantities Ordered via FedMall |
| First work day of each month. |
| KO and COR |
| 1 |
| Monthly |